l v Correct @ Here are the project risk management processes: . 1. Identify risks 2. Control risks 3. Perform quantitative risk analysis 4. Plan risk responses 5. Plan risk management 6. Perform qualitative risk analysis Which of the following is the correct sequence for the project risk management processes? v A ' 5-1-6-3-4-2 £ 1-3-4-2-6-5 C 1-2-3-4-5-6 D 4-3-5-1-2-6