STUDENT 3 - NASA Mars Case Study
docx
keyboard_arrow_up
School
Arizona State University *
*We aren’t endorsed by this school
Course
5116
Subject
Industrial Engineering
Date
Dec 6, 2023
Type
docx
Pages
6
Uploaded by sallyplone
NASA
Mars
Case
Study
NASA
Mars
Case
Study
University
of
the
People
Dr.
Osinubi
March
9,
2021
NASA
Mars
Case
Study
Introduction
Although,
many
have
argued
that
operations
management
may
not
be
crucial
to
success
of
an
operation,
almost
every
case
study
one
looks
at
would
argue
the
opposite.
That
is
no
different
in
the
NASA
1999
mission
we
reviewed
this
week.
This
mission
offer
lots
of
opportunities
for
companies
to
explore
the
failures
of
the
mission
and
determine
what
could
have
been done
better
to
prevent
the
problems
that
occurred.
The
overall
failure
of
the
mission
can
be
attributed
to
many
things,
but
it
seems
that
errors
in
basic
operations
management
technique
were
an
important
factor.
This
case
study
will
show
the
importance
of
proper
operations
management
in
achieving
success.
Description
of
Case
To
give
a
little
background
to
the
case,
NASA
had
set
out
to
circle
and
land
an
aircraft
on
the
planet
of
mars
(NASA,
2020).
The
shuttles
were
planned
to
bring
top
of
the
line
technology
that
would
advance
the
understanding
of
planet
for
scientist
a
crossed
the
world.
The
mission
was
planned
to
advance
the
knowledge
of
Mars
(NASA,
2019).
There
were
and
still
are
many
high
priority
topics
scientist
are
looking
to
study
about
the
planet
due
to
its
similarities
to
earth
(NASA,
2020).
An
in-depth
plan
was
created
to
get
the
spacecraft
to
the
planet
based
off
a
former
operation
(NASA,
2020).
Although
the
plan
originally
seemed
detailed,
it
was
clearly
not
detailed
enough
as
the
plan
did
not
wield
successful
results.
It
was
determined
in
later
studies
that
there
were
numerous
design
flaws
in
the
mission
that
could
have
resulted
in
the
failure
of
the
mission
(Casani,
2000).
The
ultimate
question
is
what
led
to
the
project
having
major
design
NASA
Mars
Case
Study
flaws.
In
the
next
section
we
will
look
further
at
what
might
have
caused
such
severe
design
flaws
in
a
major
project
like
this.
Analysis
At
first
glance,
it
may
appear
the
NASA
project
was
well
backed
but
that
was
hardly
the
case.
This project
was
significantly
underfunded
and
forced
to
work
on
expedited
schedules
that
were
not
anticipated
at
the
project
kickoff
(Casani,
2000).
This
was
a
large
cause
for
the
failure,
but
it
was
not
noted
until after
the
failure
of
the
project.
Project
teams
were
established
after
the
operation
failed
to
figure
out
what went wrong.
At
that
point,
it
was
clearly
far
to
late
to
address
any
of
the
issues
that
were
relevant
during
the
project,
but
the
goal
was
to
understand
and
address
the
issues
for
future
operations.
The
team
assessed
many
failure
modes
and
used
a
DMAIC
method
to
determine
what
went
wrong
with
the
project
(Casani,
2000).
These
methods
they
employed
after
failure
did
little
good
to
help
the
project
and
could
have
been
implemented
much
sooner
to
see
the
issues
before
they
happened.
Major
Issues
There
are
many
issues
that
may
have
been
a
cause
for
the
failure
of
the
project
but there
are
three
that
stand
out
expedited
schedules,
low
cost,
and
lack
of
risk
analysis
(Casani,
2000).
The
project
was
expected
to
deliver
a
similar
product
to
the
last
mission
on
just
about
half
cost
and
a
tighter
scheduler.
Even
with
the
improved
technology
from
the
previous
missions,
this
is
a
huge
stretch
no
matter
the
goal.
On
top
of
that,
the
program
had
limited
staffing
that
was
being
overworked
greatly
(Casani,
2000).
It
was
easy
for
people
to
overlook
simple
mistake
when
they
were
working
sixty
to
eighty-hour
weeks
on
a
regular
basis.
Furthermore,
the
board
of
the
program
was
driven
to
take
more
risky
choices
to
complete
the
program
because
of
the
low
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
NASA
Mars
Case
Study
budget
(Cownig,
2000).
They
did
not
properly
assess
the
risk
of
the
choices
they
were
making
because
of
both
the
tight
schedule
and
cost.
Risk
assessment
is
not
particularly
costly
or
time
consuming
but
the
results
of
what
comes
out
of
a
good
risk
assignment
can
be
both
(Hayes,
2021).
Given
the
pushing
factors
on
the
project,
they
simply
could
not
afford
the
delay
of
a
risk
assessment
because
there
was
not
room
to
address
the
issues.
Solutions
Ultimately
there
may
have
been
no
answer
that
could
have
fixed
the
issue
in
this
situation
because
of
the
extreme
pressure
that
was
on
the
project.
If
more
funding
and
time
could
not
be
received
even
perfect
implementation
of
the
tools,
I
will
talk
about
below
would
likely
have
had
minimal
impacts.
To
have
success
the
team
likely
should
have
scrapped
the
project
in
the
initiation
stages
but
they
let
it
go
on
far
too
long.
If
the
team
was
to
salvage
the
project,
they
should
have
looked
at
using
a
DMAIC
(Define,
Measure,
Analyze,
Improve
and
Control)
approach
(DMAIC,
N/A).
An
approach
like
this
could
have
provided
extreme
insights
to
the
failure
modes
that
the
project
was
experiencing.
A
second
method
the
team
should
have
considered
is
Value
Stream
Mapping.
This
is
a
method
to
document
processes
and
eliminate
waste
(Knaster,
2020).
A
method
like
this
helps
a
team
focus
in
on
what
truly
is
important
to
the
mission
at
hand
and
lets
them
tune
out
the
unimportant
information.
Given
a
mission
everything
seems
important,
they
needed
to
prioritize
the
key
factors
that
would
make
the
mission
successful.
A
final
thing
the
project
should
have
done
was
a
FMEA.
An
FMEA
is
a
tool
that
allows
for
understanding
of
risk
to
a
program
(Failure
Mode
and
Effects
Analysis,
N/A).
Once
again,
a
tool
like
this
would
help
them
prioritize
what
is
important
to
the
success
of
the
program
and
NASA
Mars
Case
Study
determine
what
problems
are
the
most
important
to
address.
It
is
not
well
documented
that
the
INASA
team
used
any
of
the
three
methods
mentioned
above
all
of
which
could
have
led
to
a
successful
project.
Conclusion
There
are
many
things
that
could
have
been done
differently
to
make
a
more
successful
project
but
were
any
of
these
things
possible
given
the state the
team
was
place
in?
It
seems
that
there
was
not
time
or
money
to
support
these
extra
efforts.
The
team
needed
to
strongly
elaborate
to
their
customer
about
the
importance
of
these
tools
and
operations
management
to
be
successful.
If
the
team
had
the
time
and
money
to
use
the
some
of
the
methods
we
discussed,
I
think
they
could
have
made
the
project
successful
but
I
simply
do
not
think
that
was
an
option
for
the
team.
NASA
Mars
Case
Study
References
Casani,
J.,
Report
on
the
loss
of
the
Mars
Polar
Lander
and
Deep
Space
2
missions
(2000).
Pasadena,
CA;
Jet
Propulsion
Laboratory,
California
Institute
of
Technology.
Cowing,
K.
(2000,
March
28).
NASA
Reveals
Probable
Cause
of
Mars
Polar
Lander
and
Deep
Space-2
Mission
Failures.
SpaceRef.
http://www.spaceref.com/news/viewnews.html?
id=105#:~:text=NASA%20Reveals%20Probable%20Cause%200f%20Mars%20Polar
%20Lander,lander%20thought%20the%20j01t%200f%20its%20landing%20.
Failure
Mode
and
Effects
Analysis
(FMEA).
ASQ.
https://asq.org/quality-resources/fmea.
Hayes,
A.
(2021,
February
19).
How
Risk
Analysis
Works.
Investopedia.
https://www.investopedia.com/terms/r/risk-analysis.asp.
Knaster,
R.
(2020,
June
30).
Value
Streams.
Scaled
Agile
Framework.
https://www.scaledagileframework.com/value-streams/#:~:text=A%20value%?20stream
%20contains%?20the%?20people%20who0%20do,time%?20reduces%20the%?20time-to-
market.%20That%?20is%20the%20focus.
NASA.
(2019,
July
25).
In
Depth.
NASA.
https://solarsystem.nasa.gov/missions/mars-polar-
lander-deep-space-2/in-depth/.
NASA.
(2020,
August
19).
Mars
Polar
Lander/Deep
Space
2.
NASA.
https://mars.nasa.gov/mars-exploration/missions/polar-lander/.
The
Define,
Measure,
Analyze,
Improve,
Control
(DMAIC)
Process.
ASQ.
https://asq.org/quality-
resources/dmaic.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help