FIN 550 - Module 5 HW
docx
keyboard_arrow_up
School
Southern New Hampshire University *
*We aren’t endorsed by this school
Course
550
Subject
Finance
Date
Jan 9, 2024
Type
docx
Pages
3
Uploaded by SargentSandpiperMaster672
You are a financial analyst for the Brittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments: Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12%. The projects' expected net cash flows are shown in the table below.
Expected Net Cash Flows
Year
Project X
Project Y
0
– $10,000
– $10,000
1
6,500
3,500
2
3,000
3,500
3
3,000
3,500
4
1,000
3,500
a)
Use the Homework Student Workbook to calculate each project’s (NPV), (IRR), (MIRR),
and (PI).
b)
Which project or projects should be accepted if they are independent?
“The net present value (NPV) is defined as the present value of a project’s expected cash flows (including its initial cost) discounted at the appropriate risk-adjusted rate. The NPV measures how much wealth the project contributes to shareholders” (Ehrhardt & Brigham,2019). If the projects are independent, and the NPV is greater than zero, both projects should be accepted. Both of our projects have positive NPVs. Project X has a higher NPV compared to project Y.
Project X
Project Y
NPV
$ 966
$ 631
IRR
18 %
15 %
MIRR
14.52 %
13.68 %
PI
1.10
1.06
“The IRR is an estimate of the rate of return the company would earn if it invested in the project.
If this return exceeds the opportunity cost of the funds used to finance the project, then the difference benefits the firm’s stockholders. On the other hand, if the IRR is less than the cost of capital, stockholders suffer a loss in value.” (Ehrhardt & Brigham,2019)
“The modified IRR (MIRR) is similar to the regular IRR, except it is based on the assumption that cash flows are reinvested at the WACC”. (Ehrhardt & Brigham,2019)
The IRR and the MIRR for both projects are positive, if the projects were independent, they should both be accepted, because both projects will return a greater rate of return than the cost of
capital.
“The profitability index (PI) measures how much value a project creates for each dollar of the project’s cost.” (Ehrhardt & Brigham,2019) A project should be accepted if the PI is greater than 1.0. Projects with higher PIs should be chosen above the projects with lower PIs.
In conclusion, if project X and project Y were independent, they should both be chosen because they both independently provide a higher rate of return compared to the cost of capital when analyzed using NPV, IRR, MIRR and PI. c)
Which project or projects should be accepted if they are mutually exclusive?
If Project X and Project Y are mutually exclusive, the financial analyst should choose Project X. The reason for that is because project X has a greater NPV than project Y, it also has a greater IRR and MIRR percentage that project Y, and the PI index is higher for project X when compared to project Y. Project X will return a higher value to the shareholders than project Y will.
References:
Ehrhardt, M. C., & Brigham, E. F. (2019). Corporate Finance: A Focused Approach (7th ed.). Cengage Learning US.
https://mbsdirect.vitalsource.com/books/9781337910231
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Documents
Related Questions
You are a financial analyst for the Hittle Company. The director of capital budgeting
has asked you to analyze two proposed capital investments, Projects X and Y. Each
project has a cost of $10,000, and the cost of capital for each is 12%. The projects’
expected net cash flows are as follows:
Expected Net Cash Flows
Year Project X Project Y
0 −$10,000 −$10,000
1 6,500 3,500
2 3,000 3,500
3 3,000 3,500
4 1,000 3,500
a. Calculate each project’s payback period, net present value (NPV), internal rate
of return (IRR), modified internal rate of return (MIRR), and profitability
index (PI).
b. Which project or projects should be accepted if they are independent?
c. Which project should be accepted if they are mutually exclusive?
d. How might a change in the cost of capital produce a conflict between the NPV
and IRR rankings of these two projects? Would this conflict exist if r were 5%?
(Hint: Plot the NPV profiles.)
e. Why does the conflict exist?
arrow_forward
You are a financial analyst for the Brittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments: Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12%. The projects' expected net cash flows are shown in the table below.
Expected Net Cash Flows
Year
Project X
Project Y
0
– $10,000
– $10,000
1
6,500
3,500
2
3,000
3,500
3
3,000
3,500
4
1,000
3,500
Use the Homework Student Workbook to calculate each project's net present value (NPV), internal rate of return (IRR), modified internal rate of return (MIRR), and profitability index (PI).
Which project or projects should be accepted if they are independent?
Which project or projects should be accepted if they are mutually exclusive?
arrow_forward
You are a financial analyst for the Brittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments: Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12%. The projects' expected net cash flows are shown in the table below.
Expected Net Cash Flows
Year
Project X
Project Y
0
– $10,000
– $10,000
1
6,500
3,500
2
3,000
3,500
3
3,000
3,500
4
1,000
3,500
Which project or projects should be accepted if they are independent?
Which project or projects should be accepted if they are mutually exclusive?
arrow_forward
You are a financial analyst for the Hittle Company. The director of capital budgeting has
asked you to analyze two proposed capital investments, Projects X and Y. Each project
has a cost of $10,000, and the cost of capital for each is 12%. The projects' expected net
cash flows are as follows:
Expected Net Cash Flows
Year
Project X
Project Y
-S10,000
-$10,000
6,500
3,500
3,000
3,500
3,500
3,500
3,000
1,000
a. Calculate each project's payback period, net present value (NPV), internal rate of
return (IRR), modified internal rate of return (MIRR), and profitability index (PI).
b. Which project or projects should be accepted if they are independent?
c. Which project should be accepted if they are mutually exclusive?
arrow_forward
You are a financial analyst for the Vincenzo Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each project is 12%. The projects’ expected net cash flows are as follows:
Expected Net Cash Flows
Year Project X Project Y
0 ($10,000) ($10,000)
1 6,500 3,500
2 3,000 3,500
3 3,000 3,500
4 1,000 3,500
Calculate each project’s payback period, net present value (NPV), internal rate of return (IRR), and modified internal rate of return (MIRR).
Which project or projects should be accepted if they are…
arrow_forward
You are a financial analyst for the Hittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12% for both projects. The projects’ expected net cash flows are as follows:
Expected Net cash flows
Year
Project X
Project Y
0
-10000
-10000
1
6350
3600
2
2988
3700
3
3145
3500
4
945
3500
Calculate each project’s payback period, net present value (NPV), internal rate of return (IRR), and profitability index (PI)
arrow_forward
You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%.
The projects’ expected net cash flows are as follows:
Expected Net Cash Flows
Year
Project A
Project B
0
($50,000)
($50,000)
1
25,000
15,000
2
20,000
15,000
3
10,000
15,000
4
5,000
15,000
5
5,000
15,000
Which project or projects should be accepted if they are independent?
arrow_forward
You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%.
The projects’ expected net cash flows are as follows:
Expected Net Cash Flows
Year
Project A
Project B
0
($50,000)
($50,000)
1
25,000
15,000
2
20,000
15,000
3
10,000
15,000
4
5,000
15,000
5
5,000
15,000
Which project should be accepted if they are mutually exclusive?
arrow_forward
You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%.
The projects’ expected net cash flows are as follows:
Expected Net Cash Flows
Year
Project A
Project B
0
($50,000)
($50,000)
1
25,000
15,000
2
20,000
15,000
3
10,000
15,000
4
5,000
15,000
5
5,000
15,000
Which project will you select if your decision was based solely on the project’s payback period?
arrow_forward
You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%.
The projects’ expected net cash flows are as follows:
Expected Net Cash Flows
Year
Project A
Project B
0
($50,000)
($50,000)
1
25,000
15,000
2
20,000
15,000
3
10,000
15,000
4
5,000
15,000
5
5,000
15,000
d. How might a change in the cost of capital produce a conflict between the NPV and IRR rankings of these two projects? Would this conflict exist if r were 6%? (Hint: Plot the NPV profiles.)
arrow_forward
You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%.
The projects’ expected net cash flows are as follows:
Expected Net Cash Flows
Year
Project A
Project B
0
($50,000)
($50,000)
1
25,000
15,000
2
20,000
15,000
3
10,000
15,000
4
5,000
15,000
5
5,000
15,000
Calculate each project’s modified internal rate of return (MIRR), and profitability index (PI).
arrow_forward
You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%.
The projects’ expected net cash flows are as follows:
Expected Net Cash Flows
Year
Project A
Project B
0
($50,000)
($50,000)
1
25,000
15,000
2
20,000
15,000
3
10,000
15,000
4
5,000
15,000
5
5,000
15,000
Calculate each project’s payback period, net present value (NPV), internal rate of return (IRR), modified internal rate of return (MIRR), and profitability index (PI).
Which project will you select if your decision was based solely on the project’s payback period?
Which project or projects should be accepted if they are independent?
Which project should be accepted if they are mutually exclusive?
d. How might a change in the cost of capital produce a conflict between the NPV and…
arrow_forward
You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%.
The projects’ expected net cash flows are as follows:
Expected Net Cash Flows
Year
Project A
Project B
0
($50,000)
($50,000)
1
25,000
15,000
2
20,000
15,000
3
10,000
15,000
4
5,000
15,000
5
5,000
15,000
Calculate each project’s payback period, net present value (NPV), internal rate of return (IRR), modified internal rate of return (MIRR), and profitability index (PI).
arrow_forward
You are financial analyst for the XYZ company. The director has asked you to analyze two proposed capital investments, Project A and Project B. Each project has a cost of RM 10, 000, and the cost of capital for each project is 12 percent. The project s’ cash flows are as follows:
Year
Project A
Project B
0
(10,000)
(10,000)
1
6500
3500
2
3000
3500
3
3000
3500
4
1000
3500
Question 1: Calculate each project’s NPV.
Question 2: Which project or projects should be accepted?
arrow_forward
Need answers fo C and D
arrow_forward
Suppose that you are working as a capital budgeting analyst in a finance department of a firm and you are going to evaluate two mutually exclusive projects by implementing different capital budgeting techniques. The cash flows for these two projects are given below.
YEAR / CASH FLOW (A) /CASH FLOW (B)0 -$17,000 -$17,0001 8,000 2,0002 7,000 5,0003 5,000 9,0004 3,000 9,500
a. Calculate the Payback Period of each project. Which project should you accept according to this method? Explain whether the Payback Period is or is not an appropriate method in this case.
b. Suppose that the discount rate is 11%. Calculate the Net Present Values (NPV) of both projects. Which project should you accept according to NPV? Evaluate your findings.
c. Calculate the Internal Rate of Returns (IRR) for both projects (use excel). Which…
arrow_forward
You are analyzing two proposed capital investments with the following cash flows:
Project X
- $20,000
Year
0
1
2
3
12,530
6,360
6,360
2,020
Project Y
-$20,000
6,570
6,570
6,570
The PI for project X is
6,570
The cost of capital for both projects is 10 percent.
Calculate the profitability index (PI) for each project. (Do not round discount factors. Round intermediate calculations to 2
decimal places, e.g. 15.25 and final answers to 4 decimal places, e.g. 1.2527.)
1.13 and the PI for project Y is
1.04
arrow_forward
Assume you are the chief financial officer at Lehman Memorial Hospital. The CEO has asked you to analyze two proposed capital investment Project X and project Y each project requires a net investment outlay of $10,000 and the opportunity cost of capital for each project is 14% the project's expected net cash flows are as following Year Project x Project Y 0 (10,000) (10,000) 1 6,500 3,000 2 3,000 3,000 3 3,000 3,000 4 1,000 3,000 a. Calculate each project’s payback, NPV and IRR. b. Which project is financially acceptable? Explain your answer.
arrow_forward
QUESTIONS THREEYou are a financial Analyst for Bandari Limited. The director of capital budgeting has asked you to analyze two proposed capital investments , project a X and Y. Each project has a cost of $ 10,000 and the cost of capital for each each project is 12%. The projects expected net cash flow are as followsYEAR PROJECT X PRJECT Y0 (10,000) (10,000)1 6,500 3,5002 3,000 3,5003 3,000 3,5004 1,000 3,500For each Project, estimate;(a) Regular pay back period(b) NPV(c) MIRR(d) IRR(e) Cross over rate(f) NPV for each project using the Cross over rate estimated in part (e)(g) Assumed re-investment rate based on (i) IRR assumption(ii) NPV assumption
arrow_forward
Use the information in the table below for the following 5 questions.
A capital investment project is estimated to have the following after-tax cash flows, by year:
2
3
4
-$60,000
$20,000
$22,500
$17,500
$25,000
The company utilizes a discount rate of 15% to evaluate capital projects. You may have rounding errors in your calculations so
choose the closest answer. Assume cash flows are received equally over the year.
The NET PRESENT VALUE for the project shown above is:
O-$4,789.25
O $1,150.33
O $0.00
O $204.90
O $1183.65
Click Save and Submit to save and submit. Click Save All Answers to save all answers.
arrow_forward
You are analyzing two proposed capital investments with the following cash flows:
Year
0
1
2
3
4
Project X
- $20,000
12,230
6,360
6,360
2,020
Project Y
- $20,000
The Pl for project X is
6,670
6,670
6,670
6,670
The cost of capital for both projects is 10 percent.
Calculate the profitability index (PI) for each project. (Do not round discount factors. Round intermediate calculations to 2
decimal places, e.g. 15.25 and final answers to 4 decimal places, e.g. 1.2527.)
1.1266 and the PI for project Y is
Which project, or projects, should be accepted if you have unlimited funds to invest?
If you have unlimited funds you should invest in
Which project should be accepted if they are mutually exclusive?
If they are mutually exclusive you should invest in
1,0572
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you

Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning


EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT

Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College

Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Related Questions
- You are a financial analyst for the Hittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12%. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project X Project Y 0 −$10,000 −$10,000 1 6,500 3,500 2 3,000 3,500 3 3,000 3,500 4 1,000 3,500 a. Calculate each project’s payback period, net present value (NPV), internal rate of return (IRR), modified internal rate of return (MIRR), and profitability index (PI). b. Which project or projects should be accepted if they are independent? c. Which project should be accepted if they are mutually exclusive? d. How might a change in the cost of capital produce a conflict between the NPV and IRR rankings of these two projects? Would this conflict exist if r were 5%? (Hint: Plot the NPV profiles.) e. Why does the conflict exist?arrow_forwardYou are a financial analyst for the Brittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments: Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12%. The projects' expected net cash flows are shown in the table below. Expected Net Cash Flows Year Project X Project Y 0 – $10,000 – $10,000 1 6,500 3,500 2 3,000 3,500 3 3,000 3,500 4 1,000 3,500 Use the Homework Student Workbook to calculate each project's net present value (NPV), internal rate of return (IRR), modified internal rate of return (MIRR), and profitability index (PI). Which project or projects should be accepted if they are independent? Which project or projects should be accepted if they are mutually exclusive?arrow_forwardYou are a financial analyst for the Brittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments: Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12%. The projects' expected net cash flows are shown in the table below. Expected Net Cash Flows Year Project X Project Y 0 – $10,000 – $10,000 1 6,500 3,500 2 3,000 3,500 3 3,000 3,500 4 1,000 3,500 Which project or projects should be accepted if they are independent? Which project or projects should be accepted if they are mutually exclusive?arrow_forward
- You are a financial analyst for the Hittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12%. The projects' expected net cash flows are as follows: Expected Net Cash Flows Year Project X Project Y -S10,000 -$10,000 6,500 3,500 3,000 3,500 3,500 3,500 3,000 1,000 a. Calculate each project's payback period, net present value (NPV), internal rate of return (IRR), modified internal rate of return (MIRR), and profitability index (PI). b. Which project or projects should be accepted if they are independent? c. Which project should be accepted if they are mutually exclusive?arrow_forwardYou are a financial analyst for the Vincenzo Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each project is 12%. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project X Project Y 0 ($10,000) ($10,000) 1 6,500 3,500 2 3,000 3,500 3 3,000 3,500 4 1,000 3,500 Calculate each project’s payback period, net present value (NPV), internal rate of return (IRR), and modified internal rate of return (MIRR). Which project or projects should be accepted if they are…arrow_forwardYou are a financial analyst for the Hittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12% for both projects. The projects’ expected net cash flows are as follows: Expected Net cash flows Year Project X Project Y 0 -10000 -10000 1 6350 3600 2 2988 3700 3 3145 3500 4 945 3500 Calculate each project’s payback period, net present value (NPV), internal rate of return (IRR), and profitability index (PI)arrow_forward
- You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project A Project B 0 ($50,000) ($50,000) 1 25,000 15,000 2 20,000 15,000 3 10,000 15,000 4 5,000 15,000 5 5,000 15,000 Which project or projects should be accepted if they are independent?arrow_forwardYou are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project A Project B 0 ($50,000) ($50,000) 1 25,000 15,000 2 20,000 15,000 3 10,000 15,000 4 5,000 15,000 5 5,000 15,000 Which project should be accepted if they are mutually exclusive?arrow_forwardYou are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project A Project B 0 ($50,000) ($50,000) 1 25,000 15,000 2 20,000 15,000 3 10,000 15,000 4 5,000 15,000 5 5,000 15,000 Which project will you select if your decision was based solely on the project’s payback period?arrow_forward
- You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project A Project B 0 ($50,000) ($50,000) 1 25,000 15,000 2 20,000 15,000 3 10,000 15,000 4 5,000 15,000 5 5,000 15,000 d. How might a change in the cost of capital produce a conflict between the NPV and IRR rankings of these two projects? Would this conflict exist if r were 6%? (Hint: Plot the NPV profiles.)arrow_forwardYou are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project A Project B 0 ($50,000) ($50,000) 1 25,000 15,000 2 20,000 15,000 3 10,000 15,000 4 5,000 15,000 5 5,000 15,000 Calculate each project’s modified internal rate of return (MIRR), and profitability index (PI).arrow_forwardYou are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project A Project B 0 ($50,000) ($50,000) 1 25,000 15,000 2 20,000 15,000 3 10,000 15,000 4 5,000 15,000 5 5,000 15,000 Calculate each project’s payback period, net present value (NPV), internal rate of return (IRR), modified internal rate of return (MIRR), and profitability index (PI). Which project will you select if your decision was based solely on the project’s payback period? Which project or projects should be accepted if they are independent? Which project should be accepted if they are mutually exclusive? d. How might a change in the cost of capital produce a conflict between the NPV and…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub

Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning


EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT

Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College

Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub