W8EVM_Assignment_BG6MCZ

pdf

School

Seneca College *

*We aren’t endorsed by this school

Course

115

Subject

Industrial Engineering

Date

Dec 6, 2023

Type

pdf

Pages

7

Uploaded by EarlBravery4233

Report
BG6MCZ XXXXXXXXX Activity 4 8 12 16 20 24 28 Concept Design $500 $1,500 $2,000 $3,600 $3,000 $1,500 Proposal $450 $4,500 $100 $100 $4,500 Negotiations $500 $1,200 Resource Acquisition $500 Training $300 $750 $950 Modeling $400 $1,000 Planning $2,000 $500 $3,000 $2,000 Testing $1,000 $4,000 Control $1,200 $2,000 Quality Assurance $100 $500 $500 $500 $500 $3,500 Scope Verification $1,000 $1,000 $6,000 Contract Closure $2,000 $4,000 Total Cumulative Total $500 $2,550 $8,800 $8,550 $9,050 $10,700 Acual Cost $500 $3,500 $11,000 $5,500 $8,000 $8,000 Cumulative Actual Cost BAC SV ($10,470) SPI by Month 0.74 CPI 0.81 CV ($6,820) EAC i. Calculate the Total Budget at Completion ( BAC ) for the project ii. Calculate the Schedule Variance and the SPI for this project at the end of the 24th month iii. Calculate the Cost Variance and the CPI for the project at the end of the 24th month iv. Calculate the Estimate at Completion v. Is the project on budget / over budget / under budget? What is showing you this? Based on the fact that the CV is negative ($6820) and the EAC ($49567.90) is greater than the BAC ($401 To sum up, according to the data provided, the project budget was overrun, that is, the project exceeded vi. What might this mean in terms of upcoming payments for this project? Based on the provided data indicating that the project is over budget, it suggests that there may be upco Since the project is over budget, it implies that the actual costs have exceeded the planned budget. As a Payment for remaining work: To complete the project, additional payments may be required to cover the Adjustments in funding: The project team may need to request additional funding from stakeholders or s Contractual obligations: If the project involves contracts with vendors or suppliers, there might be upcom It is essential to assess the current financial situation of the project, identify the cost overruns, and devel a. Is the project on schedule / ahead of schedule / behind schedule? What is showing you this? To determine whether the project is on schedule, ahead of schedule, or behind schedule, we need to ana SV (Schedule Variance) measures the difference between the earned value (EV) and the planned value (P SPI (Schedule Performance Index) reflects the efficiency of schedule performance by comparing the earn Based on SV and SPI values, we can conclude the following:
Is the project on schedule/ahead of schedule/behind schedule? Based on the negative SV (-$10470) and Therefore, according to the provided data, the project is behind schedule, indicating that the actual prog
TOTAL % Complete EV(24Month) PV(24Month) SPI by Project $12,100 85% $10,285 $12,100 0.85 $9,650 90% $8,685 $9,650 0.9 $1,700 100% $1,700 $1,700 1 $500 100% $500 $500 1 $2,000 100% $2,000 $2,000 1 $1,400 75% $300 $400 0.75 $7,500 60% $3,300 $5,500 0.6 $5,000 10% $100 $1,000 0.1 $3,200 30% $360 $1,200 0.3 $5,600 50% $1,050 $2,100 0.5 $8,000 30% $600 $2,000 0.3 $6,000 40% $800 $2,000 0.4 $29,680 $40,150 $40,150 $36,500 $40,150 $49,567.90 50), it can be inferred that the project is over budget. Actual costs exceeded budget, so project cost control w d the budget. oming payments that need to be considered for the project. result, there may be a need to allocate additional funds to cover the remaining work and meet the project's e remaining tasks or deliverables. sponsors to address the cost overruns and ensure the successful completion of the project. ming payments required based on the contractual terms, even if the project is over budget. lop a plan to address the budget shortfall. By analyzing the upcoming payments and making necessary adjust alyze the provided data and evaluate the project's schedule performance indicators. PV) and indicates the project's schedule performance. According to the provided data, SV is -$10470, which m ned value (EV) to the planned value (PV). With an SPI of 0.74, which is less than 1, it further confirms that the
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
gress is slower than planned. This delay could have implications for project milestones, deadlines, and overall
tments, the project team can better manage the project's financial aspects and mitigate the impact of being ov
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
ver budget.