1. You are required to prepare a network diagram for constructing a 5 floor apartmer The major activities of the project are given as follows: Activity Description Immediate Predecessor A Selection of site B Preparation of drawings с Arranging the for finance A D Selection of contractor A E Getting approval from Govt A F Laying the foundation E G Start construction D, F H Advertise in newspaper B, C I Allocation of tenants G, H 2. For the problem No.1 the time estimates in days are given. Determine the Time earliest and Time latest, and the critical activities Activity A B с Ꭰ E F GH I Time (days) 3 5 7 2 5 20 60 2 10
1. You are required to prepare a network diagram for constructing a 5 floor apartmer The major activities of the project are given as follows: Activity Description Immediate Predecessor A Selection of site B Preparation of drawings с Arranging the for finance A D Selection of contractor A E Getting approval from Govt A F Laying the foundation E G Start construction D, F H Advertise in newspaper B, C I Allocation of tenants G, H 2. For the problem No.1 the time estimates in days are given. Determine the Time earliest and Time latest, and the critical activities Activity A B с Ꭰ E F GH I Time (days) 3 5 7 2 5 20 60 2 10
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter14: Pricing General Expenses
Section: Chapter Questions
Problem 4RQ
Related questions
Question

Transcribed Image Text:1.
You are required to prepare a network diagram for constructing a 5 floor apartmer
The major activities of the project are given as follows:
Activity
Description
Immediate Predecessor
A
Selection of site
B
Preparation of drawings
с
Arranging the for finance
A
D
Selection of contractor
A
E
Getting approval from Govt
A
F
Laying the foundation
E
G
Start construction
D, F
H
Advertise in newspaper
B, C
I
Allocation of tenants
G, H
2.
For the problem No.1 the time estimates in days are given. Determine the Time
earliest and Time latest, and the critical activities
Activity
A
B с
Ꭰ
E
F
GH
I
Time (days)
3
5
2
5
20
60
2
10
7
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you

Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,

Architectural Drafting and Design (MindTap Course…
Civil Engineering
ISBN:
9781285165738
Author:
Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:
Cengage Learning

Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning

Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,

Architectural Drafting and Design (MindTap Course…
Civil Engineering
ISBN:
9781285165738
Author:
Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:
Cengage Learning

Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning

Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning

Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781285852225
Author:
Gregory W Fletcher
Publisher:
Cengage Learning

Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning