Fundamentals of Corporate Finance
Fundamentals of Corporate Finance
11th Edition
ISBN: 9780077861704
Author: Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Bradford D Jordan Professor
Publisher: McGraw-Hill Education
Question
Book Icon
Chapter 9, Problem 13QP
Summary Introduction

To calculate: The rate of crossover for two projects.

Introduction:

The net present value is one of the capital budgeting techniques, which is used to identify the profitability in the proposed investment. The internal rate of return is a rate of discount, which makes the predictable investment’s NPV equal to zero.

Expert Solution & Answer
Check Mark

Answer to Problem 13QP

The crossover rate for the two projects is 10.19%. The NPV profiles show that both the projects have a higher NPV for the rate of discount below 10.19% and have a lower NPV for the rate of discount above 10.19%.

Explanation of Solution

Given information:

The details of two projects are provided. The project X cash that flows for year 1, year 2, and year 3, are $10,620, $10,900, and $10,500 respectively. The initial investment is $24,000. The project Y cash that flows for 4 years are $12,100, $9,360, $10,400 respectively and the initial investment is $24,000.

Note:

  • NPV is the difference between the present values of the cash inflows from the present value of cash outflows.
  • The IRR is the rate of interest, which makes the project’s NPV equal to zero. Hence, when using the available information, assume that the NPV is equal to zero and forms an equation to compute the IRR.

Equation of NPV to compute IRR by assuming that NPV is equal to zero is as follows:

NPV=0=$24,000+$10,600(1+IRR)+$10,900(1+IRR)2+$10,500(1+IRR)30=$24,000+$10,600(1+IRR)+$10,900(1+IRR)2+$10,500(1+IRR)3

Compute IRR for the project X using a spreadsheet:

Step 1:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  1

  • Type the equation of NPV in H6 of the spreadsheet and consider the IRR value as H7.

Step 2:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  2

  • Assume the IRR value as 10%.

Step 3:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  3

  • In the spreadsheet, go to data and select the what-if-analysis.
  • In what-if-analysis, select goal seek.
  • In a set cell, select H6 (the Formula).
  • The “To value” is considered as 0 (the assumption value for NPV).
  • The H7 cell is selected for the 'by changing the cell'.

Step 4:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  4

  • Following the previous step click OK in the goal seek. The goal seek status appears with the IRR value

Step 5:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  5

  • The value appears to be 15.9555848576331%

Hence, the IRR value is 15.96%.

Compute the IRR for project Y using a spreadsheet:

Step 1:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  6

  • Type the equation of NPV in H6 of the spreadsheet and consider the IRR value as H7.

Step 2:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  7

  • Assume the IRR value as 10%.

Step 3:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  8

  • In the spreadsheet, go to data and select the what-if-analysis.
  • In what-if-analysis, select goal seek.
  • In a set cell, select H6 (the Formula).
  • The “To value” is considered as 0 (the assumption value for NPV).
  • The H7 cell is selected for the 'by changing the cell'.

Step 4:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  9

  • Following the previous step click OK in the goal seek. The goal seek status appears with the IRR value.

Step 5:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  10

  • The value appears to be 16.1307523542427%.

Hence, the IRR value is 16.13%.

Formula to compute the crossover rate is as follows:

Crossover rate for each year=Cash flows from project XCash flows from project Y

Equation of the crossover rate to compute R is as follows:

0=$1,480(1+R)+$1,540(1+R)2+$100(1+R)3

Where,

R” denotes crossover rate.

Compute R by using a spreadsheet:

Step 1:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  11

  • Type the equation of NPV in H6 of the spreadsheet and consider the IRR value as H7.

Step 2:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  12

  • Assume the IRR value as 10%.

Step 3:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  13

  • In the spreadsheet, go to data and select the whatif analysis.
  • In what-if analysis select goal seek
  • In set cell select H6 (the Formula)
  • The “To value” is considered as 0 (the assumption value for NPV)
  • The H7 cell is selected for the by changing cell

Step 4:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  14

  • Following the previous step click OK in the goal seek. The goal seek status appears with the IRR value.

Step 5:

Fundamentals of Corporate Finance, Chapter 9, Problem 13QP , additional homework tip  15

  • The value appears to be 10.1861807452249%

Hence, the R-value is 10.19%.

Formula to calculate the NPV is as follows:

NPV=Present value of cash inflowPresent value of cash outflow

Note: As the discount rate is over a range of 0% to 25%, calculate NPV for 0%, 5%, 10%, 15%, 20%, and 25%.

Compute the NPV with the discount rate of 0% for the project X:

NPV=Present value of cash inflowPresent value of cash outflow=($10,620(1+0)+$10,900(1+0)2+$10,500(1+0)3)$24,000=$8,020

Compute the NPV with the discount rate of 0% for the project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($12,100(1+0)+$9,360(1+0)2+$10,400(1+0)3)$24,000=$7,860

Hence, the NPV for the projects X and Y at the rate of 0% is $8,020 and $7,860 respectively.

Compute the NPV with the discount rate of 5% for the project X:

NPV=Present value of cash inflowPresent value of cash outflow=($10,620(1+0.05)+$10,900(1+0.05)2+$10,500(1+0.05)3)$24,000=$10,114.2857142857+$9,886.62131519274+$9,070.29478458049$24,000=$5071.20

Compute the NPV with the discount rate of 5% for the project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($12,100(1+0.05)+$9,360(1+0.05)2+$10,400(1+0.05)3)$24,000=$11,523.8095238095+$8,489.79591836734+$8,983.91102472735$24,000=$4,997.52

Hence, the NPV for the projects X and Y at 5% is $5071.20 and $4,997.52 respectively.

Compute the NPV with the discount rate of 10% for the project X:

NPV=Present value of cash inflowPresent value of cash outflow=($10,620(1+0.10)+$10,900(1+0.10)2+$10,500(1+0.10)3)$24,000=$9654.54545454545+$9008.26446280991+$7888.80540946656$24,000=$2,551.62

Compute the NPV with the discount rate of 10% for the project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($12,100(1+0.10)+$9,360(1+0.10)2+$10,400(1+0.10)3)$24,000=$11,000+$7735.53719008264+$7813.67392937640$24,000=$2,549.21

Hence, the NPV for the projects X and Y at the rate of 10% is $2,551.62 and $2,549.21 respectively.

Compute the NPV with the discount rate of 15% for the project X:

NPV=Present value of cash inflowPresent value of cash outflow=($10,620(1+0.15)+$10,900(1+0.15)2+$10,500(1+0.15)3)$24,000=$9,234.78260869565+$8,241.96597353497+$6,903.92044053587$24,000=$380.67

Compute the NPV with the discount rate of 15% for the project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($12,100(1+0.15)+$9,360(1+0.15)2+$10,400(1+0.15)3)$24,000=$10,521.7391304347+$7,077.50472589792+$6,838.16881729267$24,000=$437.41

Hence, the NPV for the projects X and Y at the rate of 15% is $3,80.67 and $437.41 respectively.

Compute the NPV with the discount rate of 20% for the project X:

NPV=Present value of cash inflowPresent value of cash outflow=($10,620(1+0.20)+$10,900(1+0.20)2+$10,500(1+0.20)3)$24,000=$8,850+$7,569.44444444444+$6,076.38888888888$24,000=$1,504.17

Compute the NPV with the discount rate of 20% for the project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($12,100(1+0.20)+$9,360(1+0.20)2+$10,400(1+0.20)3)$24,000=$10,083.33333333333+$6,500+$6,018.51851851851$24,000=$1,398.15

Hence, the NPV for the projects X and Y at the rate of 20% is -$1,504.17 and -$1,398.15 respectively.

Compute the NPV with the discount rate of 25% for the project X:

NPV=Present value of cash inflowPresent value of cash outflow=($10,620(1+0.25)+$10,900(1+0.25)2+$10,500(1+0.25)3)$24,000=$8,496+$6,976+$5,376$24,000=$3,152

Compute the NPV with the discount rate of 25% for the project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($12,100(1+0.25)+$9,360(1+0.25)2+$10,400(1+0.25)3)$24,000=$9,680+$5,990.4+$5,324.8$24,000=$3,004.80

Hence, the NPV for the projects X and Y at the rate of 25% is -$3,152 and -$3,004.80 respectively.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
None
Over what range of discount rates would the company choose Project A? Project B? At what discount rate would the company be indifferent between these two projects? Explain.
3) could you use the Figure below that shows the net present value profile of two projects Y and W to answer the following questions:  What is the internal rate of return on project Y?   Determine the “approximate” discount rate at which you would be indifferent between the two projects   Find the “approximate” net present value of project W when the discount rate is 4%.

