a)
To determine: The time taken to complete the task at the end of second day.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
b)
To determine: The time taken to complete the task at the end of fourth day.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
c)
To determine: The time taken to complete the task at the end of eighth day.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
d)
To determine: The time taken to complete the task at the end of sixteenth day.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Want to see the full answer?
Check out a sample textbook solutionChapter E Solutions
Operations Management
- Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the second plane took 18,000 hours to produce. Using an 85% learning curve and a $35-per-hour labor charge, he wants to determine the cost of the six additional planes. Part 2 Time required for the sixth unit = 13900 hours (round your response to the nearest whole number). Part 3 Cost of the sixth unit = 486500 dollars (round your response to the nearest whole number). Part 4 Time required for the seventh unit = enter your response here hours (round your response to the nearest whole number). Part 5. Cost of the seventh unit?arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 35 hours. The contractor estimates an 85 percent learning rate. Without using the computer: a. How long do you estimate the time required to install the second pool? b. How long do you estimate the time required to install the fourth pool?arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 38 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool? The time required to install the sixth pool is enter your response herehours. (Enter your response rounded to two decimal places.) Part 2 What is your estimate of the total time for all six pools? The total time for all six pools is enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forward
- The owner of Touchdown Sports Bar wants to develop a time standard for the task of mixing a specialty cocktail. In a preliminary study, he observed one of his bartenders perform this task seven times with an average of 90 seconds and a standard deviation of five seconds. What is the standard time for this task if the bartender worked at a 20 percent faster pace than is average, and an allowance of 10 percent of job time is used?arrow_forward9. Manufacturer Ċ went through serious process changes in order to eliminate unnecessary processes from the work flow. However they have to bare the slow down in the process for a while due to this transition. They want to estimate when they can reach to the expected performance level based on a 'learning curve' study. For a certain task they have measured a completion time of 137 minutes in the first time an average employee finished the renewed task. Please provide the values in the below table for three different learning rates and two different repetition units. 2nd 4th 13th 27th Learning Rate 70% 80% 60%arrow_forwardLeading refers to guiding the efforts of human resources to ensure high levels of task accomplishment. True Falsearrow_forward
- Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the second plane took 18,000 hours to produce. Using an 85% learning curve and a $35-per-hour labor charge, he wants to determine the cost of the six additional planes. Time required for the sixth unit = hours (round your response to the nearest whole number).arrow_forwardOnline training could be an example of asynchronous training. True or falsearrow_forwardazmine Peters, the operations manager at Frontiers Inc., wants to estimate the learning rate for a new task her company will undertake. Jazmine has obtained completion time estimates for the first eight repetitions of this type of task as shown below. UNIT COMPLETION TIME (in hours) 1 33 2 30.361 3 28.915 4 27.931 5 27.191 6 26.602 7 26.113 8 25.7arrow_forward
- The first unit of a job took 40 hours to complete. The work has a learning percentage of 88. The manager wants time estimates for units 2, 3, 4, and 5. Develop those time estimates.arrow_forwardSuad Alwan, the purchasing agent for Dubai Airlines, has determined that the third plane took 20,000 hours to produce. Using an 80% learning curve and a $40-per-hour labor charge, he wants to determine the cost of the four additional planes. a) Time required for the fourth unit = 18,231 hours b) Cost of the fourth unit = ? dollars (round to the nearest whole number)arrow_forwardThe product S takes 67 hours for production of 1 unit, where learning curve rate is 67% and what will be the total time taken by 4th unit of product S using incremental unit time method ?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.