When might a Sprint be abnormally cancelled? When the Sprint Goal becomes obsolete. The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress. What should the Development Team do? Inform the Product Owner so he/she can work with the CEO. An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? a. Without a new vocabulary as a reminder of the change, very little change may actually happen. b. The organization may not understand what has changed with Scrum and the benefits of Scrum may be lost. c. Management may feel less anxious. d. All answers apply. d. All answers apply. When multiple teams work together on the same product, each team should maintain a separate Product Backlog. False Note: Products have one Product Backlog, regardless of how many teams are used. Any other
the same time and same place? each day to reduce complexity. Which two (2) things does the Development Team do during the first Sprint? a. Deliver an increment of releasable software. b. Determine the complete architecture and infrastructure for the product. c. Develop and deliver at least one piece of functionality. d. Develop a plan for the rest of the release. e. Create the complete Product Backlog to be developed in subsequent Sprints a. Deliver an increment of releasable software. AND c. Develop and deliver at least one piece of functionality. What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? a. By facilitating Development Team decisions b. By removing impediments that hinder the Development Team c. By starting and ending the meetings at the proper time a. By facilitating Development Team decisions AND b. By removing impediments that hinder the Development Team
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
d. By keeping high value features high in the Product Backlog When do Development Team members become the exclusive owner of a Sprint Backlog item? a. At the Sprint planning meeting. b. Never. All Sprint Backlog Items are "owned" by the entire Development Team, even though each one may be done by an individual development team member. c. Whenever a team member can accommodate more work. d. During the Daily Scrum. b. Never. All Sprint Backlog Items are "owned" by the entire Development Team, even though each one may be done by an individual development team member. During a Sprint, a Development Team determines that it will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected? a. The Scrum Master, the project manager and the Development Team. b. The Product Owner and the Development Team. c. The Product Owner and all b. The Product Owner and the Development Team.
stakeholders. d. The Development Team. The time-box for the Sprint Planning meeting is? a. 4 hours b. 8 hours for a monthly Sprint. For shorter Sprints it is usually shorter. c. Whenever it is done. d. Monthly. b. 8 hours for a monthly Sprint. For shorter Sprints it is usually shorter. Which statement best describes the Sprint Review? a. It is a mechanism to control the Development Team's activities during a Sprint. b. It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next. c. It is a demo at the end of the Sprint for everyone in the organization to check on the work done. b. It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out Upon what type of process control is Scrum based? a. Empirical
Your Progress With Progress, you can start studying the terms you still need to master in one click. Not studied Study Still learning Study Mastered Study Get access to all your stats, your personal progress dashboard and smart study shortcuts with Quizlet Plus. Unlock Progress Terms in this set (35) Virtual ScrumMaster Class Visit Site Ad effectiveagiledev.com/ScrumMaster Who should know the most about the progress toward a business objective or a release, and be able to explain the alternatives most clearly? The Product Owner How much work must a Development Team do to a Product backlog item it selects for a Sprint? As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of done. Which of the below are roles on a Scrum Team? a. Development Team b. Users c. Customers A, D, E a. Development Team d. Product Owner e. Scrum Master
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
d. Product Owner e. Scrum Master Scrum does not have a role called "project manager." True or False True What are the 3 Pillars of Empirical Process control Inspection, Transparency, Adaptation When many Development Teams are working on a single product, what best describes the definition of "done?" a. Each Development Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint. b. Each Development Team uses its own but must make their definition clear to all other Teams so the differences are known. c. All Development Teams must have a definition of "done" that makes their combined work potentially releasable. d. It depends. . c. All Development Teams must have a definition of "done" that makes their combined work potentially releasable. Upgrade to remove ads Only $2.99/month
When is a Sprint over? a. When all Product Backlog items meet their definition of done. b. When the Product Owner says it is done. c. When all the tasks are completed. d. When the time-box expires d. When the time-box expires The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity. Based on this, which of the following is FALSE? a. The Product Owner can help clarify or optimize the Sprint when asked by the Development Team. b. The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change during the Sprint. c. As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes and may grow as the work emerges. b. The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change during the Sprint.
Upgrade to remove ads Only $2.99/month Trendsetters Feed Follow 4 9 Send Reply Here 140 Sponsored ___ -12% True or False setup makes it difficult for the Development Team to determine what it should work on. What is the role of Management in Scrum? a. Continually monitor staffing levels of the Development Team. b. Monitor the Development Team's productivity. c. Support the Product Owner with insights and information into high value product and system capabilities. Support the Scrum Master to cause organizational change that fosters empiricism, self- organization, bottom-up intelligence, and intelligent release of software. d. Identify and remove people that aren't working hard enough. c. Support the Product Owner with insights and information into high value product and system capabilities. Support the Scrum Master to cause organizational change that fosters empiricism, self- organization, bottom-up intelligence, and intelligent release of software. What does it mean to say that an event has a time-box? The event can take no more than a maximum amount of time. Why is the Daily Scrum held at The Daily Scrum is held at the same time and place
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
d. The Development Team may work with the Product Owner to remove or add work if it finds it has more or less capacity than it expected. Who has the final say on the order of the Product Backlog? The Product Owner The time-box for a Daily Scrum is? 15 minutes During the Daily Scrum, the Scrum Master's role is to: a. Lead the discussions of the Development Team. b. Make sure that all 3 questions have been answered. c. Manage the meeting in a way that each team member has a chance to speak. d. Teach the Development Team to keep the Daily Scrum within the 15 minute time-box. e. All answers apply. b. Make sure that all 3 questions have been answered. It is mandatory that the product increment be released to production at the end of each Sprint. False
True or False When does the next Sprint begin? a. Next Monday. b. Immediately following the next Sprint Planning. c. When the Product Owner is ready. d. Immediately after the conclusion of the previous Sprint. d. Immediately after the conclusion of the previous Sprint. The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity. Based on this, which of the following is FALSE? a. The Product Owner can help clarify or optimize the Sprint when asked by the Development Team. b. The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change during the Sprint. b. The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change during the Sprint.
c. As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes and may grow as the work emerges. d. The Development Team may work with the Product Owner to remove or add work if it finds it has more or less capacity than it expected. The length of a Sprint should be: a. Short enough to keep the business risk acceptable to the Product Owner. b. Short enough to be able to synchronize the development work with other business events. c. No more than one month. d. All of these answers are correct. d. All of these answers are correct. Which statement best describes a Product Owner's responsibility? a. Optimizing the value of the work the Development Team does. b. Directing the Development a. Optimizing the value of the work the Development Team does.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Team. c. Managing the project and ensuring that the work meets the commitments to the stakeholders. d. Keeping stakeholders at bay. Who is required to attend the Daily Scrum? a. The Development Team. b. The Scrum team. c. The Development Team and Scrum Master. d. The Development Team and Product Owner. e. The Scrum Master and Product Owner. a. The Development Team. Which statement best describes Scrum? a. A complete methodology that defines how to develop software. b. A cookbook that defines best practices for software development. c. A framework within which c. A framework within which complex products in complex environments are developed.
complex products in complex environments are developed. d. A defined and predictive process that conforms to the principles of Scientific Management The length of a Sprint should be: a. Short enough to keep the business risk acceptable to the Product Owner. b. Short enough to be able to synchronize the development work with other business events. c. No more than one month. d. All of these answers are correct. d. All of these answers are correct.
THIS SET IS OFTEN IN FOLDERS WITH... PSM 1 145 terms kate_v3 PSM 1 277 terms nemguzina PSM 1 277 terms vicki_knudtson PSM 1 - SCRUM 80 terms lucasscarpa
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Upgrade to remove ads Only $2.99/month Buy One Take One Brio Italian Brio Italian Grille a. Empirical b. Hybrid c. Defined d. Complex The purpose of a Sprint is to produce a done increment of working product. True or False True The Development Team should have all the skills needed to: a. Complete the project as estimated when the date and cost are committed to the Product Owner. b. Do all of the development work, except for specialized testing that requires additional tools and environments. c. Turn the Product Backlog items it selects into an increment of potentially releasable product functionality. c. Turn the Product Backlog items it selects into an increment of potentially releasable product functionality.