1. An excavation is to be made for a footing 1.5 m x 1.5 m. However during the excavation you encountered the water table as shown the depth of excavation to be is 2m from the surface but the ground water table is 1m from the surface. How will you be able to pour the concrete mix for the footing if ground water is continuously infiltrating into your excavation and filling up the pit with water. Draw each stage of the excavation up to finishing up the footing with a short explanation for each drawing, include stage of placing formworks and rebar as well as other process to ensure that additional ground water will not mix with your newly poured concrete. Imagine you are already an engineer trying to illustrate to your client or your workers how will you make the footing (the photo shown is just 1m excavation you still have 1m more to excavate) Ground water table level

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
1. An excavation is to be made for a footing 1.5 m x 1.5 m. However during the excavation you
encountered the water table as shown the depth of excavation to be is 2m from the surface but
the ground water table is 1m from the surface.
How will you be able to pour the concrete mix for the footing if ground water is
continuously infiltrating into your excavation and filling up the pit with water. Draw each
stage of the excavation up to finishing up the footing with a short explanation for each
drawing, include stage of placing formworks and rebar as well as other process to ensure
that additional ground water will not mix with your newly poured concrete. Imagine you are
already an engineer trying to illustrate to your client or your workers how will you make the
footing (the photo shown is just 1m excavation you still have 1m more to excavate)
Ground water
table level
Transcribed Image Text:1. An excavation is to be made for a footing 1.5 m x 1.5 m. However during the excavation you encountered the water table as shown the depth of excavation to be is 2m from the surface but the ground water table is 1m from the surface. How will you be able to pour the concrete mix for the footing if ground water is continuously infiltrating into your excavation and filling up the pit with water. Draw each stage of the excavation up to finishing up the footing with a short explanation for each drawing, include stage of placing formworks and rebar as well as other process to ensure that additional ground water will not mix with your newly poured concrete. Imagine you are already an engineer trying to illustrate to your client or your workers how will you make the footing (the photo shown is just 1m excavation you still have 1m more to excavate) Ground water table level
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning