. The following seven activities constitute an overall bar chart portrayal of a six-month project. Month 1 0.5 Activity Develop Project Charter Develop Work Plan Cost Month 2 Month 3 Month 4 Month 5 Month 6 $1,500 $8,000 0.5 0.5 Develop Specifications Design Framework $5,000 0.5 $15,000 Build the $11,500 0.5 Framework Test the Framework $2,000 0.5 Implement Framework $20,000 Note: 0.5 means half month Three months after the start of the project, activities develop project charter, develop work plan, develop specifications, 70% of design and 20% of building were completed for a cost of $28,500. Evaluate the status of the project. For this project, using earned value concepts determine the percent schedule variance, the percent cost variance, cost performance index, schedule performance index, the percentage completion, and estimate at completion. State if the project is over or under budget and if it is ahead or behind schedule. (show detail calculation)

Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
icon
Related questions
Question
. The following seven activities constitute an overall bar chart portrayal of a six-month project.
Month 1
0.5
Month 2
Month 3
Activity
Develop Project
Charter
Cost
Month 4
Month 5
Month 6
$1,500
Develop Work
Plan
$8,000
0.5
0.5
Develop
Specifications
Design
Framework
$5,000
0.5
$15,000
Build the
$11,500
0.5
Framework
Test the
Framework
$2,000
0.5
Implement
Framework
$20,000
Note: 0.5 means half month
Three months after the start of the project, activities develop project charter, develop work
plan, develop specifications, 70% of design and 20% of building were completed for a cost
of $28,500. Evaluate the status of the project. For this project, using earned value concepts
determine the percent schedule variance, the percent cost varjance, cost performance index,
schedule performance index, the percentage completion, and estimate at completion. State if
the project is over or under budget and if it is ahead or behind schedule. (show detail
calculation)
Transcribed Image Text:. The following seven activities constitute an overall bar chart portrayal of a six-month project. Month 1 0.5 Month 2 Month 3 Activity Develop Project Charter Cost Month 4 Month 5 Month 6 $1,500 Develop Work Plan $8,000 0.5 0.5 Develop Specifications Design Framework $5,000 0.5 $15,000 Build the $11,500 0.5 Framework Test the Framework $2,000 0.5 Implement Framework $20,000 Note: 0.5 means half month Three months after the start of the project, activities develop project charter, develop work plan, develop specifications, 70% of design and 20% of building were completed for a cost of $28,500. Evaluate the status of the project. For this project, using earned value concepts determine the percent schedule variance, the percent cost varjance, cost performance index, schedule performance index, the percentage completion, and estimate at completion. State if the project is over or under budget and if it is ahead or behind schedule. (show detail calculation)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 8 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Essentials Of Investments
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
FUNDAMENTALS OF CORPORATE FINANCE
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:
9781260013962
Author:
BREALEY
Publisher:
RENT MCG
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
Foundations Of Finance
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education