1) An operator is used for loading and unloading of parts to automated machines. Loading time is 1 minute; unloading time is 2 minutes, machining time is 30 minutes, Operator travel time between the machines including the inspection time is 4 minutes. Cost of operator is C₁=40 TL/Hour, cost of a machine is C₂-200 TL/Hour. What is the cost per unit of production if optimum number of machines is assigned to the operator? (Note: Times are given in minutes and costs are per hour) a) 231 TL/unit b) 6930 TL/unit c) 115.5 TL/unit d) 240 TL/unit e) 132 TL/unit 2) An operator is used for loading and unloading of parts to automated machines. Loading time is 1 minute; unloading time is 2 minutes, machining time is 30 minutes; Operator travel time between the machines including the inspection time is 4 minutes. Cost of operator is C1=40 TL/Hour; cost of a machine is C₂=200 TL/Hour. How many machines (integer number) should be assigned to the operator so that the total operator and machine costs per cycle are minimized? a) 3 b) 6 c) 4 d) 2 e) 5

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

1) An operator is used for loading and unloading of parts to automated machines. Loading time is 1 minute; unloading time is 2 minutes, machining time is 30 minutes, Operator travel time between the machines including the inspection time is 4 minutes. Cost of operator is C₁=40 TL/Hour, cost of a machine is C₂-200 TL/Hour. What is the cost per unit of production if optimum number of machines is assigned to the operator? (Note: Times are given in minutes and costs are per hour)

a) 231 TL/unit

b) 6930 TL/unit

c) 115.5 TL/unit

d) 240 TL/unit

e) 132 TL/unit

2) An operator is used for loading and unloading of parts to automated machines. Loading time is 1 minute; unloading time is 2 minutes, machining time is 30 minutes; Operator travel time between the machines including the inspection time is 4 minutes. Cost of operator is C1=40 TL/Hour; cost of a machine is C₂=200 TL/Hour. How many machines (integer number) should be assigned to the operator so that the total operator and machine costs per cycle are minimized?

a) 3

b) 6

c) 4

d) 2

e) 5

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Forecasting methods
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.