Part 1 Costing Systems_Sol 14 Aug 2022
pdf
keyboard_arrow_up
School
Cedar Mount Academy *
*We aren’t endorsed by this school
Course
AC1
Subject
Industrial Engineering
Date
Jun 7, 2024
Type
Pages
66
Uploaded by HighnessRiverHerring36
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
1/66
Question 1
1.D.2.h
tb.ab.cost.010_1809
LOS: 1.D.2.h
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: medium
Bloom Code: 3
Sip Healthy Company manufactures juicers and blenders. Management has compiled the following information:
Juicer
Blender
Units produced
7,500
15,000
Direct materials/unit
$62.50 $40.00
Direct labor/unit
$15.00
$5.00
Direct labor hours, production 22,500
15,000
Machine hours, production
30,000 20,000
Batches
10,000 15,000
Production costs are as follows:
Activity
Cost
Activity Driver
Machining
$420,000 Machine hours
Moving/ warehousing $255,000 Direct labor hours
Equipment setup
$160,000 Batches
Total overhead cost
$835,000
What is the cost per driver unit for the cost of machining?
$6.80 per direct labor hour.
$37.11 per unit.
Rationale
$6.80 per direct labor hour.
Incorrect. This amount is the cost per driver unit for moving/warehousing. Make sure to use the correct production cost and correct activity driver
for machining.
Rationale
$6.40 per batch.
Incorrect. This amount is the cost per driver unit for equipment setup. Make sure to use the correct production cost and correct activity driver for
machining.
Rationale
$8.40 per machine hour.
Correct. The overhead cost for machining is $420,000, and the activity driver for machining is machine hours. The two products had 30,000 and
20,000 machine hours; therefore, the cost per driver unit for machining is $8.40 per machine hour ($420,000 ÷ (30,000 + 20,000)).
Rationale
$37.11 per unit.
Incorrect. This amount is the cost per unit using a traditional costing system. Make sure to use the correct production cost and correct activity
driver for machining.
$8.40 per machine hour.
Correct
$6.40 per batch.
Your Answer
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
2/66
Question 2
1.D.2.f
tb.proc.c.008_1809
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: medium
Bloom Code: 3
Sweetums Syrup adds raw materials costs at the beginning of its manufacturing process and incurs conversion costs uniformly throughout the process.
At the beginning of last month, Sweetums had 20,000 units that were 40% complete in its Beginning Work-in-Process Inventory. Over the course of the
month, the company began production of 150,000 units; at month's end, 90,000 of those units were finished and transferred out, while the remaining
units were 90% complete. Using the Weighted Average method, what was Sweetums’ equivalent units of production for materials for the month?
98,000 equivalent units.
162,000 equivalent units.
240,000 equivalent units.
Rationale
170,000 equivalent units.
Correct. The first step is to calculate the number of units in Ending Work-in-Process Inventory. Since units to account for must equal units
accounted for, Ending Work-in-Process Inventory can be solved for as follows:
Units to account for are Beginning Work-in-Process plus units started (20,000 + 150,000 = 170,000).
Units accounted for are units transferred out plus Ending Work-in-Process (90,000 + Ending Work-in-Process Inventory).
20,000 + 150,000 = 90,000 + Ending Work-in-Process Inventory
Ending Work-in-Process Inventory = 170,000 −
90,000
Ending Work-in-Process Inventory = 80,000 units.
Because Ending Work-in-Process is 100% complete with respect to materials (they are added at the beginning of the process), equivalent units of
production under the Weighted Average method = 170,000 units (90,000 + (80,000 × 100%)).
Rationale
98,000 equivalent units.
Incorrect. This number is the equivalent units of production assuming Ending Work-in-Process is 10% (100% −
90%) complete. Materials are added
at the beginning of the process, so the Ending Work-in-Process is not 10% complete with respect to materials.
Rationale
162,000 equivalent units.
Incorrect. This number is the equivalent units for conversion costs. Materials are added at the beginning of the process, so the Ending Work-in-
Process is not 90% complete with respect to materials.
Rationale
240,000 equivalent units.
Incorrect. Units accounted for is not calculated as units started plus units transferred out. Units started includes units that have been transferred
out by the end of the month.
170,000 equivalent units.
Correct
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
3/66
Question 3
1.D.2.f
tb.proc.c.007_1809
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: medium
Bloom Code: 3
This month, the Roasting Department of Java Coffee Company completed and transferred out 75,000 one-pound bags of coffee. The department also
had 25,000 units that were 80% complete with respect to conversion costs and no Beginning Work-in-Process. Using the FIFO method, how many
equivalent units of production for conversion costs does the department have for the month?
70,000
80,000
Rationale
70,000
Incorrect. When calculating equivalent units of output, make sure to add, not subtract, the equivalent units in Ending Work-in-Process, and multiply
by the percent complete, not the complement.
Rationale
95,000
Correct. Since there is no beginning Work-in-Process Inventory, the equivalent units of output equal units transferred out plus the equivalent units
in Ending Work-in-Process; therefore, the equivalent units of production equals 95,000 (75,000 + (25,000 × 80%)).
Rationale
100,000
Incorrect. When calculating equivalent units of output, make sure to calculate the equivalent units of the Ending Work-in-Process.
Rationale
80,000
Incorrect. When calculating equivalent units of output, make sure to multiply the units in Ending Work-in-Process by the percent complete, not the
complement.
95,000
Correct
100,000
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
4/66
Question 4
1.D.2.b
1C2-LS04
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 4
A company uses job order costing and begins the period with no finished goods inventory, but with a beginning work-in-process (WIP) of these jobs:
Job #15 = $42,000
Job #16 = $33,000
Job #17 = $12,000
Total WIP = $87,000
During the period, a new job is started (Job #18) and these costs are incurred:
Direct materials: $100,000 (20% each for Jobs #15, #16, #17 and 40% for Job #18)
Direct labor: 5,000 hours at $15 per hour (hours for Jobs #15, #16, #17, and #18 are 1,500, 1,500, 1,200, and 800, respectively)
Factory overhead (using a predetermined rate where total overhead for the year is estimated to be $200,000 and total direct labor (cost driver) is
50,000 hours).
Jobs #15 and #16 are completed and sold during the period. What is ending WIP inventory?
$98,000.
$12,000.
Rationale
$90,000.
This answer is incorrect. This answer did not consider the costs in beginning work-in-process for Job #17. Further, this answer did not consider the
overhead for either job.
Rationale
$98,000.
TThis answer is incorrect. This answer did not consider the costs in beginning work-in-process for Job #17.
Rationale
$12,000.
This answer is incorrect. This answer did not consider costs incurred for the two jobs during the period.
Rationale
$110,000.
The cost of the jobs not completed can be broken down as: (note the predetermined overhead rate is $200,000 ÷ 50,000 or $4/direct labor hour).
Job #17
Job #18
Beg. WIP
$12,000
$ 0
Current:
DM
20,000
40,000 (20% and 40% of $100,000)
DL
18,000
12,000 (1,200, 800 hours x $15/hour)
OH
4,800
3,200 (1,200, 800 hours x $4/hour)
Total
$54,800
$55,200 Grand total = $110,000
$110,000.
Correct
$90,000.
Your Answer
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
5/66
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
6/66
Question 5
1.D.2.f
tb.proc.c.004_1809
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: medium
Bloom Code: 3
The Cutting Department at the Blanc Company had 4,000 units in Beginning Work-in-Process, 9,000 units transferred out, and 2,000 units in Ending Work-
in-Process. How many units were started by Blanc during the month?
11,000 units.
9,000 units
Rationale
11,000 units.
Incorrect. With units started of 11,000 units, units to account for (Beginning Work-in-Process + Units started) do not equal units accounted for (Units
completed + Ending Work-in-Process).
Rationale
6,000 units.
Incorrect. With units started of 6,000 units, units to account for (Beginning Work-in-Process + Units started) do not equal units accounted for (Units
completed + Ending Work-in-Process).
Rationale
7,000 units.
Correct. In process costing, units to account for (Beginning Work-in-Process + Units started) equals units accounted for (Units transferred out +
Ending Work-in-Process). Units accounted for equals 11,000 (9,000 + 2,000); therefore, units started is calculated as follows:
Units started + 4,000 = 11,000
Units started = 11,000 −
4,000 = 7,000
Rationale
9,000 units
Incorrect. With units started of 9,000 units, units to account for (Beginning Work-in-Process + Units started) do not equal units accounted for (Units
completed + Ending Work-in-Process).
7,000 units.
Correct
6,000 units.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
7/66
Question 6
1.D.2.b
ac.job.oc.007_0820
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: hard
Bloom Code: 5
Contra Bricks manufactures custom brick products and uses job order costing. The following information relates to the fiscal year ending December 31,
20X7.
Beginning balance in Raw Materials Inventory
$13,600
Purchases of raw materials
$211,000
Ending balance in Raw Materials Inventory
$15,100
Beginning balance in Work-in-Process
$18,700
Ending balance in Work-in-Process
$16,500
Direct labor cost
$78,600
Manufacturing overhead applied
$47,900
Actual manufacturing overhead
$44,800
Beginning balance in Finished Goods
$26,200
Ending balance in Finished Goods
$24,500
Sales Revenue
$421,000
Selling expenses
$115,400
General and administrative expenses
$75,900
What is Cost of Goods Manufactured?
$339,700
$335,100
$383,000
Rationale
$339,700
This answer is incorrect. Purchases of raw materials is not used directly in the Cost of Goods Manufactured calculation. First calculate raw materials
used, then use that number in the Cost of Goods Manufactured calculation.
Rationale
$338,200
Correct. The raw materials used in production must first be calculated, then the Cost of Goods Manufactured can be calculated. Raw materials used
in production equals beginning Raw Materials plus purchases of raw materials minus ending Raw Materials. The raw materials used in production
equals $209,500 ($13,600 + $211,000 −
$15,100). Cost of Goods Manufactured equals beginning Work-in-Process plus raw materials used plus direct
labor plus overhead applied minus ending Work-in-Process. Cost of Goods Manufactured equals $338,200 ($18,700 + $209,500 + $78,600 + $47,900 −
$16,500).
Rationale
$335,100
This answer is incorrect. Actual overhead is not used in the calculation of Cost of Goods Manufactured.
Rationale
$383,000
This answer is incorrect. Actual and applied overhead are not used together in the calculation of Cost of Goods Manufactured. Actual overhead
should not be included in this calculation.
$338,200
Correct
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
8/66
Question 7
1.D.2.g
tb.ab.cost.005_1809
LOS: 1.D.2.g
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: medium
Bloom Code: 3
Stockholm Skis makes two different products: downhill racing skis and cross-country skis. The company uses an ABC system that features the following
activity cost pools and drivers:
Cost Pool
Driver
Manufacturing
Machine hours
Assembly
Parts used
Ordering and receiving Purchase orders processed
Painting
Square inches painted
Sanding
Square inches sanded
Inspection and testing
Inspections performed
For the coming year, Stockholm estimates that it will use 36,000 parts in the assembly of its downhill skis and 31,500 parts in the assembly of its cross-
country skis. Based on this information, we can conclude that:
Downhill skis will account for a larger percentage of overhead costs from the manufacturing pool.
Cross-country skis will account for a smaller percentage of overhead costs from the inspection and testing pool.
Rationale
Downhill skis will account for a larger percentage of overhead costs from the manufacturing pool.
Incorrect. The driver for the manufacturing pool is machine hours, and we have no information about the machine hours used for each product;
therefore, we cannot determine how the overhead will be allocated for the manufacturing pool.
Rationale
Cross-country skis will account for a smaller percentage of overhead costs from the inspection and testing pool.
Incorrect. The driver for the inspection and testing pool is inspections performed, and we have no information about the inspections performed for
each product; therefore, we cannot determine how the overhead will be allocated for the inspection and testing pool.
Rationale
Downhill skis will account for a larger percentage of overhead costs from the ordering and receiving pool.
Incorrect. The driver for the ordering and receiving pool is purchase orders processed, and we have no information about the purchase orders
processed for each product; therefore, we cannot determine how the overhead will be allocated for the ordering and receiving pool.
Rationale
Cross-country skis will account for a smaller percentage of overhead costs from the assembly pool.
Correct. We have information about the parts used for each type of ski, and parts used is the driver for assembly costs. Using activity-based costing,
any product which uses a greater amount of the driver will be assigned more overhead than a product which uses a smaller amount of the driver.
Cross-country skis will account for a smaller percentage of overhead costs from the assembly pool.
Correct
Downhill skis will account for a larger percentage of overhead costs from the ordering and receiving pool.
Your Answer
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
9/66
Question 8
1.D.2.c
1C2-LS19
LOS: 1.D.2.c
Lesson Reference: Process Costing
Difficulty: medium
Bloom Code: 3
A company that uses a process costing system inspects its goods at the 60% stage of completion. If the firm's ending work-in-process inventory is 80%
complete, how would the firm account for its normal and abnormal spoilage?
* Source: Retired ICMA CMA Exam Questions.
Both normal and abnormal spoilage costs would be added to the cost of the good units completed during the period.
Normal spoilage costs would be added to the cost of the good units completed during the period; in contrast, abnormal spoilage costs would be
written off as a loss.
Both normal and abnormal spoilage costs would be written off as an expense of the period.
Rationale
Both normal and abnormal spoilage costs would be added to the cost of the good units completed during the period.
This answer is incorrect. The firm would not account for its normal and abnormal spoilage by adding both normal and abnormal spoilage costs to
the cost of the good units completed during the period.
Rationale
Normal spoilage costs would be allocated between the cost of good units completed during the period and the ending work-in-process
inventory. In contrast, abnormal spoilage costs would be written off as a loss.
If a firm has normal and abnormal spoilage, the normal spoilage costs would be allocated between the cost of good units completed during the
period and the ending work-in-process inventory. In contrast, abnormal spoilage costs would be written off as a loss.
Rationale
Normal spoilage costs would be added to the cost of the good units completed during the period; in contrast, abnormal spoilage costs
would be written off as a loss.
This answer is incorrect. The firm would not account for its normal spoilage by adding the entire cost to good units completed during the period if
there is ending inventory.
Rationale
Both normal and abnormal spoilage costs would be written off as an expense of the period.
This answer is incorrect. Normal spoilage would not be written off as an expense of the period. Abnormal spoilage, however, will be written off as a
loss.
Normal spoilage costs would be allocated between the cost of good units completed during the period and the ending work-in-process inventory. In
contrast, abnormal spoilage costs would be written off as a loss.
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
10/66
Question 9
1.D.2.a
ac.job.oc.003_1809
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 2
Using job order costing, what general ledger accounts are involved when a job is delivered to the customer?
Increase (debit) Finished Goods Inventory and decrease (credit) Work-in-Process Inventory.
Increase (debit) Cost of Goods Sold and decrease (credit) Work-in-Process Inventory.
Rationale
Increase (debit) Finished Goods Inventory and decrease (credit) Work-in-Process Inventory.
This answer is incorrect. The cost flows of a job order costing system flow from Work-in-Process Inventory to Finished Goods inventory when a job is
finished, not when a job is delivered to the customer.
Rationale
Increase (debit) Cost of Goods Sold and decrease (credit) Finished Goods Inventory.
Correct. The cost flows of a job order costing system flow from Finished Goods Inventory to Cost of Goods Sold as jobs are delivered to customers.
Rationale
Increase (debit) Finished Goods Inventory and decrease (credit) Cost of Goods Sold.
This answer is incorrect. The cost flows of a job order costing system flow from Work-in-Process Inventory to Finished Goods Inventory when jobs
are completed, and flow from Finished Goods Inventory to Cost of Goods Sold when jobs are delivered to customers. Therefore, a debit to Finished
Goods Inventory would not equal a credit to Cost of Goods Sold.
Rationale
Increase (debit) Cost of Goods Sold and decrease (credit) Work-in-Process Inventory.
This answer is incorrect. The cost flows of a job order costing system flow from Work-in-Process Inventory to Finished Goods Inventory when jobs
are completed, and flow from Finished Goods Inventory to Cost of Goods Sold when jobs are delivered to customers.
Increase (debit) Cost of Goods Sold and decrease (credit) Finished Goods Inventory.
Correct
Increase (debit) Finished Goods Inventory and decrease (credit) Cost of Goods Sold.
Your Answer
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
11/66
Question 10
1.D.2.a
tb.job.oc.010_1809
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 3
Wolf Company used $5,940 of indirect raw materials and $56,700 of direct raw materials during the period. The company incurred $37,800 of direct
factory labor and $6,480 of indirect factory labor during the period. What amount will Wolf assign to Manufacturing Overhead?
$50,220
$62,640
$94,500
Rationale
$50,220
Incorrect. Direct factory labor is not considered manufacturing overhead.
Rationale
$62,640
Incorrect. Direct raw materials are not considered manufacturing overhead. Additionally, indirect factory labor is considered manufacturing
overhead.
Rationale
$12,420
Correct. The amounts assigned to manufacturing overhead are indirect raw materials and indirect factory labor; therefore, manufacturing overhead
equals $12,420 ($5,940 + $6,480).
Rationale
$94,500
Incorrect. Direct raw materials and direct factory labor are not considered manufacturing overhead.
$12,420
Correct
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
12/66
Question 11
1.D.2.b
tb.job.oc.044_1809
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 3
Harmony Co. used $31,920 of direct materials, worked 840 direct labor hours, and utilized 560 machine hours to complete a custom fishing boat for a
customer. Harmony's direct labor rate is $22.00 per hour and overhead is applied based on machine hours at $34.00 per hour. What is the total
manufacturing cost for this custom boat?
$78,960
$79,520
Rationale
$78,960
Incorrect. Overhead is incorrectly applied in this calculation. Overhead should be applied using machine hours, not direct labor hours.
Rationale
$50,400
Incorrect. This amount is the direct materials plus the direct labor; however, it incorrectly excludes applied overhead.
Rationale
$69,440
Correct. The total manufacturing cost equals direct materials plus direct labor plus applied overhead. The total manufacturing cost for the custom
boat equals $69,440 ($31,920 + (840 × $22.00) + (560 × $34.00)).
Rationale
$79,520
Incorrect. This amount is calculated as direct materials, plus direct labor, plus applied overhead, assuming the direct labor rate is $34.00 per hour;
however, the direct labor rate is $22.00 per hour.
$69,440
Correct
$50,400
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
13/66
Question 12
1.D.2.f
1C2-AT12
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: medium
Bloom Code: 4
Kimbeth Manufacturing uses a process cost system to manufacture dust density sensors for the mining industry. The following information pertains to
operations for the month of May.
Units
Beginning work-in-process inventory, May 1
16,000
Started in production during May
100,000
Completed production during May
92,000
Ending work-in-process inventory, May 31
24,000
The beginning inventory was 60% complete for materials and 20% complete for conversion costs. The ending inventory was 90% complete for materials
and 40% complete for conversion costs.
Costs pertaining to the month of May are:
Beginning inventory costs are: materials, $54,560; direct labor, $20,320; and factory overhead, $15,240.
Costs incurred during May are: materials used, $468,000; direct labor, $182,880; and factory overhead, $391,160.
Using the first-in, first-out (FIFO) method, the equivalent units of production for materials are:
98,400 units.
100,000 units.
Rationale
98,400 units.
This answer is incorrect. This answer represents the equivalent units for conversion, not materials.
Rationale
104,000 units.
The FIFO approach follows the production flow and assumes that units will be sold in the order in which they were placed in inventory.
To calculate the equivalent units of production for materials using FIFO, calculate the equivalent units for materials for:
1. units in beginning inventory,
2. products started into production during the month, and,
3. units in ending inventory.
First, the 16,000 units in the beginning inventory would be completed, requiring the addition of 6,400 [(16,000) × (1 – 0.6)] equivalent units for
materials.
Next, of the 100,000 units started during the month, 76,000 would be completed, requiring 76,000 equivalent units for materials.
(92,000 units completed during month −
16,000 units from beginning inventory = 76,000 units)
Lastly, of the 100,000 units started, 24,000 would be in the ending inventory, 90% complete with respect to materials, requiring 21,600 [(0.90) ×
(24,000)] equivalent units for materials.
Therefore, the total equivalent units for materials would be 6,400 + 76,000 + 21,600 = 104,000.
Rationale
100,000 units.
104,000 units.
Correct
88,000 units.
Your Answer
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
14/66
This answer is incorrect. This answer represents the units started in production during May, not the equivalent units for materials.
Rationale
88,000 units.
This answer is incorrect. For materials, this answer calculated beginning work-in-process equivalent units with 60% instead of 40% and calculated
ending work-in-process with 10% instead of 90%.
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
15/66
Question 13
1.D.2.b
tb.job.oc.034_1809
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 4
Elaine's Fine Furniture has just started operations. Elaine's had the following job cost sheets for the month of January.
Job Number
Start Date
End Date
Delivery Date
Total Cost
J1-1
Jan 2
Jan 6
Jan 15
$19,582
J1-2
Jan 4
Jan 14
Jan 19
$10,631
J1-3
Jan 9
Jan 22
Jan 25
$7,526
J1-4
Jan 17
Feb 23
$6,312
J1-5
Jan 18
Jan 29
Feb 14
$3,856
J1-6
Jan 24
Jan 31
Feb 22
$2,033
J1-7
Jan 29
Feb 17
Feb 28
$17,522
J1-8
Jan 30
Feb 25
$10,267
What was the balance in Elaine's Finished Goods Inventory account as of January 31?
$34,101
$23,411
Rationale
$37,739
Incorrect. This amount is the total of all jobs started, finished, and delivered in January, which totals Cost of Goods Sold for January, not Finished
Goods Inventory.
Rationale
$34,101
Incorrect. This amount is the total of all jobs that were started in January and had an end date in February, which totals Work-in-Process Inventory,
not Finished Goods Inventory.
Rationale
$5,889
Correct. Finished Goods Inventory as of January 31 is the total of all jobs with an end date in January but a delivery date in February, which are jobs
J1-5 and J1-6; therefore, the Finished Goods Inventory balance equals $5,889 ($3,856 + $2,033).
Rationale
$23,411
Incorrect. This amount is the total of jobs J1-5, J1-6, and J1-7. Make sure to include only those jobs with an end date in January in the Finished
Goods Inventory as of January 31.
$5,889
Correct
$37,739
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
16/66
Question 14
1.D.3.m
cma11.p1.t1.me.0073_0820
LOS: 1.D.3.m
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: hard
Bloom Code: 4
A company is implementing an activity-based budgeting system. Setup overhead is allocated based on setup hours, and manufacturing overhead is
allocated based on direct manufacturing labor hours. Budget information is listed in the table below.
Cost driver information
Product A
Product B
Number of units per batch
50
25
Setup time per batch
1.75 hours 1.25 hours
Direct manufacturing labor time per batch 1.00 hours 0.75 hours
The company plans to produce 1,000 units of Product A and 750 units of Product B. The activity rates are $100 per setup hour and $150 per direct
manufacturing labor hour. What is the total budgeted overhead (OH)?
*Source: Retired ICMA CMA Exam Questions.
$10,063
$15,125
$20,125
Rationale
$10,063
This answer is incorrect. The batch size for Product B is not 50 units per batch.
Rationale
$13,625
Product A
Rate/batch
# batches
Time/batch
Allocated OH
Setup
$100/hr 1,000/50 = 20
1.75 hr
$3,500
Manf. OH
$150/hr 1,000/50 = 20
1 hr
$3,000
Product B
Setup
$100/hr
750/25 = 30
1.25 hr
$3,750
Manf. OH
$150/hr
750/25 = 30
0.75 hr
$3,375
$13,625
Rationale
$15,125
This answer is incorrect. The set-up time for Product B is not 1.75 hours per batch.
Rationale
$20,125
This answer is incorrect. The batch size for Product A is not 25 units per batch.
$13,625
Correct
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
17/66
Question 15
1.D.2.a
ac.job.oc.004_0820
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 3
Ahrens Advertising creates ad campaigns for small local businesses. Ahrens offers three services—print, radio, and online. Customers choose which
combination of ad types they would like and then Ahrens produces three ads for each of the selected types. Which cost system should Ahrens use and
why?
A job order cost system because production of an ad campaign is a service rather than a manufactured good
A process cost system because each client can select ad types from only three possible options
A process cost system because clients receive a set number of ads for each type of advertising they select
Rationale
A job order cost system because production of an ad campaign is a service rather than a manufactured good
This answer is incorrect. A company would use job order costing instead of process costing when its services require different amounts of materials,
labor, and overhead. Both a job order cost system and a process cost system can be used for either services or manufactured goods.
Rationale
A process cost system because each client can select ad types from only three possible options
This answer is incorrect. Even though the options are limited, each order will require different amounts of labor hours and overhead to produce a
particular combination of ad types. Process costing is appropriate when each service involves similar amounts of materials, labor, and overhead.
Rationale
A job order cost system because each ad campaign is a specific job with its own set of costs
Correct. A process cost system assumes each service takes similar amounts of materials, labor, and overhead while a job order cost system can
account for different materials, labor, and overhead for each service. Since each advertising service will require different amounts of labor and
overhead to produce a particular combination of ad types, a job cost system would be most appropriate.
Rationale
A process cost system because clients receive a set number of ads for each type of advertising they select
This answer is incorrect. Even though the number of ads for each type of advertising is set, each service can require different amounts of labor
hours and overhead to produce a particular combination of ad types. Process costing is appropriate when each service takes similar amounts of
materials, labor, and overhead.
A job order cost system because each ad campaign is a specific job with its own set of costs
Correct
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
18/66
Question 16
1.D.2.h
tb.ab.cost.008_1809
LOS: 1.D.2.h
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: medium
Bloom Code: 3
Mandy Appliances manufactures toaster ovens. Each oven contains 15 parts totaling $35 in direct materials. Each oven requires 3 hours of machine time
at $15 per machine hour, and 1.5 hours for inspection. The company has the following information regarding activities, activity drivers, and cost per
driver units:
Activity
Activity Driver
Cost per Driver Unit
Machining
Machine hours
$3.75/machine hour
Materials handling Number of parts
$1.20/part
Assembly
Number of parts
$0.85/part
Inspection
Inspection hours $11.80/inspection hour
What is the cost of assembly per toaster oven?
$18.00
$11.25
$17.70
Rationale
$18.00
Incorrect. This amount is the cost of materials handling per toaster oven. Make sure to use the correct cost per driver unit and the correct activity in
the driver for assembly.
Rationale
$12.75
Correct. The cost per driver unit for assembly is $0.85 per part, and each toaster oven has 15 parts; therefore, the cost of assembly per toaster oven
is $12.75 ($0.85 × 15).
Rationale
$11.25
Incorrect. This amount is the cost of machining per toaster oven. Make sure to use the correct cost per driver unit and the correct activity in the
driver for assembly.
Rationale
$17.70
Incorrect. This amount is the inspection cost per toaster oven. Make sure to use the correct cost per driver unit and the correct activity in the driver
for assembly.
$12.75
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
19/66
Question 17
1.D.2.b
ac.job.oc.006_0820
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 3
Frank's Frames makes custom silver picture frames engraved with names and significant dates, such as weddings or births. Although the frames can be
partially completed in advance, all frames remain in the Work-in-Process Inventory account until the final engraving is completed. Job AAA01 was
completed in January. At the beginning of January, costs accumulated on the frame were direct materials of $40, direct labor of $60, and overhead of
$16. Completing the frame required 1.5 hours of direct labor at $15 per hour. Overhead is applied at $4 per direct labor hour. What is the total cost on the
job cost sheet for Job AAA01 at the end of January?
$122.50
$116.00
$128.60
Rationale
$144.50
Correct. The total cost of the job is the total of the costs incurred in January plus the costs to finish the job.
Total costs = ($40 + $60 + $16) + ((1.5 × $15) + (1.5 × 4))
Total costs = $116 + $28.50 = $144.50
Rationale
$122.50
This answer is incorrect. This amount is the sum of materials and labor at the beginning of January plus the labor added in January. Applied
overhead is a part of the total cost of the job as well.
Rationale
$116.00
This answer is incorrect. This amount is the total of all costs incurred prior to January. The total cost of the job includes costs added to complete
the job.
Rationale
$128.60
This answer is incorrect. This amount does not include the overhead applied prior to January. The total cost of the job includes all costs incurred to
complete the job.
$144.50
Correct
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
20/66
Question 18
1.D.2.b
1C1-LS36
LOS: 1.D.2.b
Lesson Reference: Process Costing
Difficulty: medium
Bloom Code: 4
Exhibit B
The estimated unit costs for a company using full absorption costing and a plan to produce 20,000 units this period are as follows:
Sales price per unit
$200
Direct materials/unit
$ 50
Direct labor/unit
$ 40
Variable overhead/unit
$ 10
Fixed overhead/unit
$
8
Variable selling costs/unit $
3
Fixed selling costs/unit
$
2
Using information from Exhibit B, what are conversion costs per unit?
$18.
$113.
$108.
Rationale
$18.
This answer is incorrect. This answer did not consider the direct labor costs.
Rationale
$113.
This answer is incorrect. This answer incorrectly included the cost of direct materials, variable selling, and fixed selling.
Rationale
$108.
This answer is incorrect. This answer incorrectly included the cost of direct materials.
Rationale
$58.
Conversion costs per unit are defined as direct labor per unit plus overhead per unit. In this case, $40 + $10 + $8 = $58.
$58.
Correct
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
21/66
Question 19
1.D.3.m
1C2-CQ14
LOS: 1.D.3.m
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: hard
Bloom Code: 6
The Chocolate Baker specializes in chocolate baked goods. The firm has long assessed the profitability of a product line by comparing revenues to the
cost of goods sold. However, Barry White, the firm's new accountant, wants to use an activity-based costing system that takes into consideration the cost
of the delivery person. Listed below are activity and cost information relating to two of Chocolate Baker's major products.
Muffins
Cheesecake
Revenue
$53,000
$46,000
Cost of goods sold
26,000
21,000
Delivery Activity
Number of deliveries
150
85
Average length of delivery
10 Minutes
15 Minutes
Cost per hour for delivery
$20.00
$20.00
Using activity-based costing, which one of the following statements is correct?
The cheesecakes are $75 more profitable.
The muffins are $2,000 more profitable.
Rationale
The cheesecakes are $75 more profitable.
This answer is incorrect. This answer only considers delivery costs and does not also consider the gross margin on the products.
Rationale
The muffins are $2,000 more profitable.
This answer is incorrect. This answer did not consider the delivery costs and only considers the gross margin on the products.
Rationale
The muffins have a higher profitability as a percentage of sales and, therefore, are more advantageous.
This answer is incorrect. The cheesecake earns more profit per delivery. Therefore, the cheesecake has a higher profitability as a percentage of sales
than the muffins.
Rationale
The muffins are $1,925 more profitable.
The gross profit for muffins after assigning delivery costs would be calculated as:
Gross profit, muffins = revenue −
cost of goods sold −
assigned delivery costs
Gross profit, muffins = $53,000 −
$26,000 −
assigned delivery costs
Gross profit, muffins = $27,000 −
assigned delivery costs
The assigned delivery costs are calculated as:
Assigned delivery costs, muffins = (number of deliveries) × (cost per delivery)
Assigned delivery costs, muffins = (150 deliveries) × (10 minutes ÷ 60 minutes) × ($20 per hour) = $500
Gross profit for muffins = $27,000 −
$500 = $26,500
The muffins are $1,925 more profitable.
Correct
The muffins have a higher profitability as a percentage of sales and, therefore, are more advantageous.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
22/66
The gross profit for cheesecake after assigning delivery costs would be calculated as:
Gross profit, cheesecake = revenue −
cost of goods sold −
assigned delivery costs
Gross profit, cheesecake = $46,000 −
$21,000 −
assigned delivery costs
Gross profit, cheesecake = $25,000 −
assigned delivery costs
The assigned delivery costs are calculated as:
Assigned delivery costs, cheesecake = (number of deliveries) × (cost per delivery)
Assigned delivery costs, cheesecake = (85 deliveries) × (15 minutes ÷ 60 minutes) × ($20 per hour) = $425
Gross profit for cheesecake = $25,000 −
$425 = $24,575
The gross profit for cheesecake is $1,925 less than the gross profit for muffins.
$26,500 −
$24,575 = $1,925.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
23/66
Question 20
1.D.2.b
1C2-CQ03
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: hard
Bloom Code: 5
Loyal Co. produces three types of men's undershirts: T-shirts, V-neck shirts, and athletic shirts. In the Folding and Packaging Department, operations
costing is used to apply costs to individual units, based on the standard time allowed to fold and package each type of undershirt. The standard time to
fold and package each type of undershirt is as follows.
T-shirt
40 seconds per shirt
V-neck shirt
40 seconds per shirt
Athletic shirt 20 seconds per shirt
During the month of April, Loyal produced and sold 50,000 T-shirts, 30,000 V-neck shirts, and 20,000 athletic shirts. If costs in the Folding and Packaging
Department were $78,200 during April, how much folding and packaging cost should be applied to each T-shirt?
$0.0217.
$1.5640.
Rationale
$0.0217.
This answer is incorrect. This answer represents the cost rate per second, not the cost applied to each T-shirt.
Rationale
$0.7820.
This answer is incorrect. This answer did not consider that different shirts take different amounts of time to produce and that the costs should be
allocated accordingly.
Rationale
$0.8689.
The folding and packaging cost applied to each T-shirt can be calculated as:
Folding and packaging cost applied = (40 seconds) × (cost rate per second)
The cost rate per second = ($78,200) ÷ (total seconds)
Cost rate per second = ($78,200) ÷ [(50,000 T-shirts) × (40 seconds per shirt) + (30,000 V-neck shirts) × (40 seconds per shirt) + (20,000 athletic shirts) ×
(20 seconds per shirt)]
Cost rate per second = ($78,200) ÷ (2,000,000 seconds +1,200,000 seconds + 400,000 seconds)
Cost rate per second = $78,200 ÷ 3,600,000 seconds
Cost rate per second = $0.0217222 per second
Cost applied to each T-shirt = (40 seconds) × (0.0217222 per second) = $0.8689.
Rationale
$1.5640.
This answer is incorrect. This answer divided the Folding and Packaging Department costs by the amount of T-shirts. However, the answer did not
consider the other shirts that were also produced.
$0.8689.
Correct
$0.7820.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
24/66
Question 21
1.D.2.a
tb.job.oc.022_1809
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 2
What factors should a service company consider when determining whether to use process costing or job order costing?
Whether the services are provided continuously. If they are continuous, process costing is appropriate; if they are not continuous, job order costing is
appropriate.
Whether the services are provided independently of other services. If they are independent, job order costing is appropriate; if they are not, process
costing is appropriate.
Whether a service is provided or a good is manufactured. If a service is provided, job order costing is appropriate; if a good is manufactured, process
costing is appropriate.
Rationale
Whether the services are provided continuously. If they are continuous, process costing is appropriate; if they are not continuous, job
order costing is appropriate.
Incorrect. Continuous production of services is not a factor to consider when determining whether to use process costing or job order costing.
Rationale
Whether the services are provided independently of other services. If they are independent, job order costing is appropriate; if they are
not, process costing is appropriate.
Incorrect. Independence of services is not a factor to consider when determining whether to use process costing or job order costing.
Rationale
Whether a service is provided or a good is manufactured. If a service is provided, job order costing is appropriate; if a good is
manufactured, process costing is appropriate.
Incorrect. This is not a factor to consider when determining whether to use process costing or job order costing because both manufacturing
industries and service industries can use either type of costing system.
Rationale
Whether the services provided require similar amounts of materials, labor, and overhead. If they require similar inputs, process costing
is appropriate; if the inputs are not similar, job order costing is appropriate.
Correct. Process costing is appropriate when all services provided require similar amounts of materials, labor, and overhead; while job order
costing is appropriate when all services provided require unique inputs.
Whether the services provided require similar amounts of materials, labor, and overhead. If they require similar inputs, process costing is appropriate;
if the inputs are not similar, job order costing is appropriate.
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
25/66
Question 22
1.D.2.a
tb.job.oc.011_1809
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 2
Which of the following indicates that direct materials have been moved from the storeroom to production?
A purchase order.
A customer invoice.
Rationale
A purchase order.
Incorrect. A purchase order means that materials will be added to the materials storeroom because of a purchase of materials.
Rationale
A materials requisition slip.
Correct. When materials are requisitioned, they are moved from the materials storeroom into production.
Rationale
A job order cost sheet.
Incorrect. A job order cost sheet accumulates the total of the direct materials, direct labor, and overhead applied to the job.
Rationale
A customer invoice.
Incorrect. A customer invoice means that the job has been completed and delivered, moving the total cost from Finished Goods Inventory to Cost of
Goods Sold.
A materials requisition slip.
Correct
A job order cost sheet.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
26/66
Question 23
1.D.2.b
tb.job.oc.031_1809
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 3
Sugar Industries manufactures specialized candy dispensers. One of Sugar's customers ordered 500 candy dispensers, Job 317C, which was started in
March and finished on March 31. The job cost sheet for Job 317C as of March 31 shows $1,750 in direct materials, 30 direct labor hours, and 40 machine
hours. The labor rate is $18 per direct labor hour and overhead is applied at the rate of $25 per machine hour. What is the cost per candy dispenser as of
March 31 for Job 317C?
$6.08
$6.94
$4.58
Rationale
$6.08
Incorrect. When calculating applied overhead, make sure to use the correct driver (labor hours or machine hours).
Rationale
$6.94
Incorrect. When calculating the amount of direct labor, make sure to use direct labor hours and not machine hours to calculate the total cost.
Rationale
$4.58
Incorrect. This amount is the total of the materials plus the labor costs divided by number of units. Make sure to calculate applied overhead and
add it to the amount posted to Finished Goods Inventory.
Rationale
$6.58
Correct. The total cost of the job is materials plus labor plus overhead. The total cost equals $3,290 ($1,750 + (30 × $18) + (40 × $25)). The cost per
unit equals total cost divided by the number of dispensers. The cost per unit = $6.58 per candy dispenser ($3,290 ÷ 500 dispensers).
$6.58
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
27/66
Question 24
1.D.2.b
1C2-LS12
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 4
A promotional department for a retailer uses job order costing. At the beginning of the period Job #154 had a work-in-process (WIP) inventory balance of
$5,000. During the current period, Job #154 required $4,000 in direct materials and $6,000 in direct labor. The department has an overhead cost pool of
$80,000 for all jobs. (The pool uses labor-hours as a cost-allocation base.) All jobs in the department consumed 10,000 labor-hours. If Job #154 used 1,000
labor-hours and sold for $34,000, what is its gross profit margin?
$16,000.
$19,000.
$23,000.
Rationale
$16,000.
This answer is incorrect. This answer did not consider the costs in beginning work-in-process.
Rationale
$11,000.
To calculate the gross profit margin, first calculate the indirect cost rate by dividing the overhead cost by the total cost allocation base ($80,000 ÷
10,000 = $8/labor-hour).
Then multiply the indirect cost rate by the actual units of the allocation base for the job ($8/labor-hour × 1,000 labor-hours = $8,000).
This amount plus the beginning work in process and current period direct materials and direct labor costs equals the total costs ($8,000 + $5,000 +
$4,000 + $6,000 = $23,000).
The gross profit margin is the profit less the total costs ($34,000 −
$23,000 = $11,000).
Rationale
$19,000.
This answer is incorrect. This answer did not consider the overhead for the job.
Rationale
$23,000.
This answer is incorrect. This answer represents total costs for the job, not the gross profit margin.
$11,000.
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
28/66
Question 25
1.D.2.f
tb.proc.c.001_1809
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: medium
Bloom Code: 3
Wilson Tech's production cost data for the current period is:
Beginning Work-in-Process 0 units
Units Started
16,000 units
Units Transferred Out
9,800 units
Ending Work-in-Process
6,200 units
Materials are entered at the beginning of the process. The Ending Work-in-Process units are 40% complete as to conversion costs. Using the FIFO
method, what are the equivalent units of production for materials?
12,280 units.
6,200 units.
Rationale
12,280 units.
Incorrect. If materials are entered at the beginning of the process, Ending Work-in-Process is 100%, not 40%, complete with respect to materials.
Rationale
16,000 units.
Correct. If materials are entered at the beginning of the process, Ending Work-in-Process is 100% complete with respect to materials; therefore, the
equivalent units of production equals 16,000 units (9,800 + (6,200 × 100%)).
Rationale
9,800 units.
Incorrect. Equivalent units of production for materials includes the equivalent units of the units in Ending Work-in-Process as well as the units
transferred out.
Rationale
6,200 units.
Incorrect. Equivalent units of production for materials includes the units transferred out as well as the equivalent units of the units in Ending Work-
in-Process.
16,000 units.
Correct
9,800 units.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
29/66
Question 26
1.D.2.a
tb.job.oc.001_1809
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 2
Rubins Resources uses a process cost system to track manufacturing costs. Rubins likely makes:
Cruise ships.
Movies.
Rationale
Cruise ships.
Incorrect. Process costing is not appropriate when finished products are not identical. Cruise ships would have variation in size and features.
Rationale
Movies.
Incorrect. Process costing is not appropriate when finished products are not identical. Movies are individual in their length, content, and costs.
Rationale
Gears.
Correct. Process costing is appropriate for output where all the finished products are identical to each other.
Rationale
Custom houses.
Incorrect. Process costing is not appropriate when finished products are not identical. Custom houses are individual in their sizes and features.
Gears.
Correct
Custom houses.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
30/66
Question 27
1.D.2.h
1D3-LS57
LOS: 1.D.2.h
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: medium
Bloom Code: 3
Young Company is beginning operations, and is considering three alternative ways in which to allocate manufacturing overhead to individual units
produced. Young can use a plantwide rate, departmental rates, or activity based costing. Young will produce many types of products in its single plant,
and not all products will be processed through all departments. In which one of the following independent situations would reported net income for the
first year be the same regardless of which overhead allocation method had been selected?
* Source: Retired ICMA CMA Exam Questions.
All production costs approach those costs that were budgeted.
The sales mix does not vary from the mix that was budgeted.
Rationale
All ending inventory balances are zero.
If a period begins with no inventory balances, reported net income for the first year would be the same regardless of which overhead allocation
method has been selected.
Rationale
All manufacturing overhead is a fixed cost.
This answer is incorrect. Net income for the first year would not be the same regardless of which overhead allocation method had been selected,
even if all manufacturing overhead is a fixed cost.
Rationale
All production costs approach those costs that were budgeted.
This answer is incorrect. Net income for the first year would not be the same regardless of which overhead allocation method had been selected,
even if all production costs approach those costs that were budgeted.
Rationale
The sales mix does not vary from the mix that was budgeted.
This answer is incorrect. Net income for the first year would not be the same regardless of which overhead allocation method had been selected,
even if the sales mix does not vary from the mix that was budgeted.
All ending inventory balances are zero.
Correct
All manufacturing overhead is a fixed cost.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
31/66
Question 28
1.D.2.a
tb.job.oc.017_1809
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 2
A process cost accounting system would most likely be used for:
Motion picture production.
Custom home building.
Rationale
Toy doll production.
Correct. A process cost accounting system assumes each product has similar materials, labor, and overhead. Because each toy doll of the same
model would have similar materials, labor, and overhead, a toy doll producer would be likely to use process cost accounting.
Rationale
Motion picture production.
Incorrect. A process cost accounting system assumes each product has similar materials, labor, and overhead. Because each motion picture is
unique and requires different inputs, motion picture production would not be likely to use process cost accounting.
Rationale
Custom home building.
Incorrect. A process cost accounting system assumes each product has similar materials, labor, and overhead. Because each custom home is
unique and requires different inputs, a custom home builder would not be likely to use process cost accounting.
Rationale
Developing advertising campaigns.
Incorrect. A process cost accounting system assumes each product has similar materials, labor, and overhead. Because each advertising campaign
is unique and requires different inputs, an advertising company would not be likely to use process cost accounting.
Toy doll production.
Correct
Developing advertising campaigns.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
32/66
Question 29
1.D.2.a
tb.job.oc.013_1809
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 2
Tom worked 40 hours during the week ending February 28. On his time ticket, he recorded the following:
Job 123
14 hours
Job 124
8 hours
Job 125
11 hours
Machine maintenance 2 hours
Breaks and travel
5 hours
On Tom's time ticket, how many hours of labor will be allocated to indirect labor?
5 hours indirect labor.
33 hours indirect labor.
Rationale
5 hours indirect labor.
Incorrect. All hours that are not allocated to specific jobs, including machine maintenance, are considered indirect labor.
Rationale
33 hours indirect labor.
Incorrect. Hours that are allocated to specific jobs are considered direct labor, not indirect labor.
Rationale
40 hours indirect labor.
Incorrect. Hours that are allocated to specific jobs are considered direct labor; hours that are not allocated to specific jobs are considered indirect
labor.
Rationale
7 hours are indirect labor.
Correct. The hours that are not allocated to specific jobs are considered indirect labor. In this example, it is the sum of the machine maintenance
and breaks and travel hours, which equals 7 hours (2 hours + 5 hours).
7 hours are indirect labor.
Correct
40 hours indirect labor.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
33/66
Question 30
1.D.2.f
1C2-AT14
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: hard
Bloom Code: 5
Kimbeth Manufacturing uses a process cost system to manufacture dust density sensors for the mining industry. The following information pertains to
operations for the month of May.
Units
Beginning work-in-process inventory, May 1
16,000
Started in production during May
100,000
Completed production during May
92,000
Ending work-in-process inventory, May 31
24,000
The beginning inventory was 60% complete for materials and 20% complete for conversion costs. The ending inventory was 90% complete for materials
and 40% complete for conversion costs.
Costs pertaining to the month of May are:
Beginning inventory costs are: materials, $54,560; direct labor, $20,320; and factory overhead, $15,240.
Costs incurred during May are: materials used, $468,000; direct labor, $182,880; and factory overhead, $391,160.
Using the first-in, first-out (FIFO) method, the equivalent unit cost of materials for May is:
$4.68.
$3.98.
Rationale
$4.68.
This answer is incorrect. This answer divided the material cost by the units started in production instead of the equivalent units for materials.
Rationale
$3.98.
This answer is incorrect. This answer subtracted beginning inventory material cost from material costs incurred during May.
Rationale
$5.03.
This answer is incorrect. This answer included beginning inventory costs when calculating the equivalent unit cost of materials for May.
Rationale
$4.50.
The FIFO approach follows the production flow and assumes that units will be sold in the order in which they were placed in inventory.
In order to compute the cost per equivalent unit for materials, it is first necessary to calculate the number of equivalent units with respect to
materials.
To calculate the equivalent units of production for materials using FIFO, calculate the equivalent units for materials for:
1. units in beginning inventory,
2. products started into production during the month, and,
3. units in ending inventory.
$4.50.
Correct
$5.03.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
34/66
First, the 16,000 units in the beginning inventory would be completed, requiring the addition of 6,400 [(16,000) × (1 −
0.6)] equivalent units for
materials.
Next, of the 100,000 units started during the month, 76,000 would be completed, requiring 76,000 equivalent units for materials. (92,000 units
completed during month −
16,000 units from beginning inventory = 76,000 units)
Lastly, of the 100,000 units started, 24,000 would be in the ending inventory, 90% complete with respect to materials, requiring 21,600 [(0.90) ×
(24,000)] equivalent units for materials.
The total equivalent units for materials would be 6,400 + 76,000 + 21,600 = 104,000.
The cost of materials used is $468,000.
Therefore, the equivalent unit cost for materials = ($468,000 material cost) ÷ (104,000 equivalent units for materials) = $4.50 per unit
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
35/66
Question 31
1.D.2.a
ac.job.oc.001_0820
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 2
Which of the following correctly depicts the flow of inventory costs in a job order cost system?
Work-in-Process Inventory, Raw Materials Inventory, Finished Goods Inventory, Cost of Goods Sold
Cost of Goods Sold, Work-in-Process Inventory, Raw Materials Inventory, Finished Goods Inventory
Rationale
Raw Materials Inventory, Work-in-Process Inventory, Finished Goods Inventory, Cost of Goods Sold
Correct. A business would first purchase and store raw materials in Raw Materials Inventory. The raw materials would then be requisitioned into
Work-in-Process Inventory where labor and overhead are applied. When the goods are finished, they are transferred from Work-in-Process
Inventory to Finished Goods Inventory. Goods that are sold are transferred from Finished Goods Inventory to Cost of Goods Sold.
Rationale
Finished Goods Inventory, Work-in-Process Inventory, Cost of Goods Sold
This answer is incorrect. Since goods are transferred from Work-in-Process Inventory to Finished Goods Inventory, Finished Goods Inventory would
not come before Work-in-Process Inventory when depicting the flow of inventory costs in a job order cost system.
Rationale
Work-in-Process Inventory, Raw Materials Inventory, Finished Goods Inventory, Cost of Goods Sold
This answer is incorrect. Since goods are transferred from Raw Materials Inventory to Work-in-Process Inventory, Work-in-Process Inventory would
not come before Raw Materials Inventory when depicting the flow of inventory costs in a job order cost system.
Rationale
Cost of Goods Sold, Work-in-Process Inventory, Raw Materials Inventory, Finished Goods Inventory
This answer is incorrect. Since Cost of Goods Sold is the final step in the flow of costs in a job order cost system, it would not come before all other
inventory accounts when depicting the flow of inventory costs. In addition, since goods are transferred from Raw Materials Inventory to Work-in-
Process Inventory, Work-in-Process Inventory would not come before Raw Materials Inventory when depicting the flow of inventory costs.
Raw Materials Inventory, Work-in-Process Inventory, Finished Goods Inventory, Cost of Goods Sold
Correct
Finished Goods Inventory, Work-in-Process Inventory, Cost of Goods Sold
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
36/66
Question 32
1.D.2.b
aq.proc.c.001_0820
LOS: 1.D.2.b
Lesson Reference: Process Costing
Difficulty: easy
Bloom Code: 2
A characteristic of products that use a process cost accounting system and are mass produced in a continuous fashion is:
They are grouped in small batches.
They are custom produced at the time an order is received.
Rationale
They are grouped in small batches.
This answer is incorrect. Products that are grouped in small batches generally require different amounts of material, labor, and overhead. This is
not a characteristic of products that are mass produced in a continuous fashion.
Rationale
They are custom produced at the time an order is received.
This answer is incorrect. Products that are custom produced at the time an order is received generally require different amounts of material, labor,
and overhead. This is not a characteristic of products that are mass-produced in a continuous fashion.
Rationale
The accounting system assumes the products require identical amounts of materials, labor, and overhead.
Correct. Process cost accounting assumes each unit requires the same amount of material, labor, and overhead. This is characteristic of products
that are mass produced in a continuous fashion.
Rationale
Their costs are accumulated on job cost sheets.
This answer is incorrect. Accumulating costs on job cost sheets is a characteristic of job order cost accounting, not process cost accounting.
The accounting system assumes the products require identical amounts of materials, labor, and overhead.
Correct
Their costs are accumulated on job cost sheets.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
37/66
Question 33
1.D.2.b
tb.job.oc.042_1809
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 4
John at Tim's Toys was working on a custom-made miniature car for a customer. The job, BCB101, was started in March. At the end of March, the job cost
sheet for BCB101 showed direct materials of $6,000, direct labor of 200 hours at $75 per hour, and overhead of 80% of direct labor cost. During April,
direct materials of $1,700 were added, and John's time ticket showed 50 hours on Job BCB101, 25 hours on Job BCB102, and 40 hours on a new job,
BCB103. Job BCB101 was completed on April 29. What is the total cost of Job BCB101 as of April 29?
$8,450
$26,450
Rationale
$41,450
Correct. The total cost of Job BCB101 equals direct materials plus direct labor plus overhead applied in March and April.
Direct materials = $6,000 + $1,700 = $7,700
Direct labor = (200 + 50) × $75 = $18,750
Overhead applied = $18,750 × 80% = $15,000
Total cost of Job BCB101 = $7,700 + $18,750 + $15,000 = $41,450
Rationale
$33,000
Incorrect. This amount is the total cost applied to Job TBCB101 in March. The total cost of Job BCB101 includes all costs applied in March and April.
Rationale
$8,450
Incorrect. This amount is the total cost applied to Job BCB101 in April. The total cost of Job BCB101 includes all costs applied in March and April.
Rationale
$26,450
Incorrect. This amount is the total of direct labor and overhead for Job TBCB101. The total cost of a job equals direct materials plus direct labor
plus overhead applied.
$41,450
Correct
$33,000
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
38/66
Question 34
1.D.2.e
1C2-LS02d
LOS: 1.D.2.e
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: easy
Bloom Code: 2
A company has a method of collecting and organizing cost information in an accounting system, called (1)_______. This system performs (2)_______,
which (3)_______ indirect costs and (4)_______ direct costs.
(1) cost assignment, (2) cost accumulation, (3) allocates, (4) traces.
(1) cost assignment, (2) cost accumulation, (3) traces, (4) allocates.
(1) cost accumulation, (2) cost assignment, (3) traces, (4) allocates.
Rationale
(1) cost assignment, (2) cost accumulation, (3) allocates, (4) traces.
This answer is incorrect. This answer mixed up cost accumulation and cost assignment.
Rationale
(1) cost assignment, (2) cost accumulation, (3) traces, (4) allocates.
This answer is incorrect. This answer mixed up cost accumulation and cost assignment. Additionally, this answer mixed up allocates and traces.
Rationale
(1) cost accumulation, (2) cost assignment, (3) allocates, (4) traces.
Cost accumulation collects and organizes cost information in an accounting system. Cost assignment uses both allocation and tracing to assign
accumulated costs to a cost object. Indirect relationship costs are allocated and direct relationship costs are traced.
Rationale
(1) cost accumulation, (2) cost assignment, (3) traces, (4) allocates.
This answer is incorrect. This answer mixed up allocates and traces.
(1) cost accumulation, (2) cost assignment, (3) allocates, (4) traces.
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
39/66
Question 35
1.D.2.a
1A4-CQ19
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 4
Playtime Toys estimates that it will sell 200,000 dolls during the coming year. The beginning inventory is 12,000 dolls; the target ending inventory is
15,000 dolls. Each doll requires two shoes which are purchased from an outside supplier. The beginning inventory of shoes is 20,000; the target ending
inventory is 18,000 shoes. The number of shoes that should be purchased during the year is:
203,000 shoes.
201,000 shoes.
Rationale
203,000 shoes.
This answer is incorrect. This answer represents expected production of dolls, not number of shoes to be purchased.
Rationale
398,000 shoes.
This answer is incorrect. This answer used sales estimate instead of production estimate in the calculation of the number of shoes that should be
purchased during the year.
Rationale
201,000 shoes.
This answer is incorrect. This answer used expected production of dolls, not number of shoes needed for expected production of dolls in the
calculation of number of shoes to be purchased. Each doll requires two shoes.
Rationale
404,000 shoes.
The purchase of shoes is calculated as follows:
Purchase of shoes = (production requirement) + (expected ending inventory) −
(expected beginning inventory)
Production requirement = (2 shoes per doll)(number of dolls)
Expected production, dolls = (sales) + (expected ending finished goods inventory) −
(expected beginning finished goods inventory)
Expected production, dolls = 200,000 dolls + 15,000 dolls −
12,000 dolls = 203,000 dolls.
Therefore, the number of shoes to be purchased during the year is calculated as follows:
Number of shoes to be purchased = (2 shoes/doll)(203,000 dolls) + 18,000 shoes −
20,000 shoes
Number of shoes to be purchased = 406,000 shoes + 18,000 shoes −
20,000 shoes = 404,000 shoes
404,000 shoes.
Correct
398,000 shoes.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
40/66
Question 36
1.D.2.f
1C1-LS21d
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: medium
Bloom Code: 4
The following information was gathered for the current period of manufacturing production for a firm:
DM
CC
Total
Beginning WIP
$ 14,000 $ 15,000 $ 29,000
Current Period Costs
$240,000
$200,000
$440,000
Total costs
$254,000
$215,000
$469,000
There were 100 units in beginning work-in-process (WIP), which were 20% complete in direct materials (DM) and 30% complete in conversion costs (CC).
During the period 2,000 units were started in production and 1,900 were completed. Ending WIP inventory was 70% complete in DM and 60% complete in
CC. If the firm uses the first-in, first-out (FIFO) inventory method, what are equivalent units for the period?
DM: 2,120 units; CC: 2,090 units.
DM: 1,900 units; CC: 1,900 units.
DM: 2,040 units; CC: 2,020 units.
Rationale
DM: 2,120 units; CC: 2,090 units.
This answer is incorrect. This answer used 1,900 as the units started and finished, but only 1,800 units were started and finished.
Rationale
DM: 2,020 units; CC: 1,990 units.
Compute the number of units in ending inventory = 100 + 2,000 −
1,900 = 200 units. Compute units to account for = 100 units in beginning WIP +
2,000 units started = 2,100 units. Units started and finished = units to account for −
ending WIP −
beginning WIP completed first = 2,100 −
200 −
100 =
1,800 units. The EU calculation is:
DM
CC
Beginning WIP (100 units)
80 (80%)
70 (70%)
Units started and finished (1,800)
1,800
1,800
Ending WIP (200 units)
140 (70%)
120 (60%)
Total EU
2,020
1,990
Rationale
DM: 1,900 units; CC: 1,900 units.
This answer is incorrect. This answer represents the units completed during the period, but does not consider beginning or ending WIP completion
percentages.
Rationale
DM: 2,040 units; CC: 2,020 units.
This answer is incorrect. This answer represents the equivalent units if the firm uses the weighted-average inventory method, not the first-in, first-
out method.
DM: 2,020 units; CC: 1,990 units.
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
41/66
Question 37
1.D.3.m
tb.ab.cost.032_1809
LOS: 1.D.3.m
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: medium
Bloom Code: 3
The Grelle Company applies overhead based on direct labor hours. For 20x4, the company estimated overhead costs to be $500,000 based on estimated
direct labor hours of 25,000. The actual direct labor hours were 32,000, and actual overhead was $540,000. What was Grelle's predetermined overhead
rate?
$15.625 per direct labor hour.
$21.60 per direct labor hour.
Rationale
$15.625 per direct labor hour.
Incorrect. Actual direct labor hours are not used to calculate the predetermined overhead rate.
Rationale
$20.00 per direct labor hour.
Correct. The predetermined overhead rate is calculated as estimated overhead divided by the estimated base, in this case direct labor hours;
therefore, the predetermined overhead rate equals $20.00 per direct labor hour ($500,000 ÷ 25,000 direct labor hours).
Rationale
$16.875 per direct labor hour.
Incorrect. Actual overhead is not used to calculate the predetermined overhead rate.
Rationale
$21.60 per direct labor hour.
Incorrect. Actual overhead and actual direct labor hours are not used to calculate the predetermined overhead rate.
$20.00 per direct labor hour.
Correct
$16.875 per direct labor hour.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
42/66
Question 38
1.D.2.a
tb.job.oc.019_1809
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 2
An example of a similarity between a job order cost system and a process cost system would be the:
Unit cost computations.
Method used to track costs.
Rationale
Point at which costs are totaled.
Incorrect. Using a job order cost system, costs are totaled either at the end of the accounting period, or when a job is completed. Using a process
cost system, costs are totaled either at the end of the accounting period, or the end of a batch run; therefore, this is not an example of a similarity
between a job order cost system and a process cost system.
Rationale
Unit cost computations.
Incorrect. Using a job order cost system, unit costs are computed by dividing the total cost of a job by the number of units produced for that job.
Using a process cost system, unit costs are computed by dividing the total costs in the beginning inventory plus the costs added to the process by
the equivalent units of production; therefore, this is not an example of a similarity between a job order cost system and a process cost system.
Rationale
Flow of costs.
Correct. Whether a job order cost system or a process cost system is used, costs will flow from Work-in-Process Inventory to Finished Goods
Inventory when goods are finished, and from Finished Goods Inventory to Cost of Goods Sold when delivered to customers; therefore, this is an
example of a similarity between a job order cost system and a process cost system.
Rationale
Method used to track costs.
Incorrect. Using a job order cost system, costs are tracked by job number. Using a process cost system, costs are tracked either at the end of the
accounting period, or the end of a batch run; therefore, this is not an example of a similarity between a job order cost system and a process cost
system.
Flow of costs.
Correct
Point at which costs are totaled.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
43/66
Question 39
1.D.2.a
1A4-CQ20
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 4
Maker Distributors has a policy of maintaining inventory at 15% of the next month's forecasted sales. The cost of Maker's merchandise averages 60% of
the selling price. The inventory balance as of May 31 is $63,000, and the forecasted dollar sales for the last seven months of the year are as follows:
June
$700,000
July
600,000
August
650,000
September
800,000
October
850,000
November
900,000
December
840,000
What is the budgeted dollar amount of Maker's purchases for July?
$360,000.
$418,500.
Rationale
$360,000.
This answer is incorrect. This answer represents the cost of sales for units sold in July. However, it does not consider beginning or expected ending
inventory.
Rationale
$355,500.
This answer is incorrect. This answer mixed up beginning and ending inventory when calculating purchases for July.
Rationale
$418,500.
This answer is incorrect. This answer did not subtract beginning inventory when calculating purchases for July.
Rationale
$364,500.
Purchases in dollars is calculated as follows:
Purchases in dollars = (cost of sales) + (expected ending inventory) −
(expected beginning inventory)
Cost of sales = (100% −
the gross profit percentage)(sales)
Cost of sales = (100% −
40%)(sales in dollars)
The expected ending inventory for each month = 15% of the next month's expected sales. Therefore, the purchases in dollars for July can be
calculated as follows:
Purchases for July = (0.6)($600,000) + (0.15)(0.6)($650,000) −
(0.15)(0.6)($600,000)
Purchases for July = $360,000 + $58,500 −
$54,000 = $364,500
$364,500.
Correct
$355,500.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
44/66
Question 40
2.C.3.h
2C3-LS28
LOS: 2.C.3.h
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: easy
Bloom Code: 2
Which of the following is a primary benefit of involving cross-functional teams in the target costing process?
More accurate input and maintenance of cost table databases
More realistic market assessment of customer wants and needs
Rationale
More accurate input and maintenance of cost table databases
This answer is incorrect. More accurate input and maintenance of cost table databases is not a primary benefit of involving cross-functional teams
in the target costing process.
Rationale
More realistic market assessment of customer wants and needs
This answer is incorrect. More realistic market assessment of customer wants and needs is not a primary benefit of involving cross-functional teams
in the target costing process.
Rationale
Improved analysis of how to gain and sustain competitive advantage
This answer is incorrect. Improved analysis of how to gain and sustain competitive advantage is not a primary benefit of involving cross-functional
teams in the target costing process.
Rationale
Better assurance that the proposed product or service generates the desired profit margin
The cross-functional participation of research and design, engineering, production, marketing, and accounting are necessary to ensure that the
proposed product or service when sold generates the desired profit margin. Stated another way, the cross-functional team is given the
responsibility to design and develop the product or service so that it can be made for the target cost.
Better assurance that the proposed product or service generates the desired profit margin
Correct
Improved analysis of how to gain and sustain competitive advantage
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
45/66
Question 41
1.D.3.l
1C2-AT20
LOS: 1.D.3.l
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: easy
Bloom Code: 1
An accounting system that collects financial and operating data on the basis of the underlying nature and extent of the cost drivers is:
target costing.
variable costing.
direct costing.
Rationale
target costing.
This answer is incorrect. Target costing does not collect financial and operating data on the basis of the underlying nature and extent of the cost
drivers.
Rationale
variable costing.
This answer is incorrect. Variable costing does not collect financial and operating data on the basis of the underlying nature and extent of the cost
drivers.
Rationale
activity-based costing (ABC).
ABC is an accounting technique that allocates production support costs to the activities that drive these costs. The ABC system then reassigns the
costs from the activities to the products produced.
Rationale
direct costing.
This answer is incorrect. Direct costing does not collect financial and operating data on the basis of the underlying nature and extent of the cost
drivers.
activity-based costing (ABC).
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
46/66
Question 42
1.D.2.b
1C1-LS07
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 3
A company has a beginning material inventory of $50,000, makes purchases of $20,000, and has an ending materials inventory of $30,000. If its beginning
work-in-process (WIP) inventory is $100,000 and ending WIP inventory is $60,000 and its conversion costs are $80,000, what is its cost of goods
manufactured for the period?
$340,000.
$40,000.
Rationale
$180,000.
This answer is incorrect. This answer subtracted purchases and added ending material inventory when calculating direct material used in
manufacturing.
Rationale
$160,000.
Direct materials (DM) used is equal to the beginning material inventory plus purchases minus ending material inventory ($50,000 + $20,000 −
$30,000 = $40,000). Cost of goods manufactured is beginning WIP inventory plus DM, plus conversion costs, minus ending WIP inventory ($100,000 +
$40,000 + $80,000 −
$60,000 = $160,000).
Rationale
$340,000.
This answer is incorrect. When calculating direct material used in manufacturing, this answer added ending inventory. Additionally, when
calculating cost of goods manufactured, this answer added ending WIP inventory.
Rationale
$40,000.
This answer is incorrect. This answer represents the direct materials used in manufacturing, not the cost of goods manufactured.
$160,000.
Correct
$180,000.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
47/66
Question 43
1.D.2.a
1C2-LS11
LOS: 1.D.2.a
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 2
Which of the following is true of job order costing?
Job order costing cannot be used with actual, normal, or standard costing.
Actual or normal costing can be used with job order costing but not standard costing.
Rationale
Job order costing cannot be used with actual, normal, or standard costing.
This answer is incorrect. Job order costing can be used with actual, normal, or standard costing.
Rationale
Actual or normal costing can be used with job order costing but not standard costing.
This answer is incorrect. Job order costing can be used with standard costing as well.
Rationale
Standard costing can be used with job order costing but not actual or normal costing.
This answer is incorrect. Job order costing can be used with actual or normal costing as well.
Rationale
Actual, normal, or standard costing can be used with job order costing.
Job order costing allows use of actual, normal, or standard costing.
Actual, normal, or standard costing can be used with job order costing.
Correct
Standard costing can be used with job order costing but not actual or normal costing.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
48/66
Question 44
1.D.2.b
1C2-AT10
LOS: 1.D.2.b
Lesson Reference: Process Costing
Difficulty: hard
Bloom Code: 6
A sporting goods manufacturer buys wood as a direct material for baseball bats. The Forming Department processes the baseball bats, and the bats are
then transferred to the Finishing Department where a sealant is applied. The Forming Department began manufacturing 10,000 “Casey Sluggers” during
the month of May. There was no beginning inventory. Costs for the Forming Department for the month of May were as:
Direct materials
$33,000
Conversion costs
17,000
Total
$50,000
A total of 8,000 bats were completed and transferred to the Finishing Department; the remaining 2,000 bats were still in the forming process at the end of
the month. All of the Forming Department's direct materials were placed in process but, on average, only 25% of the conversion cost was applied to the
ending work-in-process inventory.
The cost of the units transferred to the Finishing Department is:
$49,000.
$40,000.
Rationale
$50,000.
This answer is incorrect. Not all of costs of the Forming Department will be transferred to the Finishing Department this period.
Rationale
$49,000.
This answer is incorrect. Not all of the direct material costs will be transferred to the Finishing Department this period.
Rationale
$42,400.
In a process costing system, costs may be added to a product at different points in the manufacturing process. In this scenario, all of the direct
material costs have been placed in process for the 10,000 units that the Forming Department began manufacturing during the month. Regarding
the conversion costs (conversion costs = direct labor + manufacturing overhead) , all conversion costs were applied to 8,000 units, but only 25% of
the conversion costs have been applied to the 2,000 units in ending work-in-process inventory.
The cost of the units transferred to the Finishing Department is calculated by taking the number of units that were transferred out and multiplying
that number by the total manufacturing cost per unit.
Cost of units transferred out = (units transferred out) × (manufacturing cost per unit)
Number of units transferred to Finishing Department = 8,000 units
Manufacturing cost per unit = direct material cost applied per unit + conversion cost applied per unit
Direct material costs applied per unit = $33,000 ÷ 10,000 units = $3.30 per unit
(Note that direct material costs are related to all 10,000 units, so that number must be used as the denominator.)
Conversion costs applied during the period totaled $17,000 and they were applied in full to the 8,000 units that were transferred out, as well as 25%
applied to the units remaining in process (2000 units × 0.25 = 500 equivalent units).
Conversion costs per unit = ($17,000) ÷ (8,000 units + 500 units) = $17,000 ÷ 8,500 units = $2.00 per unit
Cost of units transferred out = (units transferred out) × (manufacturing cost per unit)
$42,400.
Correct
$50,000.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
49/66
Cost of units transferred out = (8,000) × ($3.30 + $2.00) = (8,000) × ($5.30) = $42,400
Rationale
$40,000.
This answer is incorrect. This answer did not consider that the units remaining in work-in-process only had 25% of conversion costs, not 100%.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
50/66
Question 45
1.D.3.n
1C2-LS06
LOS: 1.D.3.n
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: easy
Bloom Code: 2
Which of the following is not an advantage of using activity-based cost drivers?
Costs are more reliably determined.
Cost deviations from expectations are highlighted.
Rationale
Costs are more reliably determined.
This answer is incorrect. An advantage of using activity-based cost drivers is that costs are more reliably determined.
Rationale
Implementation is relatively inexpensive compared to other methods.
Activity-based cost drivers require a detailed description of each type of activity, so initial implementation can be costly and time-consuming.
Rationale
Detailed breakdown of activities helps firms remove non-value-added activities.
This answer is incorrect. An advantage of using activity-based cost drivers is that detailed breakdown of activities helps firms remove non-value-
added activities.
Rationale
Cost deviations from expectations are highlighted.
This answer is incorrect. An advantage of using activity-based cost drivers is that cost deviations from expectations are highlighted.
Implementation is relatively inexpensive compared to other methods.
Correct
Detailed breakdown of activities helps firms remove non-value-added activities.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
51/66
Question 46
1.D.2.b
tb.job.oc.027_1809
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 3
Jolly Manufacturing produces furniture. Jolly has three jobs in process at the end of the month with the following information:
1. Job AA—$400 direct materials, $620 direct labor
2. Job BB—$340 direct materials, $580 direct labor
3. Job CC—$120 direct materials, $80 direct labor
Jolly's average direct labor rate is $20 per hour, and Jolly applies overhead at the rate of $17 per direct labor hour. What is the balance in Jolly's Work-in-
Process Inventory at the end of the month?
$2,140
$2,368
Rationale
$2,140
Incorrect. This amount is the total of the direct materials and direct labor, but it excludes the amount of applied overhead. To calculate the applied
overhead, first calculate the number of labor hours, then multiply the labor hours by the overhead application rate.
Rationale
$1,088
Incorrect. This amount is the total applied overhead for the three jobs; however, the total cost of a job equals the direct materials plus the direct
labor plus the applied overhead.
Rationale
$2,368
Incorrect. This amount is the direct labor plus the applied overhead for the three jobs, but it excludes the direct materials.
Rationale
$3,228
Correct. The balance in the Work-in-Process Inventory account at the end of the month equals the direct materials plus the direct labor plus the
applied overhead for each job in process. First, calculate the amount of direct labor hours for each job to find the applied overhead and then add
the costs for each job together.
Direct labor hours for Job AA = $620 ÷ $20 = 31 direct labor hours
Total cost of Job AA = $400 + $620 + (31 × $17) = $1,547
Direct labor hours for Job BB = $580 ÷ $20 = 29 direct labor hours
Total cost of Job BB = $340 + $580 + (29 × $17) = $1,413
Direct labor hours for Job CC = $80 ÷ $20 = 4 direct labor hours
Total cost of Job CC = $120 + $80 + (4 × $17) = $268
Total cost of all three jobs = $1,547 + $1,413 + $268 = $3,228
$3,228
Correct
$1,088
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
52/66
Question 47
1.D.3.m
tb.ab.cost.035_1809
LOS: 1.D.3.m
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: medium
Bloom Code: 3
At the beginning of the year, managers at King Industries estimated $400,000 in manufacturing overhead, 20,000 direct labor hours, and 30,000 machine
hours. Actual manufacturing costs at the end of the year were $425,000 in manufacturing overhead. During the year, 22,000 direct labor hours and 27,000
machine hours were incurred. If King Industries uses a normal costing system, and if overhead is applied based on direct labor hours, how much
overhead was applied during the year?
$540,000
$400,000
Rationale
$440,000
Correct. With a normal costing system, the predetermined overhead rate equals estimated overhead divided by the estimated base, in this case
direct labor hours. The actual activity in the base is then used to apply the overhead. The predetermined overhead rate is $20 per direct labor hour
($400,000 ÷ 20,000 direct labor hours). The overhead applied during the year equals $440,000 ($20 per direct labor hour × 22,000 actual direct labor
hours).
Rationale
$540,000
Incorrect. Make sure to use actual direct labor hours, not actual machine hours, to calculate the overhead applied.
Rationale
$400,000
Incorrect. This is the amount of estimated overhead. Make sure to use estimates to calculate the predetermined overhead rate and use actual
activity to apply the overhead.
Rationale
$425,000
Incorrect. This is the amount of actual overhead. Make sure to use estimates to calculate the predetermined overhead rate and use actual activity
to apply the overhead.
$440,000
Correct
$425,000
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
53/66
Question 48
1.D.2.j
1C2-AT03
LOS: 1.D.2.j
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: medium
Bloom Code: 3
Claremont Company has been asked to evaluate the profitability of a product that it manufactured and sold from 20X5 through 20X8. The product had a
one-year warranty from date of sale. The following information appears in the financial records.
Research, development and design cost
Manufacturing and distribution costs
Warranty costs
Warranty cost
(20X3 and 20X4)
(20X5–20X8)
(20X5–20X8)
(20X9)
$5,000,000
$7,000,000
$200,000
$100,000
The life-cycle cost for this product is:
$12,200,000.
$12,000,000.
Rationale
$12,200,000.
This answer is incorrect. This answer did not consider warranty cost (20X9) when calculating the life-cycle cost for this product.
Rationale
$12,000,000.
This answer is incorrect. This answer did not consider warranty costs (20X5–20X8) or warranty cost (20X9) when calculating the life-cycle cost for
this product.
Rationale
$7,300,000.
This answer is incorrect. This answer did not consider research, development, and design cost when calculating the life-cycle for this product.
Rationale
$12,300,000.
The life-cycle cost for the product = Manufacturing and distribution costs + R&D and design costs + Total warranty costs = $7,000,000 + $5,000,000 +
$200,000 + $100,000 = $12,300,000.
$12,300,000.
Correct
$7,300,000.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
54/66
Question 49
1.D.3.m
tb.ab.cost.026_1809
LOS: 1.D.3.m
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: hard
Bloom Code: 4
Turnbull Company produces two products, Beta and Delta. Overhead consists of the following: $20,000 in setup costs with number of setups as the
driver; $2,220,000 in machining costs with machine hours as the driver; and $80,000 in packing costs with packing orders as the driver. Data for the
current year follows:
Beta
Delta
Number of setups
10
30
Machine hours
1,000 4,000
Packing orders
150
350
Number of units produced 600
400
What is the total overhead allocated to Beta under activity-based costing?
$464,000
$773,333
$1,392,000
Rationale
$464,000
Incorrect. This is the amount that would have been allocated to Beta using a traditional allocation based on machine hours. Under activity-based
costing, there are three cost pools and three allocation bases.
Rationale
$473,000
Correct. Under activity-based costing, calculate an application rate for setup costs, an application rate for machining, and an application rate for
packing. After calculating the application rates, use them to calculate the amount of overhead allocated to Beta.
Application rate for setups = $20,000 ÷ (10 + 30) = $500 per setup
Application rate for machining = $2,220,000 ÷ (1,000 + 4,000) = $444 per machine hour
Application rate for packing = $80,000 ÷ (150 + 350) = $160 per packing order
Overhead allocated to Beta = (10 setups × $500 per setup) + (1,000 machine hours × $444 per machine hour) + (150 packing orders × $160 per
packing order)
Overhead allocated to Beta = $5,000 + 444,000 + 24,000 = $473,000
Rationale
$773,333
Incorrect. This amount is one-third of the total overhead. Under activity-based costing, there are three cost pools and three allocation bases.
Rationale
$1,392,000
Incorrect. This amount is the total overhead allocated by number of units. Under activity-based costing, there are three cost pools and three
allocation bases.
$473,000
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
55/66
Question 50
1.D.2.b
tb.job.oc.037_1809
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 3
Ed was working on a custom-made workbench for a customer. The job, TB0414, was started in November. At the end of November, the job cost sheet for
TB0414 showed direct materials of $215, direct labor of 14 hours at $18 per hour, and overhead of 50% of direct labor cost. During December, $85 of
direct materials were added to Job TB0414 and Ed's time ticket showed 15 hours on Job TB0414, 25 hours on Job TB0614, 10 hours of maintenance on
the lathe, and 40 hours on a new job, DR1014. Job TB0414 was completed on December 28. What is the total amount of overhead applied to Job TB0414?
$126
$135
Rationale
$126
Incorrect. This is the amount of overhead applied to Job TB0414 in November. The total overhead applied includes overhead applied in November
and December.
Rationale
$135
Incorrect. This is the amount of overhead applied to Job TB0414 in December. The total overhead applied includes overhead applied in November
and December.
Rationale
$300
Incorrect. This amount is the total direct materials applied to Job TB0414. To calculate overhead applied, first calculate the total direct labor cost,
then use the overhead application rate.
Rationale
$261
Correct. The total labor hours applied to Job TB0414 are 14 hours in November and 15 hours in December, totaling 29 hours. The total direct labor
cost equals $522 (29 hours × $18 per hour). Overhead is applied at a rate of 50% of direct labor. Total overhead applied equals $261 ($522 × 50%).
$261
Correct
$300
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
56/66
Question 51
1.D.2.g
tb.ab.cost.002_1809
LOS: 1.D.2.g
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: easy
Bloom Code: 2
In changing from a traditional costing system to an activity-based costing system, overhead costs tend to shift from high- volume standard products to
low-volume premium products because:
Organizational level overhead is not allocated under activity-based costing.
Standard products generally use more total activities than premium products.
Rationale
The general overhead cost pool is not allocated under activity-based costing.
Incorrect. General overhead cost pools are allocated under activity-based costing.
Rationale
Premium products usually consume more activities per unit than standard products.
Correct. Premium products tend to have extra features or finishing that consume more labor hours and/or machine hours than standard products.
Rationale
Organizational level overhead is not allocated under activity-based costing.
Incorrect. Organizational level overhead will not directly change when production shifts from high-volume standard products to low-volume
premium products.
Rationale
Standard products generally use more total activities than premium products.
Incorrect. Standard products generally do not use more total activities than premium products. Premium products tend to have extra features or
finishing that consume more labor hours and/or machine hours.
Premium products usually consume more activities per unit than standard products.
Correct
The general overhead cost pool is not allocated under activity-based costing.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
57/66
Question 52
1.D.2.j
1C2-LS17
LOS: 1.D.2.j
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: easy
Bloom Code: 2
In life-cycle costing, which of the these is the primary method of lowering downstream costs?
Improving supplier relationships.
Improving product designs in the downstream phase.
Proactive management during the downstream phase such as streamlining manufacturing costs.
Rationale
Improving supplier relationships.
This answer is incorrect. In life-cycle costing, improving supplier relationships is not the primary method of lowering downstream costs.
Rationale
Improving product designs in the downstream phase.
This answer is incorrect. In life-cycle costing, improving product designs in the downstream phase is not the primary method of lowering
downstream costs.
Rationale
Improving the upstream and manufacturing cost phases.
By the time a product reaches the downstream phase, it is too late to be proactive about changes unless the product has been correctly and
efficiently designed during the upstream and manufacturing cost phases.
Rationale
Proactive management during the downstream phase such as streamlining manufacturing costs.
This answer is incorrect. In life-cycle costing, proactive management during the downstream phase such as streamlining manufacturing costs is not
the primary method of lowering downstream costs.
Improving the upstream and manufacturing cost phases.
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
58/66
Question 53
1.D.3.n
1C2-LS16B
LOS: 1.D.3.n
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: easy
Bloom Code: 2
Which of these are a benefit of using activity-based costing (ABC)?
ABC reports conform to GAAP and save the expense of needing to create more than one format.
ABC simplifies the amount of information supplied to managers so that only relevant information is supplied.
Rationale
ABC reduces distortions caused by traditional methods that may make one product seem more or less profitable than it really is.
ABC reduces distortions to profits by providing a more accurate picture of costs than traditional methods because it uses the most appropriate cost
driver for each activity while traditional methods use a very limited number of cost drivers.
Rationale
ABC uses traditional rules for managers, so acceptance is usually automatic.
This answer is incorrect. ABC does not use traditional rules for managers and acceptance is not usually automatic.
Rationale
ABC reports conform to GAAP and save the expense of needing to create more than one format.
This answer is incorrect. ABC reports do not conform to GAAP and do not save the expense of needing to create more than one format.
Rationale
ABC simplifies the amount of information supplied to managers so that only relevant information is supplied.
This answer is incorrect. ABC does not simplify the amount of information supplied to managers.
ABC reduces distortions caused by traditional methods that may make one product seem more or less profitable than it really is.
Correct
ABC uses traditional rules for managers, so acceptance is usually automatic.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
59/66
Question 54
1.D.2.f
tb.proc.c.012_1809
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: medium
Bloom Code: 3
On July 1, Premiere Paints’ Mixing Department had 80,000 units in Beginning Work-in-Process that were 65% complete. Between July 1 and July 31, the
Mixing Department transferred 150,000 units to the Packaging Department. At the end of the month, on July 31, the Mixing Department had 40,000 units
in Work-in-Process that were 80% complete. Materials are added at the beginning of the process, while conversion costs are incurred uniformly
throughout the process. Premiere Paints uses the FIFO method. Based on this information, which of the following statements is accurate?
In July, the Mixing Department had 230,000 equivalent units of production for materials.
In July, the Mixing Department had 102,000 equivalent units of production for materials.
Rationale
In July, the Mixing Department had 230,000 equivalent units of production for materials.
