Chapter 7, Problem 9P

a)

Summary Introduction

To determine: The standard time for the operation.

Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.

a)

Expert Solution
Check Mark

Answer to Problem 9P

The standard time for the operation is 5.80 minutes.

Explanation of Solution

Given information:

Performance ratingObservations (minutes per cycles)Allowance
1 2 3 4 5
0.9 1.4 1.42 1.39 1.38 1.41 0.10
1.2 2.1 2.05 2 1.85 1.8 0.10
1.11 1.6 1.4 1.5 1.45 1.55 0.10

Formula:

Standardtime=Normaltime×Allowancefactor=NT×AFNT=Observedtime×PerformanceRatingAFjob=1+A

ElementPerformance ratingObservations (minutes per cycles)AllowanceObserved timeNormal timeAfjobStandard time
1 2 3 4 5
A 0.9 1.4 1.42 1.39 1.38 1.4 0.10 1.4 1.26 1.10 1.39
B 1.2 2.1 2.05 2 1.85 1.8 0.10 1.96 2.352 1.10 2.59
C 1.11 1.6 1.4 1.5 1.45 1.6 0.10 1.5 1.665 1.10 1.83
Standard time for operation 5.80

Calculation of standard time of operation:

Excel Worksheet:

EBK OPERATIONS MANAGEMENT, Chapter 7, Problem 9P , additional homework tip  1

Element A:

Normal time is calculated by multiplying observed timing, 1.4 and performance rating, 0.9 which yields 1.26 minutes.

Allowance factor is calculated by adding 1 with the allowance factor 0.10 to give 1.10.

ST=NT×AFjob=1.26minutes×1.10=1.39minutes

Standard time for element A is calculated by multiplying normal time of 1.26 minutes with allowance factor of 1.10 which gives 1.39 minutes.

Same process applies for element B and C which yields the standard times as 2.59 and 1.83. The standard time for operation is obtained by adding 1.39, 2.59 and 1.83 minutes which gives 5.80 minutes.

Hence, the standard time for the operation is 5.80 minutes.

b)

Summary Introduction

To determine: The number of observations for element A

Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.

b)

Expert Solution
Check Mark

Answer to Problem 9P

The number of observations for element A is 1.

Explanation of Solution

Given information:

Performance ratingObservations (minutes per cycles)Allowance
1 2 3 4 5
0.9 1.4 1.42 1.39 1.38 1.41 0.10
1.2 2.1 2.05 2 1.85 1.8 0.10
1.11 1.6 1.4 1.5 1.45 1.55 0.10

Confidence= 98%

4% of true value

Formula:

n=(zsax¯)2

z=Number ofnormalstandarddeviationsfordesiredconfidences=Samplestandarddeviationx¯=Sample meana=Desired accuracy

Calculation of number of observations for element A:

In the above formula the sample standard deviation is calculated by,

Calculation of standard deviation:

Element A Differences Square of differences Standard deviation
1.4 0 00.015811
1.42 0.02 0.0004
1.39 -0.01 0.0001
1.38 -0.02 0.0004
1.41 0.01 0.0001
Mean=1.4 SSQ=0.001

Excel worksheet:

EBK OPERATIONS MANAGEMENT, Chapter 7, Problem 9P , additional homework tip  2

Z value for confidence interval of 98% is 2.33.

The confidence interval 0.982 gives 0.49, (z = 2.33).

Using z = 2.33:

n=(2.33×0.01580.04×1.40)2=0.4322

The number of observations from the standard z table for confidence level of 98% is calculated by dividing the product of 2.33 and 0.0158 with product of 0.04 and 1.40 and squaring the resultant which gives 0.4322. Rounding off the value it gives the number of observation as 1.

Hence, the number of observation is 1.

c)

Summary Introduction

To determine: The number of observations for element C.

Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.

c)

Expert Solution
Check Mark

Answer to Problem 9P

The number of observations for element C is 2.

Explanation of Solution

Given information:

Performance ratingObservations (minutes per cycles)Allowance
1 2 3 4 5
0.9 1.4 1.42 1.39 1.38 1.41 0.10
1.2 2.1 2.05 2 1.85 1.8 0.10
1.11 1.6 1.4 1.5 1.45 1.55 0.10

Confidence= 90%

0.10 minute of actual value.

Formula:

n=(zse)2

z=Number ofnormalstandarddeviationsfordesiredconfidences=Samplestandarddeviatione=Maximumacceptableamountoftimeerror

Calculation of number of observations for element C:

In the above formula the sample standard deviation is calculated by,

Calculation of standard deviation:

Element C Differences Square of differences Standard deviation
1.6 0.1 0.010.0791
1.4 -0.1 0.01
1.5 0 0
1.45 -0.05 0.0025
1.55 0.05 0.0025
Mean=1.5 SSQ=0.025

Excel worksheet:

EBK OPERATIONS MANAGEMENT, Chapter 7, Problem 9P , additional homework tip  3

Z value for confidence interval of 90% is 1.65.

The confidence interval 0.902 gives 0.45, which is in the midway of 0.4495 (z = 1.64) and 0.4505 (z = 1.65).

  • Using z = 1.64:

n=(1.64×0.07910.10)2=1.6828

The number of observations from the standard z table for confidence level of 90 is calculated by dividing the product of 1.64 and 0.0791 with 0.10 and squaring the resultant which gives 1.6828.

  • Using z = 1.65:

n=(1.65×0.07910.10)2=1.7034

The number of observations from the standard z table for confidence level of 90 is calculated by dividing the product of 1.65 and 0.0791 with 0.10 and squaring the resultant which gives 1.7034.

Hence, the number of observations for element C is 2

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A Time B- Code Description (hrs) Immediate Predecessor(s) A Find location; determine resource requirements 20 None B Requisition of lumber and sand 65 A C Dig and grade 100 A D Saw lumber into appropriate sizes 30 B E Position lumber in correct locations 25 D, C F Nail lumber together E G Put sand in and under the equipment 25 F H H Put dirt around the equipment 10 F Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 0 20 40 60 80 100 120 140 160 180 200 220 Clear all
List three forms of pay you receive (not dollar amounts).  Compare your list to two of your peers.  Discuss any differences or similarities that you noticed. NO AI
Please and thank you

Chapter 7 Solutions

EBK OPERATIONS MANAGEMENT

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning