Name the formula to calculate the lines of communication.
The formula is n (n − 1) / 2.
Constraint reprioritization, interaction between constraints, and other projects are examples of what?
Influences that can impact or change the project constraints
These describe the characteristics of the functional requirements.
Nonfunctional requirements.
Name the major elements of a scope statement.
Project description, key deliverables, acceptance criteria, exclusions,
assumptions, and constraints
Name the three categories of contracts.
Fixed price, cost reimbursable, and time and materials
What entity is responsible for reviewing change requests and approving, denying, or delaying their
implementation?
The change control board
What types of activities are the responsibility of the project team members?
They contribute expertise to the project, work on deliverables according to the
project schedule, estimate task durations, estimate costs, and provide
dependencies.
In which project process group is the project charter document created?
Initiating
This chart plots two numerical variables to determine whether there is a correlation between the data
points.
Scatter diagram
Name the formula for CPI.
CPI = EV/AC.
Name the estimating technique that bases estimates on past projects of similar size and scope.