Incorrect. Under the FIFO method, equivalent units of production for materials are not calculated as Beginning Work-in-Process plus units
transferred out.
Rationale
In July, the Mixing Department had 102,000 equivalent units of production for materials.
Incorrect. Because materials are added at the beginning of the process, Ending Work-in-Process is not 80% complete for materials.
Rationale
In July, the Mixing Department had 190,000 equivalent units of production for materials.
Incorrect. This answer represents the equivalent units of production for materials calculated under the Weighted Average method, not the FIFO
method.
Rationale
In July, the Mixing Department had 110,000 equivalent units of production for materials.
Correct. Units transferred to the Packaging Department include the 80,000 units in Beginning Work-in-Process. Because materials are added at the
beginning of the process, the 80,000 units in Beginning Work-in-Process should not be included in the calculation of equivalent units of production
for materials. However, for the same reason, the units in Ending Work-in-Process should be considered. See the following calculation: 150,000
(transferred out) −
80,000 (units in beginning inventory) + 40,000 (units in ending inventory)
In July, the Mixing Department had 110,000 equivalent units of production for materials.
Correct
In July, the Mixing Department had 190,000 equivalent units of production for materials.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
60/66
Question 55
1.D.3.m
tb.ab.cost.025_1809
LOS: 1.D.3.m
Lesson Reference: Activity-Based Costing (ABC) and Life Cycle Costing
Difficulty: medium
Bloom Code: 3
Turnbull Company produces two products, Beta and Delta. Overhead consists of the following: $20,000 in setup costs with number of setups as the
driver; $2,220,000 in machining costs with machine hours as the driver; and $80,000 in packing costs with packing orders as the driver. Data for the
current year follow:
Beta
Delta
Number of setups
10
30
Machine hours
1,000 4,000
Packing orders
150
350
Number of units produced 600
400
What is the total overhead allocated to Beta under a traditional allocation based on machine hours?
$473,000
$1,392,000
Rationale
$473,000
Incorrect. This is the amount that would have been allocated to Beta using activity-based costing. Under a traditional allocation system, there is
only one overhead pool and one allocation base used to apportion the overhead.
Rationale
$773,333
Incorrect. This amount is one-third of the total overhead. Under a traditional allocation system, total overhead is allocated based upon
proportionate usage of the base, machine hours in this case.
Rationale
$1,392,000
Incorrect. This amount is the total overhead allocated by number of units. Under a traditional allocation system, total overhead is allocated based
upon proportionate usage of the base, machine hours in this case.
Rationale
$464,000
Correct. Using a traditional allocation based on machine hours, the overhead allocation rate is estimated overhead divided by the estimated base.
After calculating the overhead allocation rate, use it to calculate the amount of overhead allocated to Beta. The total estimated overhead is
$2,320,000 ($20,000 + $2,220,000 + $80,000), and the total base (machine hours) is 5,000 hours (1,000 + 4,000). The overhead allocation rate is $464
per machine hour ($2,320,000 ÷ 5,000 machine hours). The overhead allocated to Beta equals $464,000 (1,000 machine hours × $464 per machine
hour).
$464,000
Correct
$773,333
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
61/66
Question 56
1.D.2.f
1C2-AT15
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: hard
Bloom Code: 5
Kimbeth Manufacturing uses a process cost system to manufacture dust density sensors for the mining industry. The following information pertains to
operations for the month of May.
Units
Beginning work-in-process inventory, May 1
16,000
Started in production during May
100,000
Completed production during May
92,000
Ending work-in-process inventory, May 31
24,000
The beginning inventory was 60% complete for materials and 20% complete for conversion costs. The ending inventory was 90% complete for materials
and 40% complete for conversion costs.
Costs pertaining to the month of May are:
Beginning inventory costs are: materials, $54,560; direct labor, $20,320; and factory overhead, $15,240.
Costs incurred during May are: materials used, $468,000; direct labor, $182,880; and factory overhead, $391,160.
Using the first-in, first-out (FIFO) method, the equivalent unit conversion cost for May is:
$6.24.
$6.20.
Rationale
$1.86.
This answer is incorrect. This answer did not consider the factory overhead costs, just the direct labor costs.
Rationale
$6.24.
This answer is incorrect. This answer divided the conversion costs by the completed production during May instead of the equivalent units for
conversion.
Rationale
$6.20.
This answer is incorrect. This answer incorrectly included beginning inventory direct labor and factory overhead costs.
Rationale
$5.83.
The FIFO approach follows the production flow and assumes that units will be sold in the order in which they were placed in inventory.
In order to compute the cost per equivalent unit for conversion costs, it is first necessary to calculate the number of equivalent units with respect to
conversion costs.
To calculate the equivalent units of production for conversion costs using FIFO, calculate the equivalent units for:
1. units in beginning inventory,
2. products started into production during the month, and,
3. units in ending inventory.
$5.83.
Correct
$1.86.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
62/66
First, the 16,000 units in the beginning inventory would be completed, requiring the addition of 12,800 [(16,000)×(1 −
0.2)] equivalent units for
conversion costs.
Next, of the 100,000 units started during the month, 76,000 would be completed, requiring 76,000 equivalent units for conversion costs. (92,000
units completed during month −
16,000 units from beginning inventory = 76,000 units)
Lastly, of the 100,000 units started, 24,000 would be in the ending inventory, 40% complete with respect to conversion costs, requiring 9,600
[(0.40)×(24,000)] equivalent units for conversion costs.
The total equivalent units for conversion costs would be 12,800 + 76,000 + 9,600 = 98,400.
Conversion costs consist of direct labor and factory overhead.
Conversion costs = $182,880 (direct labor) + $391,160 (factory overhead)
Conversion costs = $574,040
Therefore, the equivalent unit cost for conversion = ($574,040 conversion costs) ÷ (98,400 equivalent units for conversion costs) = $5.83 per unit.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
63/66
Question 57
1.D.2.f
tb.proc.c.014_1809
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: easy
Bloom Code: 3
On August 1, Mega Manufacturing's Fabrication Department had 24,000 units in Beginning Work-in-Process that were 60% complete. Between August 1
and August 31, the department transferred a number of completed units to the Packaging Department. At the end of the month, on August 31, the
Fabrication Department had 60,000 units in Work-in-Process that were 80% complete. Materials are added at the beginning of the process, while
conversion costs are incurred uniformly throughout the process. If the Fabrication Department had 190,000 equivalent units of production for materials
for August, how many completed units did it transfer to the Packaging Department? Mega uses the FIFO method.
132,400 units.
250,000 units.
Rationale
154,000 units.
Correct. Because materials are added at the beginning of the production process, units in Beginning Work-in-Process are already 100% complete
for materials. Also, for the same reason, Ending Work-in-Process is 100% complete for materials. Therefore, units transferred out to the Packaging
Department can be calculated as follows:
Units transferred out = 190,000 (started during the period) −
60,000 (units in Ending Work-in-Process) + 24,000 (units in Beginning Work-in-Process)
= 154,000.
Rationale
84,000 units.
Incorrect. This number is units in Beginning Work-in-Process plus units in Ending Work-in-Process. However, units in Ending Work-in-Process were
not completed and transferred out. Additionally, this answer does not consider the units that were started and completed.
Rationale
132,400 units.
Incorrect. This number is units transferred out assuming the Fabrication Department had 190,000 equivalent units of production for conversion
costs. Beginning Work-in-Process is not 60% complete for materials. Additionally, Ending Work-in-Process is not 80% complete for materials.
Rationale
250,000 units.
Incorrect. This number is equivalent units of production for materials plus equivalent units of materials in ending inventory. However, equivalent
units of materials in ending inventory is already considered in equivalent units of production for materials and should be subtracted instead of
added. Additionally, this answer does not consider Beginning Work-in-Process.
154,000 units.
Correct
84,000 units.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
64/66
Question 58
1.D.2.b
tb.job.oc.036_1809
LOS: 1.D.2.b
Lesson Reference: Job Order Costing
Difficulty: medium
Bloom Code: 4
Jones Manufacturing had one job, Job PLS5, in Work-in-Process Inventory at the beginning of March. The costs incurred to date on PLS5 included
$12,300 of direct materials, $7,800 in direct labor, and $19,500 in overhead. During March, Jones finished the job by adding $1,700 of direct materials and
$3,900 of direct labor. If Jones applies overhead at the rate of 250% of direct labor cost, what total cost related to Job PLS5 was transferred to Finished
Goods Inventory during March?
$39,600
$45,200
$15,350
Rationale
$39,600
Incorrect. This amount is the total of the materials, labor, and overhead added prior to March. Materials, labor, and overhead were added to these
costs to complete the job during March, and need to be added to Finished Goods Inventory.
Rationale
$45,200
Incorrect. This amount is the total of the materials, labor, and overhead added prior to March, plus the materials and labor added during March.
You need to apply overhead based upon the activity added in March and add this amount to Finished Goods Inventory.
Rationale
$15,350
Incorrect. This is the total of the materials, labor, and overhead added during March. You also need to add the costs that were added prior to March
to the Finished Goods Inventory.
Rationale
$54,950
Correct. The total costs added prior to March equal $39,600 ($12,300 + $7,800 + $19,500). The costs added during March equal $15,350 ($1,700 +
$3,900 + ($3,900 × 250%)). The total cost transferred to Finished Goods Inventory are the costs added prior to March plus the costs added in March
which equals $54,950 ($39,600 + $15,350).
$54,950
Correct
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
65/66
Question 59
1.D.2.f
1C2-CQ12
LOS: 1.D.2.f
Lesson Reference: Process Costing
Difficulty: medium
Bloom Code: 3
Waller Co. uses a weighted-average process-costing system. Material B is added at two different points in the production of shirts, 40% is added when the
units are 20% completed, and the remaining 60% of Material B is added when the units are 80% completed. At the end of the quarter, there are 22,000
shirts in process, all of which are 50% completed. With respect to Material B, the ending shirts in process represent how many equivalent units?
4,400 units.
22,000 units.
Rationale
8,800 units.
The ending inventory of 22,000 shirts is only 50% complete. Therefore, the inventory units have only 40% of the Material B.
This equates to 8,800 equivalent units, which is calculated by multiplying the number of units in ending inventory (22,000) by the percent of
Material B (40%).
Equivalent units, shirts = (22,000 units) × (0.4) = 8,800 units.
Rationale
4,400 units.
This answer is incorrect. This answer represents 50% of the 40% of Material B added to the shirt production. 100% of the 40% is considered for the
calculation of the equivalent units.
Rationale
11,000 units.
This answer is incorrect. Only 40% of Material B is added by this point, not 50%.
Rationale
22,000 units.
This answer is incorrect. The shirts are only 50% complete, so not all of Material B is added yet.
8,800 units.
Correct
11,000 units.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
8/4/22, 6:51 PM
CMA Exam Review - Part 1 - Assessment Review
https://app.efficientlearning.com/pv5/v8/5/app/cma/part1_2020.html?#assessmentReview
66/66
Question 60
1.D.2.d
1C1-LS09
LOS: 1.D.2.d
Lesson Reference: Job Order Costing
Difficulty: easy
Bloom Code: 2
Which of the following would a merchandising company use in place of cost of goods manufactured on a statement of cost of goods sold?
Materials inventory.
Conversion costs.
Rationale
Net purchases.
The income statement for a merchandising company looks similar to that of a manufacturing company, except that it uses net purchases instead of
cost of goods manufactured.
Rationale
Prime costs.
This answer is incorrect. A merchandising company would not use prime costs in place of cost of goods manufactured on a statement of cost of
goods sold.
Rationale
Materials inventory.
This answer is incorrect. A merchandising company would not use material inventory in place of cost of goods manufactured on a statement of cost
of goods sold.
Rationale
Conversion costs.
This answer is incorrect. A merchandising company would not use conversion costs in place of cost of goods manufactured on a statement of cost
of goods sold.
Net purchases.
Correct
Prime costs.
Your Answer
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help