FIN620_Quiz HW 3
docx
keyboard_arrow_up
School
University of Maryland Global Campus (UMGC) *
*We aren’t endorsed by this school
Course
620
Subject
Finance
Date
Apr 3, 2024
Type
docx
Pages
3
Uploaded by MajorMoleMaster406
Quiz HW 3 - Capital Investment Decisions Question 1 1/ 1 point Vance incorporated is considering investing in a project with the following expected cash flows: -126, 71, 52, 21. If Vance's expected cost of capital is 13.56%, what is the expected NPV of the project? Round the answer to two decimals. Answer: -8.82 v > View question 1 feedback Question 2 1/ 1 point Heinlein Inc is considering investing in a project with a cost of $100k. If the project is expected to produce cash flows of $50k in year 1, $73k in year 2, and $445k in year 3, what is the payback period. Round the answer to two decimals. Answer: 1.68 v D View question 2 feedback Question 3 1/ 1 point Heinlein Inc is considering investing in a project with a cost of $100k. The project is expected to produce cash flows of $50 in year 1, 95 in year 2, and 236 in year 3. If the discount rate is 9.1% what is the discounted payback period.
Answer: 168 v Question 4 2/ 2 points If the Present Value of all estimated futures costs of a 10 year new investment project is 267, and the future value of all expected profits is 789, what is the projects MIRR? Round the answer to two decimals in percentage form. Write % sign in the units box. Answer: 1144 & % & D View question 4 feedback Question 5 2/ 2 points Project Salerino has the following cash flows: CFO = -100, CO1 = -338, C02 = 396, C03 = 439, CO04 = -23. What is the PV of only the costs to Salerino if the cost of capital is 13.00%? All and only cashflows CFO, CO1 and C04 are costs. Round the answer to two decimals. Answer: -413.22 v D View question 5 feedback Question 6 1/ 1 point A firm invests in a project that will produce a steady yearly savings of $6,554,655 starting one year from now. The investment needed for the project is $119,363,162. What is the IRR of the project? Round the answer to two decimals in percentage form. Write % sign in the units box. Answer: 549 v/ % D> View question 6 feedback
Question 7 1/ 1 point A firm invests in a project that will produce a steady yearly savings of $115,000 starting one year from now. The investment needed for the project is $880,000. The required rate of return is 8%. What is the NPV of the project? Answer: 557,500.00 v Attempt Score:9 / 9 - 100 % Overall Grade (highest attempt):9 / 9 - 100 %
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Documents
Related Questions
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 9 percent.
Time:
0
1
2
3
4
5
Cash flow:
-76
-76
0
111
86
61
rev: 11_25_2016_QC_CS-70617
Multiple Choice
1.49, accept
66.35, accept
9.00, reject
37.21, accept
arrow_forward
Pls help on this question ASAP
arrow_forward
L4
arrow_forward
please be soecific w answer pls complete the box
arrow_forward
Question
Compute the IRR statistic for Project A and note whether the firm should accept or reject the project with the cash flows shown
below if the appropriate cost of capital is 12 %.
Time
1
2
3
4
5
Cash
Flow ($92,000$42.999 $45,668 $38,554 $36,778 $47,000
O The project's IRR is 36.3 % and the project should be accepted.
O The project's IRR is 65.5 % and the project should be accepted.
O The project's IRR is 23.9 % and the project should be rejected..
O The project's IRR is 43.2 % and the project should be accepted.
arrow_forward
Pls correctly help thanks all
arrow_forward
Consider projects Alpha and Beta:
Cash Flows ($)
C₁
Co
Project
Alpha -385,000 246,000 272,995
Beta -195,000 133,500 147,000 28
IRR
( 8 )
Which project did you choose?
22
The opportunity cost of capital is 8%. Suppose you can undertake Alpha or Beta, but not both. Use the IRR rule to make the choice.
(Hint: What's the incremental investment in Alpha?)
Which project did you choose?
arrow_forward
QUESTION 8
The INTERNAL RATE OF RETURN for the project shown above is:
O 3.92%
O 13.25
O 15.17%
9 21.22%
O No IRR
QUESTION 9
arrow_forward
Compute the Pl statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown
below if the appropriate cost of capital is 6 percent.
Time:
Cash flow:
0
-79
1
-79
2
0
3
104
4
79
V
5
54
arrow_forward
Question 12, P 8-30 (similar to)
Part 1 of 6
>
HW Sc
Poi
You are considering the following two projects and can take only one. Your cost of capital is 10.6%. The cash flows for the two projects a
a. What is the IRR of each project?
b. What is the NPV of each project at your cost of capital?
c. At what cost of capital are you indifferent between the two projects?
d. What should you do?
a. What is the IRR of each project?
The IRR for project A is ☐ %. (Round to one decimal place.)
Data table
(Click on the following icon in order to copy its contents into a spreadsheet.)
Project
A
B
Year 0
- $99
Year 1
$27
$99
$49
Year 2
$32
$38
Print
Done
Year 3
Year 4
$38
-$49
$32
$22
arrow_forward
Hii ticher please given correct answer general Accounting
arrow_forward
Answer in Excel, Attached is Question.
arrow_forward
B
с
D
E
1 Using the set of assumptions calculate the NPV, BCR and IRR for this project:
2
3 EBIT
4 CapEx
5 Depreciation
6 Increased working capital
7
Shares outstanding
8 Tax rate
9 WACC
10 Terminal growth rate
11 Value of debt
12
13
14 EBIT
15 Tax
16 EAT
17 Dep
18 Cap expenditures
19 Increase in WC
20 FCF
21
22
23 WACC
24 Terminal growth rate
25
Terminal value
26
27
28 Value of debt
29 Value of equity
30 Shares outstanding
31 Estimated value per share
Estimated value of firm
$120.0 million
$25.0 million
$15.0 million per year
$18.0 million
4.0 million
21.00%
12.50%
4.00%
$85.0 million
17.50%
21.00%
10.00%
12.50%
4.00%
1
Year 1
Year 1
Fixed over 5 years
2
F
Growing at
Growing at
3
G
17.50%
10.00%
4
H
5
I
6
arrow_forward
Check my wor
Compute the NPV for Project X and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent.
Time:
1
4
Cash flow:
-110 -110
170
145
120
Multiple Choice
$103.10
$323.20
$111.35
$111.90
80
888
DII
arrow_forward
Consider the following two projects:
Cash flows
Project A
Project B
C0�0
−$ 240
−$ 240
C1�1
100
123
C2�2
100
123
C3�3
100
123
C4�4
100
a. If the opportunity cost of capital is 8%, which of these two projects would you accept (A, B, or both)?
b. Suppose that you can choose only one of these two projects. Which would you choose? The discount rate is still 8%.
c. Which one would you choose if the cost of capital is 16%?
d. What is the payback period of each project?
e. Is the project with the shortest payback period also the one with the highest NPV?
f. What are the internal rates of return on the two projects?
g. Does the IRR rule in this case give the same answer as NPV?
h. If the opportunity cost of capital is 8%, what is the profitability index for each project?
i. Is the project with the highest profitability index also the one with the highest NPV?
j. Which measure should you use to choose between the projects?
arrow_forward
Use attachment to answer question
q2- This question relates to the diagram, which shows the NPV profile for Projects X and Y.
At what cost of capital are we indifferent between Projects X and Y?
Select one:
a.
13%
b.
4%
c.
10%
d.
9%
arrow_forward
Value/other investment criteria (i
Saved
Help
Save
Consider the following two projects:
Cash flows
Project A Project B
-$270
CO
-$270
С1
115
143
C2
115
143
Сз
115
143
C4
115
a. If the opportunity cost of capital is 10%, which of these two projects would you accept (A, B, or both)?
b. Suppose that you can choose only one of these two projects. Which would you choose? The discount rate is still 10%.
Which one would you choose if the cost of capital is 15%?
d. What is the payback period of each project?
e. Is the project with the shortest payback period also the one with the highest NPV?
f. What are the internal rates of return on the two projects?
g. Does the IRR rule in this case give the same answer as NPV?
h-1. If the opportunity cost of capital is 10%, what is the profitability index for each project?
h-2. Is the project with the highest profitability index also the one with the highest NPV?
h-3. Which measure should you use to choose between the projects?
Complete this question by…
arrow_forward
Can you show me how this is done?
Kepner Inc, is considering a capital investment project. that will provide annual cash flows of $31,248, requires an initial investment of $62,241, and the PV of cash flows is $106,796.
What is the profitability index of the project? Round your answer 2 decimal places
Selected Answer:
76
Correct Answer:
1.72 ± 0.01
arrow_forward
8
arrow_forward
A firm is considering the following independent projects.
Project
Investment
Present value offuture cash flows
NPV
A
$130
$176
$46
B
$103
$115
$12
C
$183
$287
$104
D
$161
$199
$38
E
$184
$273
$89
What is the Profitability Index of Project B?
Question 5Answer
a.
0.85
b.
1.12
c.
0.89
d.
1.18
arrow_forward
Consider projects Alpha and Beta:
Cash Flows ($)
Project
C0
C1
C2
IRR (%)
Alpha
−384,000
247,000
268,994
22
Beta
−194,000
134,000
142,000
27
The opportunity cost of capital is 8%. Suppose you can undertake Alpha or Beta, but not both. Use the IRR rule to make the choice. (Hint: What’s the incremental investment in Alpha?)Which project did you choose?multiple choice
Alpha
Beta
arrow_forward
Consider projects Alpha and Beta:
Cash Flows ($)
Project
C0
C1
C2
IRR (%)
Alpha
−398,000
259,000
188,991
9
Beta
−193,000
140,000
82,000
11
The opportunity cost of capital is 8%. Suppose you can undertake Alpha or Beta, but not both. Use the IRR rule to make the choice. (Hint: What’s the incremental investment in Alpha?)
Which project did you choose?
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you

Related Questions
- Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 9 percent. Time: 0 1 2 3 4 5 Cash flow: -76 -76 0 111 86 61 rev: 11_25_2016_QC_CS-70617 Multiple Choice 1.49, accept 66.35, accept 9.00, reject 37.21, acceptarrow_forwardPls help on this question ASAParrow_forwardL4arrow_forward
- please be soecific w answer pls complete the boxarrow_forwardQuestion Compute the IRR statistic for Project A and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 %. Time 1 2 3 4 5 Cash Flow ($92,000$42.999 $45,668 $38,554 $36,778 $47,000 O The project's IRR is 36.3 % and the project should be accepted. O The project's IRR is 65.5 % and the project should be accepted. O The project's IRR is 23.9 % and the project should be rejected.. O The project's IRR is 43.2 % and the project should be accepted.arrow_forwardPls correctly help thanks allarrow_forward
- Consider projects Alpha and Beta: Cash Flows ($) C₁ Co Project Alpha -385,000 246,000 272,995 Beta -195,000 133,500 147,000 28 IRR ( 8 ) Which project did you choose? 22 The opportunity cost of capital is 8%. Suppose you can undertake Alpha or Beta, but not both. Use the IRR rule to make the choice. (Hint: What's the incremental investment in Alpha?) Which project did you choose?arrow_forwardQUESTION 8 The INTERNAL RATE OF RETURN for the project shown above is: O 3.92% O 13.25 O 15.17% 9 21.22% O No IRR QUESTION 9arrow_forwardCompute the Pl statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 6 percent. Time: Cash flow: 0 -79 1 -79 2 0 3 104 4 79 V 5 54arrow_forward
- Question 12, P 8-30 (similar to) Part 1 of 6 > HW Sc Poi You are considering the following two projects and can take only one. Your cost of capital is 10.6%. The cash flows for the two projects a a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of capital are you indifferent between the two projects? d. What should you do? a. What is the IRR of each project? The IRR for project A is ☐ %. (Round to one decimal place.) Data table (Click on the following icon in order to copy its contents into a spreadsheet.) Project A B Year 0 - $99 Year 1 $27 $99 $49 Year 2 $32 $38 Print Done Year 3 Year 4 $38 -$49 $32 $22arrow_forwardHii ticher please given correct answer general Accountingarrow_forwardAnswer in Excel, Attached is Question.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
