4. The partially completed MPS for a product is given below. Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Week Quantity on Hand: 400 3 4 6 8 9 10 Forecast 550 300 400 450 300 350 200 300 450 400 Customer orders 300 350 250 250 200 150 100 100 100 100 (booked) Projected on-hand inventory MPS quantity 500 MPS start Available-to- promise (ATP) inventory a. Develop the MPS for the product. b. Four customer orders arrived in the following sequence. As they arrive, you must decide whether to accept or reject them. Which orders would you accept for shipment? Why? 7, 2.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
4. The partially completed MPS for a product is given below.
Item: Ball bearings
Order Policy: 500 units
Lead Time: 1 week
Week
Quantity
on Hand:
5 6 7
400
3
4
8
10
Forecast
550
300
400
450
300
350
200
300
450
400
Customer
orders
300
350
250
250
200
150
100
100
100
100
(booked)
Projected
on-hand
inventory
MPS quantity
500
MPS start
Available-to-
promise (ATP)
inventory
a. Develop the MPS for the product.
b. Four customer orders arrived in the following sequence. As they arrive, you must decide
whether to accept or reject them. Which orders would you accept for shipment? Why?
Transcribed Image Text:4. The partially completed MPS for a product is given below. Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Week Quantity on Hand: 5 6 7 400 3 4 8 10 Forecast 550 300 400 450 300 350 200 300 450 400 Customer orders 300 350 250 250 200 150 100 100 100 100 (booked) Projected on-hand inventory MPS quantity 500 MPS start Available-to- promise (ATP) inventory a. Develop the MPS for the product. b. Four customer orders arrived in the following sequence. As they arrive, you must decide whether to accept or reject them. Which orders would you accept for shipment? Why?
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.