1) A list of activities, precedence relations, and optimistic, most likely, and pessimistic activity completion times for a project are as given below. Activity Name Predessor Activities Optimistic Most Likely Pessimistic A - 4 5 6 B A 3 4 8 C B 1 2 3 D A,C 3 6 8 E D 7 8 9 F E 4 5 7 G C 3 4 5 H D,E,G,I 12 13 15 I C 1 2 4 J G,H 1 1 1 K F,H,J 1 6 7 a) Draw an AOA network diagram for this project b) What is the expected competion time for each activity in the project? c) What is the variance associated with the expected completion time of each activity in the project? d) What is the critical path for the project? e) What is the expected completion time of the project? f) What is the variance of the expected completion time of the project?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

1) A list of activities, precedence relations, and optimistic, most likely, and pessimistic activity completion times for a project are as given below. Activity Name Predessor Activities Optimistic Most Likely Pessimistic A - 4 5 6 B A 3 4 8 C B 1 2 3 D A,C 3 6 8 E D 7 8 9 F E 4 5 7 G C 3 4 5 H D,E,G,I 12 13 15 I C 1 2 4 J G,H 1 1 1 K F,H,J 1 6 7 a) Draw an AOA network diagram for this project b) What is the expected competion time for each activity in the project? c) What is the variance associated with the expected completion time of each activity in the project? d) What is the critical path for the project? e) What is the expected completion time of the project? f) What is the variance of the expected completion time of the project? g) What is the probability that the project will be completed in 48 days, 45 days, and 42 days? 2) Using the data in problem 1), answer the following questions; use the most likely time as an estimate of the activity times in these questions. a) Draw an AON network diagram b) Compute the early start (ES), late start (LS), early finish (LF) and slack times of each activity in the network. c) What is the critical path? What is the expected completion time for the project?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.