W8EVM_Assignment_BG6MCZ
pdf
keyboard_arrow_up
School
Seneca College *
*We aren’t endorsed by this school
Course
115
Subject
Industrial Engineering
Date
Dec 6, 2023
Type
Pages
7
Uploaded by EarlBravery4233
BG6MCZ
XXXXXXXXX
Activity
4
8
12
16
20
24
28
Concept Design
$500
$1,500
$2,000
$3,600
$3,000
$1,500
Proposal
$450
$4,500
$100
$100
$4,500
Negotiations
$500
$1,200
Resource Acquisition
$500
Training
$300
$750
$950
Modeling
$400
$1,000
Planning
$2,000
$500
$3,000
$2,000
Testing
$1,000
$4,000
Control
$1,200
$2,000
Quality Assurance
$100
$500
$500
$500
$500
$3,500
Scope Verification
$1,000
$1,000
$6,000
Contract Closure
$2,000
$4,000
Total
Cumulative Total
$500
$2,550
$8,800
$8,550
$9,050
$10,700
Acual Cost
$500
$3,500
$11,000
$5,500
$8,000
$8,000
Cumulative Actual Cost
BAC
SV
($10,470)
SPI by Month
0.74
CPI
0.81
CV
($6,820)
EAC
i.
Calculate the Total Budget at Completion ( BAC ) for the project
ii.
Calculate the Schedule Variance and the SPI for this project at the end of the 24th month
iii.
Calculate the Cost Variance and the CPI for the project at the end of the 24th month
iv.
Calculate the Estimate at Completion
v.
Is the project on budget / over budget / under budget? What is showing you this?
Based on the fact that the CV is negative ($6820) and the EAC ($49567.90) is greater than the BAC ($401
To sum up, according to the data provided, the project budget was overrun, that is, the project exceeded
vi.
What might this mean in terms of upcoming payments for this project?
Based on the provided data indicating that the project is over budget, it suggests that there may be upco
Since the project is over budget, it implies that the actual costs have exceeded the planned budget. As a
Payment for remaining work: To complete the project, additional payments may be required to cover the
Adjustments in funding: The project team may need to request additional funding from stakeholders or s
Contractual obligations: If the project involves contracts with vendors or suppliers, there might be upcom
It is essential to assess the current financial situation of the project, identify the cost overruns, and devel
a.
Is the project on schedule / ahead of schedule / behind schedule? What is showing you this?
To determine whether the project is on schedule, ahead of schedule, or behind schedule, we need to ana
SV (Schedule Variance) measures the difference between the earned value (EV) and the planned value (P
SPI (Schedule Performance Index) reflects the efficiency of schedule performance by comparing the earn
Based on SV and SPI values, we can conclude the following:
Is the project on schedule/ahead of schedule/behind schedule? Based on the negative SV (-$10470) and
Therefore, according to the provided data, the project is behind schedule, indicating that the actual prog
TOTAL
% Complete
EV(24Month)
PV(24Month)
SPI by Project
$12,100
85%
$10,285
$12,100
0.85
$9,650
90%
$8,685
$9,650
0.9
$1,700
100%
$1,700
$1,700
1
$500
100%
$500
$500
1
$2,000
100%
$2,000
$2,000
1
$1,400
75%
$300
$400
0.75
$7,500
60%
$3,300
$5,500
0.6
$5,000
10%
$100
$1,000
0.1
$3,200
30%
$360
$1,200
0.3
$5,600
50%
$1,050
$2,100
0.5
$8,000
30%
$600
$2,000
0.3
$6,000
40%
$800
$2,000
0.4
$29,680
$40,150
$40,150
$36,500
$40,150
$49,567.90
50), it can be inferred that the project is over budget. Actual costs exceeded budget, so project cost control w
d the budget.
oming payments that need to be considered for the project.
result, there may be a need to allocate additional funds to cover the remaining work and meet the project's
e remaining tasks or deliverables.
sponsors to address the cost overruns and ensure the successful completion of the project.
ming payments required based on the contractual terms, even if the project is over budget.
lop a plan to address the budget shortfall. By analyzing the upcoming payments and making necessary adjust
alyze the provided data and evaluate the project's schedule performance indicators.
PV) and indicates the project's schedule performance. According to the provided data, SV is -$10470, which m
ned value (EV) to the planned value (PV). With an SPI of 0.74, which is less than 1, it further confirms that the
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
gress is slower than planned. This delay could have implications for project milestones, deadlines, and overall
tments, the project team can better manage the project's financial aspects and mitigate the impact of being ov
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
ver budget.