2. The sedimentation portion of the in-line treatment plant is to be designed. The proposed design for the sedimentation tank is 130 ft wide, 180 ft long, and 12ft in depth. The length of the effluent weir along the four channels at the end of the tank is 1160ft. Calculate the major parameters used in sizing this unit based on the design flow of 42 mgd. Determine (a) detention time (b).Over flowrate or velocity of effluent water; (c) Weir Loading; (d) Overflow rate.
2. The sedimentation portion of the in-line treatment plant is to be designed. The proposed design for the sedimentation tank is 130 ft wide, 180 ft long, and 12ft in depth. The length of the effluent weir along the four channels at the end of the tank is 1160ft. Calculate the major parameters used in sizing this unit based on the design flow of 42 mgd. Determine (a) detention time (b).Over flowrate or velocity of effluent water; (c) Weir Loading; (d) Overflow rate.
Fundamentals of Geotechnical Engineering (MindTap Course List)
5th Edition
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter7: Seepage
Section: Chapter Questions
Problem 7.6P
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning