Risk_assessment_Report

docx

School

Southern New Hampshire University *

*We aren’t endorsed by this school

Course

313

Subject

Information Systems

Date

Feb 20, 2024

Type

docx

Pages

5

Uploaded by msheba08

Report
Running Head: Risk Assessment Report 1 Bathsheba Harris Southern New Hampshire 6-2 Qualitative and Quantitative Risk Assessment Report October 7, 2023
Risk Assessment Report 2 To estimate the qualitative and quantitative risks of bringing the project to completion under different circumstances, this report will consider the potential outcomes and associated risks for each scenario: Scenario 1: On Time Qualitative Risks Since the project is completed on time, there is a low risk of financial losses due to penalties for late delivery. However, there might be moderate risks associated with unexpected technical challenges or minor delays during implementation. Quantitative Risks Given that the project is completed on time, a relatively low financial risk is associated with penalties or revenue loss. However, there may still be some minor unforeseen expenses. Scenario 2: One Month Early Qualitative Risks Completing the project one month early could introduce risks associated with potentially rushed implementation, which may lead to overlooked security measures or technical glitches. Also, there is a relatively low risk of financial penalties due to early delivery as long as all contractual obligations are met. Quantitative Risks While some additional costs may be associated with accelerated implementation, the overall financial risk is still relatively low. The potential gains from early completion of the network implementation project might outweigh any additional expenses. Scenario 3: Two Months Late Qualitative Risks
Risk Assessment Report 3 In a two-month delay in project completion, qualitative risks escalate significantly. The potential for substantial penalties due to late delivery looms large, and such a delay could also precipitate reputational damage to the U.S. government, potentially eroding trust and confidence (Gardner et al., 2021). This, in turn, may impact future contracts and collaborations. Concurrently, technical challenges may surface as a consequence of the extended timeline. Resource constraints might intensify, potentially impeding the acquisition of requisite expertise and materials. Moreover, the evolving project scope introduces additional uncertainties, potentially leading to complications. Quantitative Risks With a two-month delay, the financial implications are substantial. The company may face considerable monetary penalties due to breaching contract terms associated with tardy project delivery (Silverman, 2021). These penalties can significantly impact the project's profitability and the company's overall financial health. In the worst-case scenario, if the delay reaches a critical threshold defined in the contract, the company could face contract termination, resulting in the loss of the entire contract value. This would be a significant blow to the company's revenue and reputation. Estimate of Qualitative Risks 1. On-Time, but Not with the Required Security Qualitative Risk: High Delivering the project on time without the required security measures poses a high risk. It could potentially lead to breaches or vulnerabilities, jeopardizing sensitive information and violating compliance standards ( Jamshed et al., 2015 ). 2. One Month Early with Required Security Requirements Qualitative Risk: Medium
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Risk Assessment Report 4 Completing the project one month early with the required security measures still entails some risk. Rushing the process may result in oversight or minor technical glitches, but the security measures mitigate some potential risks. 3. Two Months Late, Without Required Security Requirements Qualitative Risk: Very High A two-month delay without implementing the required security measures carries an extremely high risk. Apart from penalties for late delivery, it could lead to severe security breaches, reputation damage, and potential contract termination. Estimate of Qualitative and Quantitative Risks Qualitative Risk: Very High The financial and reputational risks are immense. Not meeting Contractual commitments can lead to severe penalties, contract termination, and significant reputational damage. Financially, this could result in losing the entire contract value and potential legal repercussions. The impact on future contracts and collaborations could also be substantial.
Risk Assessment Report 5 References Gardner, T. A., Benzie, M., Börner, J., Dawkins, E., Fick, S., Garrett, R., Godar, J., Grimard, A., Lake, S., Larsen, R. K., Mardas, N., McDermott, C. L., Meyfroidt, P., Osbeck, M., Persson, M., Sembres, T., Suavet, C., Strassburg, B., Trevisan, A., … Wolvekamp, P. (2019). Transparency and sustainability in global commodity supply chains. World Development, 121, 163–177. https://doi.org/10.1016/j.worlddev.2018.05.025 Jamshed, N., Ozair, F., Sharma, A., & Aggarwal, P. (2015). Ethical issues in electronic health records: A general overview. Perspectives in Clinical Research, 6(2), 73. https://doi.org/10.4103/2229-3485.153997 Silverman, A. (2021). 4 types of breach of contract you need to be aware of. Contractworks.com. https://www.contractworks.com/blog/4-types-of-breach-of- contract-you-need-to-be-aware-of