Question
Book Icon
Chapter 7, Problem 9P

a)

Summary Introduction

To determine: The standard time for the operation.

Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.

a)

Expert Solution
Check Mark

Answer to Problem 9P

The standard time for the operation is 5.80 minutes.

Explanation of Solution

Given information:

Performance ratingObservations (minutes per cycles)Allowance
1 2 3 4 5
0.9 1.4 1.42 1.39 1.38 1.41 0.10
1.2 2.1 2.05 2 1.85 1.8 0.10
1.11 1.6 1.4 1.5 1.45 1.55 0.10

Formula:

Standardtime=Normaltime×Allowancefactor=NT×AFNT=Observedtime×PerformanceRatingAFjob=1+A

ElementPerformance ratingObservations (minutes per cycles)AllowanceObserved timeNormal timeAfjobStandard time
1 2 3 4 5
A 0.9 1.4 1.42 1.39 1.38 1.4 0.10 1.4 1.26 1.10 1.39
B 1.2 2.1 2.05 2 1.85 1.8 0.10 1.96 2.352 1.10 2.59
C 1.11 1.6 1.4 1.5 1.45 1.6 0.10 1.5 1.665 1.10 1.83
Standard time for operation 5.80

Calculation of standard time of operation:

Excel Worksheet:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 7, Problem 9P , additional homework tip  1

Element A:

Normal time is calculated by multiplying observed timing, 1.4 and performance rating, 0.9 which yields 1.26 minutes.

Allowance factor is calculated by adding 1 with the allowance factor 0.10 to give 1.10.

ST=NT×AFjob=1.26minutes×1.10=1.39minutes

Standard time for element A is calculated by multiplying normal time of 1.26 minutes with allowance factor of 1.10 which gives 1.39 minutes.

Same process applies for element B and C which yields the standard times as 2.59 and 1.83. The standard time for operation is obtained by adding 1.39, 2.59 and 1.83 minutes which gives 5.80 minutes.

Hence, the standard time for the operation is 5.80 minutes.

b)

Summary Introduction

To determine: The number of observations for element A

Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.

b)

Expert Solution
Check Mark

Answer to Problem 9P

The number of observations for element A is 1.

Explanation of Solution

Given information:

Performance ratingObservations (minutes per cycles)Allowance
1 2 3 4 5
0.9 1.4 1.42 1.39 1.38 1.41 0.10
1.2 2.1 2.05 2 1.85 1.8 0.10
1.11 1.6 1.4 1.5 1.45 1.55 0.10

Confidence= 98%

4% of true value

Formula:

n=(zsax¯)2

z=Number ofnormalstandarddeviationsfordesiredconfidences=Samplestandarddeviationx¯=Sample meana=Desired accuracy

Calculation of number of observations for element A:

In the above formula the sample standard deviation is calculated by,

Calculation of standard deviation:

Element A Differences Square of differences Standard deviation
1.4 0 00.015811
1.42 0.02 0.0004
1.39 -0.01 0.0001
1.38 -0.02 0.0004
1.41 0.01 0.0001
Mean=1.4 SSQ=0.001

Excel worksheet:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 7, Problem 9P , additional homework tip  2

Z value for confidence interval of 98% is 2.33.

The confidence interval 0.982 gives 0.49, (z = 2.33).

Using z = 2.33:

n=(2.33×0.01580.04×1.40)2=0.4322

The number of observations from the standard z table for confidence level of 98% is calculated by dividing the product of 2.33 and 0.0158 with product of 0.04 and 1.40 and squaring the resultant which gives 0.4322. Rounding off the value it gives the number of observation as 1.

Hence, the number of observation is 1.

c)

Summary Introduction

To determine: The number of observations for element C.

Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.

c)

Expert Solution
Check Mark

Answer to Problem 9P

The number of observations for element C is 2.

Explanation of Solution

Given information:

Performance ratingObservations (minutes per cycles)Allowance
1 2 3 4 5
0.9 1.4 1.42 1.39 1.38 1.41 0.10
1.2 2.1 2.05 2 1.85 1.8 0.10
1.11 1.6 1.4 1.5 1.45 1.55 0.10

Confidence= 90%

0.10 minute of actual value.

Formula:

n=(zse)2

z=Number ofnormalstandarddeviationsfordesiredconfidences=Samplestandarddeviatione=Maximumacceptableamountoftimeerror

Calculation of number of observations for element C:

In the above formula the sample standard deviation is calculated by,

Calculation of standard deviation:

Element C Differences Square of differences Standard deviation
1.6 0.1 0.010.0791
1.4 -0.1 0.01
1.5 0 0
1.45 -0.05 0.0025
1.55 0.05 0.0025
Mean=1.5 SSQ=0.025

Excel worksheet:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 7, Problem 9P , additional homework tip  3

Z value for confidence interval of 90% is 1.65.

The confidence interval 0.902 gives 0.45, which is in the midway of 0.4495 (z = 1.64) and 0.4505 (z = 1.65).

  • Using z = 1.64:

n=(1.64×0.07910.10)2=1.6828

The number of observations from the standard z table for confidence level of 90 is calculated by dividing the product of 1.64 and 0.0791 with 0.10 and squaring the resultant which gives 1.6828.

  • Using z = 1.65:

n=(1.65×0.07910.10)2=1.7034

The number of observations from the standard z table for confidence level of 90 is calculated by dividing the product of 1.65 and 0.0791 with 0.10 and squaring the resultant which gives 1.7034.

Hence, the number of observations for element C is 2

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Which of the following statements concerning the evaluation of training programs is true?   Most companies thoroughly evaluate the return on investment of their training programs   It is relatively easy to establish a control group and a treatment group for evaluation   Results level of evaluation measures how well participants liked the program   Behavior level criteria measure whether skills learned in training result in behavior changes back on the job
Eligibility testing is   an disparate impact validation method   none of the above   a method to validate promotions and progressive discipline activity   a test an employee administers to ensure that the potential employee is capable and qualified to perform the requirements of the position
A no-strike pledge by a union in a collective bargaining agreement is given in return for management’s agreement to:   a grievance procedure   a union shop   a wage increase   a fringe benefit increase   binding arbitration of grievances

Chapter 7 Solutions

OPERATIONS MANAGEMENT(LL)-W/CONNECT

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning