Knowledge Assessment
Matching (10 points)
Match the term in column 1 to its description in column 2.
Multiple Choice (10 Points)
Select the best response for the following statements.
1.
Which of the following is not an example of a work resource?
1.
Yan Li
2.
keyboard
3.
SD card
4.
electrician
2.
It is helpful to assign a base calendar to a group of resources when they all .
1.
have the same pay rate
2.
work the night
shift 3.
have the same Max. Units
4. do the same job function?
Column 1
Column 2
1. resource calendar a. the maximum capacity of a resource to accomplish tasks
2. Max. Units b. specifies default working and nonworking times for a resource, a project, or a task
3. material resource c. when and how much of a resource's time can be assigned to work
on tasks
4. project
calendar d. the people and equipment that do work to accomplish the tasks of the project
5. cost resource e. the people, equipment, money, and materials used to complete the tasks in a project
6. work resource f. a way of documenting information about resources, tasks, and assignments
7. base calendar g. consumable items used up as the tasks in a project are accomplished
8. availability h. a resource that doesn't depend on the amount of work on a task or the duration of a task
9. resources i. the base calendar that provides default working times for an entire
project
10. note j. defines the working and nonworking time for an individual resource
J
A
G
I
H
D
B
C
E
F
4.
A resource calendar does not apply to which of the following?
1.
material resources 2.
people resources
3.
equipment resources
4.
work resources
5.
In which of the following views can you view information for the individual people who will perform the tasks on the project?
1.
Calendar view
2.
Gantt Chart view
3.
Network Diagram view
4.
Resource
Sheet view
5.
You can provide additional information about how a resource is scheduled by doing which of the following?
1.
changing the Max. Units
2.
establishing a project calendar
3.
adding
a resource
note
4.
setting constraints
6.
For which resource is the standard rate listed per tracking unit of consumption?
1.
material
2.
equipment
3.
people
4.
all of the above
7.
If you have four electricians whom can each work part
‐
time (4 hours rather than 8), which of the
following values should you assign to Max. Units for the resource
“electrician”?
1. 50%
2. 25%
3. 100%
4
. 200%
8.
If you assign a base calendar to a resource, which of the following is true?
1.
The base calendar dictates the resource's vacation days.
2.
The base calendar gives all the available time to work on the project.
3.
The
base
calendar
gives
the
basic
days/hours
for
the
resource,
but
the
resource's
calendar can
have exceptions to
those
days/hours.
4.
The resource calendar contains all nonworking days for the entire project.
9.
To add vacation days to the calendar for an individual work resource, which dialog box would you use?
1.
Resource Information
2.
Resource Notes
3.
Change Working
Time
4.
none of the above
10. Which of the following is a reason why it is often difficult to get cost information for people resources?
1.
The
information is
often
confidential.
2.
The information is too complex to calculate.
3.
The information changes too frequently.
4.
The costs are large in comparison with other resource costs.
11. people resources
12. equipment resources
13. work resources
6.
In which of the following views can you view information for the individual people who will perform the tasks on the project?
1.
Calendar view
2.
Gantt Chart view
3.
Network Diagram view
4.
Resource Sheet view
5.
You can provide additional information about how a resource is scheduled by doing which of the following?
1.
changing the Max. Units
2.
establishing a project calendar
3.
adding a resource note
4.
setting constraints
6.
For which resource is the standard rate listed per tracking unit of consumption?
1.
material
2.
equipment
3.
people
4.
all of the above
7.
If you have four electricians whom can each work part
‐
time (4 hours rather than 8), which of the
following values should you assign to Max. Units for the resource
“electrician”?
1. 50%
2. 25%
3. 100%
4. 200%
8.
If you assign a base calendar to a resource, which of the following is true?
1.
The base calendar dictates the resource's vacation days.
2.
The base calendar gives all the available time to work on the project.
3.
The base calendar gives the basic days/hours for the resource, but the resource's calendar can have exceptions to those days/hours.
4.
The resource calendar contains all nonworking days for the entire project.
9.
To add vacation days to the calendar for an individual work resource, which dialog box would you use?
1.
Resource Information
2.
Resource Notes
3.
Change Working Time
4.
none of the above
10. Which of the following is a reason why it is often difficult to get cost information for people resources?
1.
The information is often confidential.
2.
The information is too complex to calculate.
3.
The information changes too frequently.
4.
The costs are large in comparison with other resource costs.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Submit the above questions in an MS Word or PDF file named: firstname-lastname.doc or .pdf - eg tim-nelson.doc
Competency Assessment Project 2-1: Adding People Resources for
Hiring a New Employee
(15 Points)
In the previous lesson, you entered the tasks of a project schedule for hiring a new employee. In this project, you will add some of the people resources that will be responsible for performing those tasks.
GET READY. LAUNCH Microsoft Project if it is not already running. OPEN Hiring New Employee 2
‐
1
from the data files for this lesson.
1.
Click the View tab. In the Resource Views group, select Resource Sheet
.
2.
In the Resource Sheet view, click the empty cell directly below the Resource Name column
heading.
3.
Enter the following resource names into the simple Resource Sheet:
o
Gabe Mares
o
Barry Potter
o
Amy Rusko
o
Jeff Smith
4.
SAVE the project as Hire New Employee and then CLOSE the file.
LEAVE Project open for the next exercise.
Project 2-2: Entering Pay Rates for an Office Remodel (15 Points)
You are in charge of the remodeling project for the kitchen and lunchroom for your office. Your facilities manager has just provided you with the resource pay rates for this project. In this project, you will enter the pay rates in the project schedule.
GET READY. OPEN Office Remodel 2
‐
2 from the data files for this lesson.
1.
Select the Resource Sheet view.
2.
For the drywall resource, click the Type field drop
‐
down arrow, select Material
, and then press
Tab
.
3.
In the Material Label cell, key sheet
.
4.
For the drywall screws resource, click the Type field drop
‐
down arrow, select Material
, and then
press Tab
.
5.
In the Material Label cell, key 1 pound
.
6.
In the Resource Sheet, click the Std. Rate field for resource 1, Toby Nixon.
7.
Key 1200/w and press Enter
.
8.
SAVE the project as Office Remodel and then CLOSE the file.