1) Draw and AOA diagram. ) Identifying due time of the critical path :) Compute for te, Path total, , total time duration of the critical Path 1) Compute for z value, the Pz (Normal standard distribution) and plot in a graph and the expected time for

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%
Consider a project having the following ten activities:
Optimistic
Time (o)
(weeks)
Most likely Pessimistic
Time (p)
(weeks).
9
Time (m)
(weeks)
5
Immediate
Time
Est.
Activity
A
Predecessors
none
1
B
A
6
5
C
A
3
5
9
4
A
2
4
3
E
В, С
4
4
4
4
F
D
4
7
6
G
E
2
2
8
H
E, F
7
8
8
I
F
4
7
J
G, H, I
3
5
7
5
a) Draw and AOA diagram.
b) Identifying due time of the critical path
c) Compute for te, Path total, , total time duration of the critical Path
d) Compute for z value, the Pz (Normal standard distribution) and plot in a graph and the expected time for
each activity?
Transcribed Image Text:Consider a project having the following ten activities: Optimistic Time (o) (weeks) Most likely Pessimistic Time (p) (weeks). 9 Time (m) (weeks) 5 Immediate Time Est. Activity A Predecessors none 1 B A 6 5 C A 3 5 9 4 A 2 4 3 E В, С 4 4 4 4 F D 4 7 6 G E 2 2 8 H E, F 7 8 8 I F 4 7 J G, H, I 3 5 7 5 a) Draw and AOA diagram. b) Identifying due time of the critical path c) Compute for te, Path total, , total time duration of the critical Path d) Compute for z value, the Pz (Normal standard distribution) and plot in a graph and the expected time for each activity?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.