Chapter 9 Solutions

Fundamentals of Corporate Finance

Ch. 9.6 - What does the profitability index measure?Ch. 9.6 - How would you state the profitability index rule?Ch. 9.7 - Prob. 9.7ACQCh. 9.7 - If NPV is conceptually the best procedure for...Ch. 9 - Prob. 9.1CTFCh. 9 - Prob. 9.2CTFCh. 9 - Prob. 9.3CTFCh. 9 - Prob. 9.4CTFCh. 9 - What is a benefitcost ratio?Ch. 9 - Prob. 9.7CTFCh. 9 - Prob. 1CRCTCh. 9 - Net Present Value [LO1] Suppose a project has...Ch. 9 - Prob. 3CRCTCh. 9 - Prob. 4CRCTCh. 9 - Prob. 5CRCTCh. 9 - Net Present Value [LO1] Concerning NPV: a....Ch. 9 - Prob. 7CRCTCh. 9 - Profitability Index [LO7] Concerning the...Ch. 9 - Payback and Internal Rate of Return [LO2, 5] A...Ch. 9 - Prob. 10CRCTCh. 9 - Capital Budgeting Problems [LO1] What difficulties...Ch. 9 - Prob. 12CRCTCh. 9 - Modified Internal Rate of Return [LO6] One of the...Ch. 9 - Net Present Value [LO1] It is sometimes stated...Ch. 9 - Internal Rate of Return [LO5] It is sometimes...Ch. 9 - Calculating Payback [LO2] What is the payback...Ch. 9 - Calculating Payback [LO2] An investment project...Ch. 9 - Calculating Payback [LO2] Siva, Inc., imposes a...Ch. 9 - Calculating Discounted Payback [LO3] An investment...Ch. 9 - Calculating Discounted Payback [LO3] An investment...Ch. 9 - Calculating AAR [LO4] Youre trying to determine...Ch. 9 - Calculating IRR [LO5] A firm evaluates all of its...Ch. 9 - Calculating NPV [LO1] For the cash flows in the...Ch. 9 - Calculating NPV and IRR [LO1, 5] A project that...Ch. 9 - Calculating IRR [LO5] What is the IRR of the...Ch. 9 - Prob. 11QPCh. 9 - NPV versus IRR [LO1, 5] Garage, Inc., has...Ch. 9 - Prob. 13QPCh. 9 - Problems with IRR [LO5] Light Sweet Petroleum,...Ch. 9 - Prob. 15QPCh. 9 - Problems with Profitability Index [LO1, 7] The...Ch. 9 - Comparing Investment Criteria [LO1, 2, 3, 5, 7]...Ch. 9 - NPV and Discount Rates [LO1] An investment has an...Ch. 9 - MIRR [L06] RAK Corp. is evaluating a project with...Ch. 9 - Prob. 20QPCh. 9 - Prob. 21QPCh. 9 - Cash Flow Intuition [LO1, 2] A project has an...Ch. 9 - Payback and NPV [LO1, 2] An investment under...Ch. 9 - Prob. 24QPCh. 9 - NPV Valuation [LO1] The Yurdone Corporation wants...Ch. 9 - Problems with IRR [LO5] A project has the...Ch. 9 - Problems with IRR [LO5] McKeekin Corp. has a...Ch. 9 - Prob. 28QPCh. 9 - Prob. 1MCh. 9 - Prob. 2MCh. 9 - Bullock Gold Mining Seth Bullock, the owner of...
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Essentials Of Investments
Finance
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Mcgraw-hill Education,
Text book image
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:9781260013962
Author:BREALEY
Publisher:RENT MCG
Text book image
Financial Management: Theory & Practice
Finance
ISBN:9781337909730
Author:Brigham
Publisher:Cengage
Text book image
Foundations Of Finance
Finance
ISBN:9780134897264
Author:KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:Pearson,
Text book image
Fundamentals of Financial Management (MindTap Cou...
Finance
ISBN:9781337395250
Author:Eugene F. Brigham, Joel F. Houston
Publisher:Cengage Learning
Text book image
Corporate Finance (The Mcgraw-hill/Irwin Series i...
Finance
ISBN:9780077861759
Author:Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:McGraw-Hill Education