1. Activities of a project are summarized in the following table. Activity Immediate Duration Activity Immediate Duration Predecessor(s) (Weeks) Predecessor(s) (Weeks) A 4. F C,E B G C,E 3 C.D. E C. D, E G, H 2 H D. в 5 в 3 a) Draw a network diagram and find the critical path and project completion time. b) Calculate float/ slack of the all activities. c) Can activity I be delayed without delaying the project completion time? If so, how many weeks? d) Activity G needs a delayed time of two weeks and an extra time of one week. Is it possible by keeping the pa completion time unchanged? Explain. e) The PM wants to shorten the duration of the activity E from 3 weeks to I week. What is the impact of this change o project completion time?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Sub:Engineering Management
1. Activities of a project are summarized in the following table.
Duration
(Weeks)
Immediate
Predecessor(s)
Activity
Immediate
Activity
Duration
Predecessor(s)
(Weeks)
A
F
C,E
C, E
C, D, E
C. D. E
B
G
3
7.
D.
B
2.
E
B
3
G, H
6
a) Draw a network diagram and find the critical path and project completion time.
b) Calculate float/ slack of the all activities.
c) Can activity I be delayed without delaying the project completion time? If so, how many weeks?
d) Activity G needs a delayed time of two weeks and an extra time of one week. Is it possible by keeping the project
completion time unchanged? Explain.
e) The PM wants to shorten the duration of the activity E from 3 weeks to 1 week. What is the impact of this change on the
project completion time?
Transcribed Image Text:1. Activities of a project are summarized in the following table. Duration (Weeks) Immediate Predecessor(s) Activity Immediate Activity Duration Predecessor(s) (Weeks) A F C,E C, E C, D, E C. D. E B G 3 7. D. B 2. E B 3 G, H 6 a) Draw a network diagram and find the critical path and project completion time. b) Calculate float/ slack of the all activities. c) Can activity I be delayed without delaying the project completion time? If so, how many weeks? d) Activity G needs a delayed time of two weeks and an extra time of one week. Is it possible by keeping the project completion time unchanged? Explain. e) The PM wants to shorten the duration of the activity E from 3 weeks to 1 week. What is the impact of this change on the project completion time?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Product and Service development
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.