1.
Which of the following is one of the three restrictions Congress usually places on appropriations?
A
.
Amount
B
.
Disbursing method
C
.
Events
D
.
Unit Training
10 points QUESTION 2
1.
__________ links accession, retention, and promotion targets to Army requirements as measured against the military manning program in the PPBE.
A
.
Equipment modernization
B
.
Training oversight
C
.
Equipping guidance
D
.
Manpower management
10 points QUESTION 3
1.
Which type of contract includes a mix of the Logistics Civil Augmentation Program (LOGCAP), the Air Force Contract Augmentation Program, the Navy Global Contingency Construction Multiple Award Contract, and Global Contingency Service Multiple Award Contract?
A
.
Systems support
B
.
External support
C
.
Theater support
D
.
Internal support
10 points QUESTION 4
1.
Which of the following has the mission to "streamline payment procedures and reduce the administrative burden associated with purchasing supplies and services"?
A
.
GCCS-A
B
.
DTS
C
.
GFEBS
D
.
GPC
10 points QUESTION 5
1.
Your commander has asked you, the S-3, where your BCT falls on the resourcing priority list compared to other units. Where would you find this information?
A
.
Force Allocation Decision Model (FADM)
B
.
Army Resource Priority List (ARPL)
C
.
Dynamic Army Resource Priority List (DARPL)
D
.
Integrated Requirements Priority List (IRPL)
10 points QUESTION 6
1.
Who is responsible for producing and updating the force allocation decision model (FADM)?
A
.
J-8
B
.
DCS, G-3/5/7
C
.
J-5
D
.
Army Comptroller
10 points QUESTION 7
1.
__________ is the category, or "color of money," which most of the available funds in a unit spend plan derive from.
A
.
Military personnel
B
.
Operations and maintenance
C
.
Base budget
D
.
Military construction
10 points QUESTION 8
1.
The expression "colors of money" is used in relation to appropriations to describe what?
A
.
Time
B
.
Purpose
C
.
Events
D
.
Unit Training
10 points QUESTION 9
1.
__________ are usually things a unit wants or needs, but because of resource constraints could not acquire inside its existing budget.
Lesson, Understanding Resource Management: Fiscal Law, page 34-03
A
.
Unfunded requirements
B
.
Above the line items
C
.
Below the line items
D
.
None of the above
10 points QUESTION 10
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
The project budgeting process involves two steps. The first step is to determine the total budgeted cost (TBC), which is the aggregate amount of the estimated costs of all the specific activities to perform and complete a work package or the project.
Review the below Budgeted Cost table for the five working days per activity and calculate the cumulative total cost (CTC) per each of the five days.
arrow_forward
17. The CPM schedule provides a great deal of information that is useful to a construction
project manager. What do you believe are the three most useful applications, and why do they
top your list?
18. Discuss why are various sorts of CPM data useful? Provide at least examples.
19. An example of hammock activities have been given in your textbook for the bridge project.
Provide an example of a hammock activity for the building project, together with the predecessor
and successor activities.
20. Why is the bar chart not an adequate planning and scheduling tool? And, why is it still
widely used in the construction industry?
arrow_forward
When a civil engineer is a prime professional and is constructing a market building, what should be his/her minimum compensation if the project construction cost is:
a. 15 million
b. 30 million
c. 45 million
d. 28 million
When a civil engineer is a prime professional and is constructing a tower, what should be his/her minimum compensation if the project construction cost is:
a.12 million
b. 14,500,000
c. 33,000,300
d. 9,600,017
Show your solution
arrow_forward
The following eight activities constitute an overall bar chart portrayal of a 4-month project.
After 1.5 months, activities A, B, D are completed and E is 50% complete, for a cost of $80,000.
For this project, using earned value concepts, determine the schedule and cost variance. Is the
project ahead or behind schedule? Over or under budget?
Activity
A
B
с
D
E
F
G
H
Cost
$2,000
$1,000
$6,000
$2,000
$7,000
$9,000
$3,000
$10,000
Month 1
Month 2
Month 3
Month 4
arrow_forward
Explain the significance of Present Service Index (PSI) with the help of a diagram.
arrow_forward
Using the same CPM diagram, what is the total project duration?
Immediate
Estimated
Activity
Activity Description
Predecessors
Duration
A
Excavate
2 weeks
Lay the foundation
Put up the rough wall
Put up the roof
Install the exterior plumbing
Install the interior plumbing
Put up the exterior siding
Do the exterior painting
B
A
4 weeks
C
10 weeks
D
C
6 weeks
4 weeks
5 weeks
7 weeks
9 weeks
7 weeks
8 weeks
4 weeks
E
C
F
E
G
D
E, G
Do the electrical work
F, I
Put up the wallboard
Install the flooring
Do the interior painting
Install the exterior fixtures
K
5 weeks
M
2 weeks
N
Install the interior fixtures
K, L
6 weeks
Total = 79 weeks
arrow_forward
Refer back to Chapter 7
In the real world, a limited number of days can be taken out of the schedule before it becomes impractical to try to shorten the
schedule further. Though it is impractical to take the exercise to the theoretical limit of shortening, there is a theoretical limit that
prevents any further
shortening of the project. What defines this theoretical limit, and what conditions exist in the schedule when this limit is reached?
arrow_forward
Draw the node diagram and perform the CPM
computations for the schedule shown.
Tabulate ES, EF, LS, LF, TT, and LF.
Identify the critical path and the total duration of the
project.
Activity
Duration
IPA
Lag
ES
EF
LS
LF
TF
FF
A
B
A
4
A
3
D
A
E
B
F
7
В
G
6
H
8
D
4
3
7
E, G
F
2
K
4
F, G, H
L
1
H
3
M
K, L
2.
arrow_forward
NO HANDWRITING PLEASE. I HAVE A HARD TIME UNDERSTANDING. THANK YOU FOR YOUR HELP.
arrow_forward
Develop a logic network for the sequence of activities listed in the table. Calculate the ES, EF, LS and LF times for all activities.
What is the project duration?
What are the critical activities?
Activity
Duration
PIB
5
4
None
10
2
None
15
4
5
20
3
5
25
5
10
30
1
15
35
3
25
40
7
20, 30, 35
arrow_forward
A particular project is scheduled to complete in Week 50 at a budgeted cost of $150,000. As of Week 30, an earned value chart is prepared to
present the project progress as below:
Status Date
160-
140
PV
120
100
80
AC
60
40-
20
10
15
20
25
30
35
40
45
50
Weeks
1. Calculate schedule, cost and time variances, as well as schedule and cost performance indices for Week 30. Then use this information
to comment on the project progress at Week 30 (status date).
2. Based on the performance at Week 30, estimate the final project cost (EAC). Will the final project cost be higher or lower than the
budgeted cost, and by how much? Also estimate the revised project completion date. Will the project complete sooner or later than the
planned completion date, and by how many weeks?
000.S
arrow_forward
Assignment # 1
3. For the following schedule, draw the arrow diagram
(AOA), perform the CPM calculations, mark the
critical path, and complete the table.
Activity Duration Precedent ES EFLS LFTFFF
A
B
C
D
E
F
G
H
I
J
K
L
M
3
10
7
6
5
4
2
4
10
6
4
2
1
A
A
B
B, C
с
D
D, E
E
E, F
G, H, I
H, I
J, L
CRITICAL PATH
arrow_forward
Question #5: In the real world, a limited number of days can be taken out of the
schedule before it becomes impractical to try to shorten the schedule further.
Though it is impractical to take the exercise to the theoretical limit of shortening,
there is a theoretical limit that prevents any further shortening of the project. What
defines this theoretical limit, and what conditions exist in the schedule when this
limit is reached? Explain each response in detail.
arrow_forward
*. From the given data as shown below, determine the
following:
A) What is the critical path?
B) What is the average manpower?
C) Determine the manpower scheduling of the project.
Activity Successor WEEKS Manpower
1-2 B D, E
3
1-3 A F
5
1-4 C
4
2-5 D
4
2-6 E I
4
3-6 F
I
7
4-6 G
I
3
4-7 H L, M
3
5-8 J O
5
5-9 K
N
4
6-9 I
N
8
3
5
6
7-9 L
7-10 M
8-11 O
9-11 N
10-11 P
H, G
J, K
N
P
8
7
5
4
3
3
6
4
4
4
5
5
3
5
4
6
5
arrow_forward
d Describe the Terms Below (C
1) AASHTO.
5) PG 76-22
2) G.I.
6) Short term aging
arrow_forward
10. Provide at least 3 reasons with an explanation of why seeking the optimum manpower allocation is impractical
arrow_forward
Engineering management , i need solutions in 15 minutes please.
arrow_forward
Engineering management , i need solutions in 15 minutes please.
arrow_forward
i need the answer quickly
arrow_forward
1. A project your firm is considering for implementation has these estimated costs and revenues: an investment cost of $50,000; maintenance costs that start at $5,000 at the end of year (EOY) 1 and increase by $1,000 for each of the next 4 years, and then remain constant for the following 5 years; savings of $20,000 per year (EOY 1-10); and finally a resale value of $35,000 at the EOY 10. If the project has a 10-year life and the firm's MARR is 10% per year, what is the present worth of the project? Is it a sound investment opportunity?
2. A toll bridge across the Mississippi River is being considered as a replacement for the current 1-40 bridge linking Tennessee to Arkansas. Because this bridge, if approved, will become a part of the U.S. Interstate Highway system, the B-C ratio method must be applied in the evaluation. Investment costs of the structure are estimated to be $17,500,000 and $325,000 per year in operating and maintenance costs are anticipated. In addition, the bridge…
arrow_forward
QUESTION 6.
The activities involved in the construction of a new shopping mall are given in Table Q6. One
resource type will be used during the contract. Determine minimum level of the resource
required to complete the project.
Table Q6
Activity
Duration
Predecessors
Resource (units/week)
(Weeks)
A
B
2
2
2
1
2
3
1
5
3
1
E
2
6.
2
F
G
3
H
6.
4
4
4
5, 6
6, 7
2, 8
2, 8, 9
10, 11, 12, 13
4
2
K
2
L.
2.
arrow_forward
10. Discuss what is the intended use for each of the following cost models?
a. Project budget
b. Project cost breakdown or schedule of values
c. Progress estimates
d. Change order estimates
e. Project cash flow
f. Final estimate
arrow_forward
The following bar chart shows the activities to complete a project in 6 months (each cell represents 1 month). The total project cost is $700.
After 3 months, Activities A, B, half of C, and half of D are completed, for a cost of $200. For this point in time (2 months after the start date), what are the values of the budgeted cost of work performed, the budgeted cost of work scheduled, and the actual cost of the work performed?
arrow_forward
Outline probable cost component and all possible consideration to establish budget proposal for a typical project and relate in practice methods/combination of charges for engineering services (select type of project).
arrow_forward
Engineering Management
arrow_forward
Topic: Fixed, Increment, and Sunk Costs.
Please show your complete solution.
arrow_forward
i need the answer quickly
arrow_forward
What trade-offs are involved in each of these aspects of inventory management?c. Conducting cycle counts once a quarter instead of once a year.
arrow_forward
8- Based on the below-Eamed Value chart, what is the status of the project schedule and cost at the time
of the report?
BCWS or PV
BCWP or EV
ACWP or AC
Start
Report
Schedule
Cumulative $
arrow_forward
4. Project managers have many resources that are not directly under their control, such as the designer and the owner. Provide at
least 5 bulleted points describing in detail how project managers can manage (influence) resources outside of their control or above
them in the contractual hierarchy.
5. For the following simple seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity
(ES, EF, LS, LF, TF), and calculate the project duration. Then draw a time-scaled network and under it a labor resource histogram for
the ES. Do the same for the LS. In both cases, use the maximum allowable number of workers. Make adjustments to the noncritical
activities, within the constraints of the ES and LF and the maximum and minimum workers
allowed to provide what you feel is the best labor distribution. Please use Table B (Table B.pdf) Lastly, Explain in detail what do
you feel is the biggest problem with the ES and LS configurations, and how has…
arrow_forward
How can the problems caused due to mobilization payment be solved?
arrow_forward
1
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Related Questions
- The project budgeting process involves two steps. The first step is to determine the total budgeted cost (TBC), which is the aggregate amount of the estimated costs of all the specific activities to perform and complete a work package or the project. Review the below Budgeted Cost table for the five working days per activity and calculate the cumulative total cost (CTC) per each of the five days.arrow_forward17. The CPM schedule provides a great deal of information that is useful to a construction project manager. What do you believe are the three most useful applications, and why do they top your list? 18. Discuss why are various sorts of CPM data useful? Provide at least examples. 19. An example of hammock activities have been given in your textbook for the bridge project. Provide an example of a hammock activity for the building project, together with the predecessor and successor activities. 20. Why is the bar chart not an adequate planning and scheduling tool? And, why is it still widely used in the construction industry?arrow_forwardWhen a civil engineer is a prime professional and is constructing a market building, what should be his/her minimum compensation if the project construction cost is: a. 15 million b. 30 million c. 45 million d. 28 million When a civil engineer is a prime professional and is constructing a tower, what should be his/her minimum compensation if the project construction cost is: a.12 million b. 14,500,000 c. 33,000,300 d. 9,600,017 Show your solutionarrow_forward
- The following eight activities constitute an overall bar chart portrayal of a 4-month project. After 1.5 months, activities A, B, D are completed and E is 50% complete, for a cost of $80,000. For this project, using earned value concepts, determine the schedule and cost variance. Is the project ahead or behind schedule? Over or under budget? Activity A B с D E F G H Cost $2,000 $1,000 $6,000 $2,000 $7,000 $9,000 $3,000 $10,000 Month 1 Month 2 Month 3 Month 4arrow_forwardExplain the significance of Present Service Index (PSI) with the help of a diagram.arrow_forwardUsing the same CPM diagram, what is the total project duration? Immediate Estimated Activity Activity Description Predecessors Duration A Excavate 2 weeks Lay the foundation Put up the rough wall Put up the roof Install the exterior plumbing Install the interior plumbing Put up the exterior siding Do the exterior painting B A 4 weeks C 10 weeks D C 6 weeks 4 weeks 5 weeks 7 weeks 9 weeks 7 weeks 8 weeks 4 weeks E C F E G D E, G Do the electrical work F, I Put up the wallboard Install the flooring Do the interior painting Install the exterior fixtures K 5 weeks M 2 weeks N Install the interior fixtures K, L 6 weeks Total = 79 weeksarrow_forward
- Refer back to Chapter 7 In the real world, a limited number of days can be taken out of the schedule before it becomes impractical to try to shorten the schedule further. Though it is impractical to take the exercise to the theoretical limit of shortening, there is a theoretical limit that prevents any further shortening of the project. What defines this theoretical limit, and what conditions exist in the schedule when this limit is reached?arrow_forwardDraw the node diagram and perform the CPM computations for the schedule shown. Tabulate ES, EF, LS, LF, TT, and LF. Identify the critical path and the total duration of the project. Activity Duration IPA Lag ES EF LS LF TF FF A B A 4 A 3 D A E B F 7 В G 6 H 8 D 4 3 7 E, G F 2 K 4 F, G, H L 1 H 3 M K, L 2.arrow_forwardNO HANDWRITING PLEASE. I HAVE A HARD TIME UNDERSTANDING. THANK YOU FOR YOUR HELP.arrow_forward
- Develop a logic network for the sequence of activities listed in the table. Calculate the ES, EF, LS and LF times for all activities. What is the project duration? What are the critical activities? Activity Duration PIB 5 4 None 10 2 None 15 4 5 20 3 5 25 5 10 30 1 15 35 3 25 40 7 20, 30, 35arrow_forwardA particular project is scheduled to complete in Week 50 at a budgeted cost of $150,000. As of Week 30, an earned value chart is prepared to present the project progress as below: Status Date 160- 140 PV 120 100 80 AC 60 40- 20 10 15 20 25 30 35 40 45 50 Weeks 1. Calculate schedule, cost and time variances, as well as schedule and cost performance indices for Week 30. Then use this information to comment on the project progress at Week 30 (status date). 2. Based on the performance at Week 30, estimate the final project cost (EAC). Will the final project cost be higher or lower than the budgeted cost, and by how much? Also estimate the revised project completion date. Will the project complete sooner or later than the planned completion date, and by how many weeks? 000.Sarrow_forwardAssignment # 1 3. For the following schedule, draw the arrow diagram (AOA), perform the CPM calculations, mark the critical path, and complete the table. Activity Duration Precedent ES EFLS LFTFFF A B C D E F G H I J K L M 3 10 7 6 5 4 2 4 10 6 4 2 1 A A B B, C с D D, E E E, F G, H, I H, I J, L CRITICAL PATHarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Structural Analysis (10th Edition)Civil EngineeringISBN:9780134610672Author:Russell C. HibbelerPublisher:PEARSONPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
- Fundamentals of Structural AnalysisCivil EngineeringISBN:9780073398006Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel LanningPublisher:McGraw-Hill EducationTraffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning