Production Operations and Management[1]
docx
keyboard_arrow_up
School
University of Illinois, Springfield *
*We aren’t endorsed by this school
Course
521A
Subject
Industrial Engineering
Date
Dec 6, 2023
Type
docx
Pages
7
Uploaded by ElderValorMule43
Production and Operations Management
Module 2 HW-1
Submitted by
Group 2
1
Akhila Vydugula
2
Shreya Vishwas
3
Bhavana Yadav Krishnappa
4
Sohan Shylaja Mohan
Shale Oil Case Study
Network diagrams are used by the project management technique PERT (Program Evaluation and Review
Technique) to predict the amount of time needed for project tasks. The PERT (Program Evaluation and Review Technique) 4-way technique using AON (Activity-on-Node) entails a structured study of project activities and dependencies. It consists of the following key elements:
Define Activities and Sequence.
Determine Activity Durations and Time Estimates.
Create Project Network Using AON.
Determine Critical Path and Slack.
Let’s calculate Expected time and variance using the below formulas:
T exp = (a+4m+b)/6
Variance=[(b-a)/6] 2
No
.
Activity
Optimisti
c Most Likely(m
)
Pessimistic(b
)
Predecessor
Expecte
d time
Varianc
e
1
Circulate wash water throughout unit
1
2
2.5
-
1.9
0.06
2
Install blinds
1.5
2
2.5
1
2.0
0.03
3
Open and clean
vessels and columns
2
3
4
2
3.0
0.11
4
Open and clean
heat exchangers; remove tube bundles
1
2
3
2
2.0
0.11
5
Open and clean
1
2
4
2
2.2
0.25
furnaces
6
Open and clean
mechanical equipment
2
2.5
3
2
2.5
0.03
7
Inspect instrumentatio
n
2
4
5
2
3.8
0.25
8
Inspect vessels and columns
1
2
3
3
2.0
0.11
9
Inspect
heat-exchanger
shells
1
1.5
2
4
1.5
0.03
10
Inspect tube bundles
1
1.5
2
4
1.5
0.03
11
Inspect furnaces
2
2.5
3
5
2.5
0.03
12
Retube furnaces
15
20
30
5
20.8
6.25
13
Inspect mechanical equipment
1
1.5
2
6
1.5
0.03
14
Install new pump mechanical seals
3
5
8
6
5.2
0.69
15
Repair instrumentatio
n
3
8
15
7
8.3
4.00
16
Repair vessels and columns
14
21
28
8
21.0
5.44
17
Repair
heat-exchanger
shells
1
5
10
9
5.2
2.25
18
Repair tube bundles; retube
2
5
10
10
5.3
1.78
19
Repair furnaces
5
10
20
11
10.8
6.25
20
Repair mechanical equipment
10
15
25
13
15.8
6.25
21
Test and close vessels and columns
4
5
8
16
5.3
0.44
22
Install tube bundles into heat-exchanger
shells
1
2
3
18
2.0
0.11
23
Test and close 1
2
2.5
17, 22
1.9
0.06
heat exchangers
24
Test and close furnaces
1
2
3
12, 19
2.0
0.11
25
Test and close mechanical equipment
1
2
3
14, 20
2.0
0.11
26
Test instrumentatio
n
2
4
6
15
4.0
0.44
27
Pull blinds
1.5
2
2.5
21,23,24,25,2
6
2.0
0.03
28
Purge all
equipment with steam
1
3
5
27
3.0
0.44
29
Start up unit
3
5
10
28
5.5
1.36
147.5
1)
Draw the project network using AON method
.
5) List all critical activities. What percentage of all activities are critical.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Activities that have Zero slack value are considered critical. These are the tasks that will postpone the project's completion if they are not completed on time. From the above diagram we identified the critical path as 1-2-3-8-16-21-27-28-29
. So these are the activities that are critical.
No
Critical Activity
Expected Time
1
Circulate wash water throughout unit
1.9
2
Install blinds
2.0
3
Open and clean vessels and columns
3.0
8
Inspect vessels and columns
2.0
16
Repair vessels and columns
21.0
21
Test and close vessels and columns
5.3
27
Pull blinds
2.0
28
Purge all
equipment with steam
3.0
29
Start up unit
5.5
Total= 45.7 Critical activities time = 45.7 Days
The expected time for all activities(Critical+ Non-Critical) = 146.7 Days
Critical Activities percentage= (45.7/146.7 )*100 = 31.15%
6) List all non-critical activities. All activities with slack value>0 are non-critical activities. Delaying these activities does not affect the project completion time. From the above diagram we can list them as:
No
Non-Critical Activities
4
Open and clean heat exchangers; remove tube bundles
5
Open and clean
furnaces
6
Open and clean mechanical equipment
7
Inspect instrumentation
9
Inspect
heat-exchanger shells
10
Inspect tube bundles
11
Inspect furnaces
12
Retube furnaces
13
Inspect mechanical equipment
14
Install new pump mechanical seals
15
Repair instrumentation
17
Repair
heat-exchanger shells
18
Repair tube bundles; retube
19
Repair furnaces
20
Repair mechanical equipment
22
Install tube bundles into heat-exchanger shells
23
Test and close heat exchangers
24
Test and close furnaces
25
Test and close mechanical equipment
26
Test instrumentation
7) What is the probability that the shutdown can be completed 4 days earlier than expected project completion time.
To calculate the probability of completing the project 4 days earlier than expected project completion. We need project variance and standard deviation.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Using above calculations we can draw the statistical graph,
X