Concept explainers
a)
To determine: The unit cost for 20 units.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
a)
Answer to Problem 9P
Explanation of Solution
Given information:
Formula:
Calculation of unit cost for 20 units:
The time to compute the unit cost for 20 units is to compute the average cost for 20 units. It can be computed by finding labor cost, material cost, overhead cost and total cost. From the total cost, the average cost is computed.
Estimation of labor, material, overheads and total cost:
At 90% learning curve, the unit factor for 20 unit is 14.608 (using learning curve coefficient table)
The time for completing the 20 units is calculated by multiplying 5 with the unit factors 14.608 which yields 73.04 hours.
The labor cost is calculated by multiplying 73.045 hours with 8.50 which yields $620.84.
Material cost is calculated by multiplying 20 units with $20 per unit which yields $400.
The overhead cost calculated by taking 50% of labor, material and setup cost which accounts to $535.42
The total cost is calculated by summing up labor cost, material cost and overhead cost which is adding $50, $620.84, $535.42 and $400.00 which yields $1,606.26.
The average cost per unit is calculated by dividing $1,606.26 with 20 which yields $80.31.
Hence, the unit cost for 20 units is $80.31.
b)
To determine: The minimum production quantity necessary to make the production cost less than the purchase cost.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
b)
Answer to Problem 9P
Explanation of Solution
Given information:
Formula:
Calculation of minimum production quantity necessary to make the production cost less than the purchase cost:
The production cost per unit is $80.31 per unit for 20 units and it is less than the purchase cost which is $88.50 per unit. By trial and error approach the numbers which accounts to less than the purchase cost is computed which are 10 units.
Estimation of labor, material, overheads and total cost:
At 90% learning curve, the unit factor for 10 unit is 7.994 (using learning curve coefficient table)
The time for completing 10 units is calculated by multiplying 5 with the unit factors 7.994 which yields 39.97 hours.
The labor cost is calculated by multiplying 39.97 hours with 8.50 which yields $339.75.
Material cost is calculated by multiplying 10 units with $20 per unit which yields $200.
The overhead cost calculated by taking 50% of labor, material and setup cost which accounts to $294.88
The total cost is calculated by summing up labor cost, material cost and overhead cost which is adding $50, $339.75, $294.88 and $200 which yields $884.63.
The average cost per unit is calculated by dividing $884.63 with 10 which yields $88.46 which is less than $88.50.
Hence, the minimum production quantity necessary to make the production cost less than the purchase cost is $88.46.
Want to see more full solutions like this?
Chapter 7 Solutions
EBK OPERATIONS MANAGEMENT
- The labor cost to produce a certain item is $8.50 per hour. Job setup costs $50 and material costsare $20 per unit. The item can be purchased for $88.50 per unit. The learning rate is 90 percent.Overhead is charged at a rate of 50 percent of labor, materials, and setup costs.a. Determine the unit cost for 20 units, given that the first unit took 5 hours to complete.b. What is the minimum production quantity necessary to make production cost less than purchasecost?arrow_forwardA manager wants to determine an appropriate learning percentage for a certain activity. Times of the first six units are given below: a. Determine the learning percentage using Excel. b. Using your answer from part a, estimate the average time if a total of 30 units are planned.arrow_forwardYou are setting up a new production line for a new type of delivery drones. You observed that the cost for the 10th unit was $6296.33 and the cost for the 80th unit was $4146.15. a) What is the K for the learning curve model of this production line? b) What is the s for the learning curve model of this production line? c) At which unit does its production cost start to be less than $1500?arrow_forward
- 44arrow_forwardIf the time needed to assemble the first five units is approximately 11.2 hours and the learning curve slop is 0.8. Calculate the time needed for producing the first unit?arrow_forwardA) A company working on an 80 percent learning curve has decided that the production standard should be 90 hours the first unit? Show detailed solution i of production for the 128th unit. How much time should be required for B) In a job shop, effective capacity in only 50 percent of design capacity, and actual output is 90 percent of effective of 9 jobs per weeks? Show detailed solution capacity. What design capacity would be needed to achieve an actual output C) You are an engineer who has been assigned a task to perform a HAZOP (Hazard and Operability) study on a Reactor used as main equipment in a certain chemical production plant. i. What are the steps to be followed to perform this study? ii. Use a table to give an example of the parameters, related guide words and deviations that could be used to develop this study.arrow_forward
- The product adx takes 77 hours for production of 1 unit, where learning curve rate is 57% and what will be the total time taken by 2th unit of product S using incremental unit time method ?arrow_forwardYou need to develop a labor time estimate for a customerorder of 20 network installations. It is estimated that the fi rstinstallation will require 60 hours of labor, and a learning curve of90 percent is expected.(a) How many labor-hours are required for the fi ft eenthinstallation?(b) How many labor-hours are required for the twentiethinstallation?(c) How many labor-hours are required to complete all 20installations?(d) If the average labor cost is $32, what is the total labor costfor installing the networks?arrow_forwardProblem 2 The labor cost to produce a certain item is $20 per hour. Material cost is $60 per unit. The overhead cost is charged as 70% of the labor and materials cost. The learning rate is 80%. a. Determine the average cost for 50 units, given that the first unit took 5 hours to complete. b. Assume the item can be purchased from a vendor for $162 per unit. Should we just buy the needed 50 units or produce them. Explain. c. What are your answers for a and b if the needed quantity is 100 units? Show all your workarrow_forward
- A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 38 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool? The time required to install the sixth pool is enter your response herehours. (Enter your response rounded to two decimal places.) Part 2 What is your estimate of the total time for all six pools? The total time for all six pools is enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardOn RainTite Window’s manual assembly line, a newemployee can usually assemble their first window unit in30 minutes. Management assumes a 90 percent learning rate.a. How long should a new employee take to assemble theirsecond window if management is correct in their assump-tion? How long should the 16th window take?b. On RainTite’s semi-automated line, a new employeetakes 45 minutes to assemble their first window; however,the learning rate is 75 percent. At how many windowsproduced will the semi-automated line’s employee takeless time to produce a window than an employee on themanual line?arrow_forwardsubject - operations management In Alcc ltd. The first 18 units takes 17 hours for production with learning curve rate is 74% , calculate how much time it wilm take to produce 272 units using wright model ?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.