(a)
If all the spacing and edge distance requirements are adequate.

Answer to Problem 7.3.1P
The spacing and the edge distance provided are adequate.
Explanation of Solution
Given:
Tension member is
Thickness of the gusset plate is
Diameter of the bolts is
Steel Used is
Calculation:
The properties for
The ultimate tensile stress is
Write the expression for minimum spacing.
Here, diameter of the bolt is
Substitute
The minimum spacing between the bolts is
For the edge distance to be adequate, the value of edge distance should be greater than or equal to the value of minimum edge distance.
Here, edge distance is
The value of edge distance is
Conclusion:
Thus, the spacing and the edge distance provided are adequate.
(b)
The nominal bearing strength of each bolt.

Answer to Problem 7.3.1P
The nominal bearing strength of the edge bolt is
Explanation of Solution
Calculation:
Write the expression for nominal bearing strength of a bolt.
Here, the nominal bearing strength is
With the upper limit of nominal bearing strength of the bolt,
Write the expression to calculate the value of
Here, height of the bolt is
Write the expression to calculate the value of
Here, spacing between the bolts is
Write the expression to calculate the height of the bolt.
Calculate the value of
Substitute
Calculate the value of
Substitute
Calculate the nominal bearing strength for edge bolts.
Substitute
Calculate the upper limit of nominal bearing strength for edge bolts.
Substitute
Thus, the minimum value of
Calculate the value of
Substitute
Calculate the nominal bearing strength for inner bolts.
Substitute
Calculate the upper limit of nominal bearing strength for inner bolts.
Substitute
Thus, the minimum value of
Conclusion:
Thus, the nominal bearing strength of the edge bolt is
Want to see more full solutions like this?
Chapter 7 Solutions
STEEL DESIGN W/ ACCESS
- 6000 units have been installed to date with 9,000 units to install. Labor costs are $23,300.00 to date. What is the unit cost for labor to date?arrow_forwardThe base rate for labor is $15/hr. The labor burden is 35% and 3% for small tools for the labor. There are 1000 units to install. Records indicate that trade workers can install 10 units per hour, per trade worker. The owners need 15% overhead and profit to pay bills, pay interest on loan and provide some profit to the partners. What is the minimum bid assuming no risk avoidance factor?arrow_forwardCan you show me how to obtain these answers thanks, will rate!arrow_forward
- I have the answers for part a just need help with b mostly thanksarrow_forwardPlease explain step by step and show formulasarrow_forward5. (20 Points) Consider a channel width change in the same 7-foot wide rectangular in Problem 4. The horizontal channel narrows as depicted below. The flow rate is 90 cfs, and the energy loss (headloss) through the transition is 0.05 feet. The water depth at the entrance to the transition is initially 4'. 1 b₁ TOTAL ENERGY LINE V² 129 У1 I b₂ TOP VIEW 2 PROFILE VIEW h₁ = 0.05 EGL Y₂ = ? a) b) c) 2 Determine the width, b₂ that will cause a choke at location 2. Determine the water depth at the downstream end of the channel transition (y₂) section if b₂ = 5 feet. Calculate the change in water level after the transition. Plot the specific energy diagram showing all key points. Provide printout in homework. d) What will occur if b₂ = = 1.5 ft.?arrow_forward
- 4. (20 Points) A transition section has been proposed to raise the bed level a height Dz in a 7-foot wide rectangular channel. The design flow rate in the channel is 90 cfs, and the energy loss (headloss) through the transition is 0.05 feet. The water depth at the entrance to the transition section is initially 4 feet. b₁ = b = b2 1 TOTAL ENERGY LINE V² 129 Ут TOP VIEW 2 hloss = 0.05 " EGL Y₂ = ? PROFILE VIEW a) Determine the minimum bed level rise, Dz, which will choke the flow. b) If the step height, Dz = 1 ft, determine the water depth (y2) at the downstream end of the channel transition section. Calculate the amount the water level drops or rises over the step. c) Plot the specific energy diagram showing all key points. Provide printout in Bework. d) What will occur if Dz = 3.0 ft.?. Crest Front Viewarrow_forward1. (20 Points) Determine the critical depth in the trapezoidal drainage ditch shown below. The slope of the ditch is 0.0016, the side slopes are 1V:2.5H, the bottom width is b = 14', and the design discharge is 500 cfs. At this discharge the depth is y = 4.25'. Also, determine the flow regime and calculate the Froude number. Ye= ? Z barrow_forward3. (20 Points) A broad crested weir, 10 feet high, will be constructed in a rectangular channel B feet wide. The weir crest extends a length of B = 120 feet between the banks with 2 - 4 foot wide, round nosed piers in the channel. The width of the weir crest is 8 feet. If H = 6', determine the design discharge for the weir.arrow_forward
- Steel Design (Activate Learning with these NEW ti...Civil EngineeringISBN:9781337094740Author:Segui, William T.Publisher:Cengage LearningArchitectural Drafting and Design (MindTap Course...Civil EngineeringISBN:9781285165738Author:Alan Jefferis, David A. Madsen, David P. MadsenPublisher:Cengage Learning