Operations Management
11th Edition
ISBN: 9780132921145
Author: Jay Heizer
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 9, Problem 16P
Tailwind, Inc., produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for $210, contains both gas- and liquid-filled compartments to provide more stability and better protection against knee, foot, and back injuries. Manufacturing the shoes requires 10 separate tasks. There are 40D minutes available for manufacturing the shoes in the plant each day. Daily demand is 60. The information for the tasks is as follows:
TASK | PERFORMANCE TIME (MIN) | TASK MUST FOLLOW TASK LISTED BELOW |
A | 1 | − |
B | 3 | A |
C | 2 | B |
D | 4 | B |
E | 1 | C, D |
F | 3 | A |
G | 2 | F |
H | 5 | G |
I | 1 | E, H |
J | 3 | I |
- a. Draw the precedence diagram.
- b. Assign tasks to the minimum feasible number of workstations according to the “ranked positioned weight” decision rule.
- c. What is the efficiency of the process you completed in (b)?
- d. What is the idle time per cycle?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The Sun River beverage company is a regional producer of teas, exotic juices, and energy drinks. With an interest in healthier lifestyles, there has been an increase in demand for its sugar-free formulation.
The final packing operation requires 13 tasks. Sun River bottles its sugar-free product 5 hours a day, 5 days a week. Each week, there is a demand for 3,000 bottles of this product.
TASK
TIME (MINUTES)
PRECEDING TASK
1
0.1
—
2
0.1
1
3
0.1
2
4
0.2
2
5
0.1
2
6
0.2
3, 4, 5
7
0.1
1
8
0.1
7
9
0.2
8
10
0.1
9
11
0.2
6
12
0.2
10, 11
13
0.1
12
Using the following data, solve the assembly-line balancing problem and calculate the efficiency of your solution. Use the longest task time for your decision criteria.
Note: Round your answer to the nearest whole percent.
Sue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro Popcorn
Popper. The goal is to produce five poppers per hour. The tasks,task times, and immediate predecessors for producing one MicroPopcorn Popper are as follows:TASK TIME (min)
IMMEDIATEPREDECESSORSA 10 —B 12 AC 8 A, BD 6 B, CE 6 CF 6 D, Ea) What is the theoretical minimum for the smallest number ofworkstations that Helms can achieve in this assembly line?b) Graph the assembly line, and assign workers to workstations.Can you assign them with the theoretical minimum?c) What is the efficiency of your assignment?
Canine Kernels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the following figure). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product’s price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to working on that workstation alone and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day or 40 hours/week.
The senior management at Canine…
Chapter 9 Solutions
Operations Management
Ch. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - What are the requirements for a focused work...Ch. 9 - Prob. 10DQ
Ch. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Explain the concept of cross-docking.Ch. 9 - What is a heuristic? Name several that can be used...Ch. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Three departmentsmilling (M), drilling (D), and...Ch. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Prob. 5PCh. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - After an extensive product analysis using group...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Sue Helms Appliances wants to establish an...Ch. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - The following table details the tasks required for...Ch. 9 - Tailwind, Inc., produces high-quality but...Ch. 9 - Prob. 17PCh. 9 - Because of the expected high demand for Mach 10,...Ch. 9 - Prob. 19PCh. 9 - Suppose production requirements in Solved Problem...Ch. 9 - The preinduction physical examination given by the...Ch. 9 - Samuel Smith's company wants to establish an...Ch. 9 - As the Cottrell Bicycle Co. of St. Louis completes...Ch. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Prob. 3CSCh. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek: Task Performance Time (seconds) Predecessors A 20 − B 30 A C 14 A D 15 A E 12 B, C F 27 D, E This exercise only contains parts b, c, d, e, and f. b) Given the demand, the cycle time for the production of the new train set = ____ (round your response to one decimal place). c) The theoretical minimum number of workstations is ___ d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.) e)How much is the total idle time per cycle for the process? ____ seconds f) What is…arrow_forwardThe Sun River beverage company is a regional producer of teas, exotic juices, and energy drinks. With an interest in healthier lifestyles, there has been an increase in demand for its sugar-free formulation. The final packing operation requires 13 tasks. Sun River bottles its sugar-free product 5 hours a day, 5 days a week. Each week, there is a demand for 2,500 bottles of this product. TASK 1 4 6 8 9 10 11 12 13 PERFORMANCE TIME TASK MUST (MINUTES) FOLLOW 0.1 0.2 Efficiency 0.2 0.2 0.1 0.3 0.3 0.1 0.3 0.2 0.1 0.1 0.1 2 7 B 9 6 10, 11 12 Using the above data, solve the assembly-line balancing problem and calculate the efficiency of your solution. Use the longest task time for your decision criteria. (Enter your answer as a percentage rounded to 1 decimal place.)arrow_forwardA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed . The daily demand is 100 toys . Times of the tasks are 2.73,2.01 ,2.13,2.0,2.61,2.71 and 2.95 minutes for A,B,C,D,E,F, and G, respectively . However , due to the nature of the product there are precedencerules that must be observed . Such that Task A does not need any predecessors ; task B requires task A to becompleted . To start task C and task Deach require task B to be completed . Task must be completed prior to stating task E. Task F needs both task and task E to be completed . Finally , task G can start only once task F is completed . Given we apply the most remaining tasks rule for balancing the assembly line , with ties broken according to longesttask time first , the tasks that will be assigned to the THIRD workstation are a. D and F b . None is the correct answer c. D only d. E only e. B, C , and Darrow_forward
- The M–N plant manufactures two different products: M and N. Selling prices and weekly market demands are shown in the following diagram. Each product uses raw materials with costs as shown. The plant has three different machines: A, B, and C. Each performs different tasks and can work on only one unit of material at a time. Process times for each task are shown in the diagram. Each machine is available 2,500 minutes per week. There are no "Murphys" (major opportunities for the system to foul up). Setup and transfer times are zero. Demand is constant. Operating expenses (including labor) total a constant $12,000 per week. Raw materials are not included in weekly operating expenses. a. Which machine is the constraint in this plant? multiple choice Machine A Machine C Machine B Incorrectarrow_forwardA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 261, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed. What is the minimum number of workstations needed? O a. None of them O b. 8 O c. 4 d. 2 Oe. e to searcharrow_forwardKiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow: Task Information for Kiko Teddy Bear Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…arrow_forward
- Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow: Task Information for Kiko Teddy Bear Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…arrow_forwardWaldorf Astoria Spa & Health Club at Waldorf Astoria Chicago offers high-quality hair-styling and physical relaxation services at a reasonable price, so it always has unlimited demand. The process comprised of five tasks that are completed in the sequence described below. (The time required for each task is shown in parenthesis). Task 1: Welcome a guest and offer homemade herb tea (10 minutes) Task 2: Wash and condition hair (10 minutes) Task 3: Neck, shoulder, and back stress release massage (10 minutes) Task 4: Design the hairstyle and do the hair (25 minutes) Task 5: Check out the guest (5 minutes) Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 completes Task 1. S2 completes Tasks 2 and 3. S3 completes Tasks 4 and 5. Assume a wage rate of $18 per hour. What are the direct labor costs for one guest?arrow_forwardQuestions 67, 68, 69arrow_forward
- A time study involving the preparation of hamburgers at Bill’s fast-food restaurant used the snap-back method to obtain the data (in minutes) shown below. Allowances typically constitute 15% of normal time. The schedule calls for 300 hamburgers to be prepared during the lunch rush. If each part-time employee works 190 minutes per day, how many employees will be needed? Observation Work Element 1 2 3 4 5 t F RF NT 1. Prepare Patty 0.45 0.41 0.50 0.48 0.36 1 0.9 2. Cook First side 0.85 0.81 0.77 0.89 0.83 1 1.2 3. Flip, press, and cook the other side 0.60 0.55 0.59 0.58 0.63 1 1.2 4. Assemble 0.31 0.24 0.27 0.26 0.32 1 1.0 Show workarrow_forwardA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according ?to longest task time first, What will the estimated idle time in minutes for FIRST workstation 0.06 .a O None is the correct anser .b O 0.09 .c O 1.00 .d O 1.85 .e O ace 近arrow_forwardA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed. Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, What will the estimated idle time in minutes for FOURTH workstation? O a. 0.06 O b. None is the correct answer О с. 1.85 O d. 1.00 e. 0.09arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY