Question
Chapter 7, Problem 2C
Summary Introduction
Interpretation: By using a network diagram, a table showing the project activities is to be constructed.
Concept Introduction: Networking technique is a method for planning, programming and controlling of work in progress. It is helpful for effective management. It helps the management for decisions. It helps the management for decisions.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
When developing a schedule network diagram, the project manager must take into account the dependencies between activities as well as the start and finish relationships between activities.
List and describe the four types of schedule activity relationships
List and describe the four types of schedule activity dependencies
Include examples of each item above, that do not come from the PMBOK.
The Farmer's American Bank of Leesburg is planning to install a new computerized accounts system.
Bank management has determined the activities required to complete the project, the precedence
relationships of the activities, and activity time estimates, as shown in the following table. Use POM-
QM to analyze this project. According to the result of POM-QM, the expected project completion
time is (type number only, no text)
Activity
a
b
C
d
C
f
8
k
Activity Description
Position recruiting
System development
System training
Equipment training
Manual system test
Preliminary system changeover
Computer-personnel interface
Equipment modification
Equipment testing
System debugging and installation
Equipment changeover
Activity
Predecessor
a
a
b, c
b, c
d, e
d, e
h
f.g
a
5
3
4
5
I
1
3
Time Estimates
(weeks)
1
1
2
5
m
8
12
7
8
I
4
6
2.5
1.
2
8
b
17
15
10
23
1
13
9
7
1
2
11
The table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities.
Activity
Preceding
Activity
Expected
Time (ET)
A
-
7
B
A
9
C
A,B
5
D
C
17
E
C
12
F
C
7
G
D,E,F
10
H
D,G
7
Draw a network diagram for the IS project shown above.,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST).
If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?
Chapter 7 Solutions
Operations Management: Processes and Supply Chains (11th Edition)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7P
Ch. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Consider the following table and answer the following questions. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9. 1. Draw an AOA network diagram representing the project. 2. Prepare a Gantt Chart considering the start date of the project as 1st November. Make necessary assumptions where required. 3. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8 as guide for how to represent each path. 4. What is the critical path for this project and how long is it? 5. What is the shortest possible time needed to complete this project? Activity In itial Node Final Node Estimated Duratlon 1 2 В 3 2 4 D 2 4 E 6 F 4 6. 3 6. 6. 8. 2 I 6. 7 J 7 8 1 K 8arrow_forwardTeams must provide a table diagram (as shown in the sample below) of the projectimplementation plan. i.e., a table which details the major activities involved in settingup the new product operation with their time estimates and predecessor relationships.Note: The implementation plan must include at least ten (10) activities. (Note: SeeChapter 3 of the course text for assistance) Teams must provide a PERT/CPM network diagram (as shown in the sample below)of the project implementation plan. i.e., a diagram which details the major activitiesinvolved in setting up the new product operation with their time estimates andpredecessor relationships. Note: The implementation plan must include at least ten(10) activities. (Note: See Chapter 3 of the course text for assistance)arrow_forwardThe following is the data available for a project: Activity Predecessor Expected Duration (Days) A - 12 B A 9 C B,E 3 D - 10 E D 6 F E 3 G - 2 H G 9 I E,H 2 Expected duration for the completion of the project. Calculate earliest and latest start and finish times for each activity. Draw the network diagram for the project and determine the critical patharrow_forward
- Activities, preceding activities, normal and crashed completion times of each of the activities and crashed costs of activities per week of a project are given in the following table. Activity Preceding Activity Normal Crashed Completion time (week) Crashed Cost Completion Time (week) 7 per week A 7 B $500 C 4 3 $700 $600 A A, C В, D D, E D 7 E F 10 9. $800 9 8 $400 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table. ii. Find the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the drawn diagram of the project and hence the completion time of the project and the critical path.arrow_forwardThe table below represents a IS project set of activities, its expected completion time (weeks) and preceding activities. Activity Expected Time (weeks) Preceding activities A 5 None B 4 None C 10 A D 8 B E 14 B F 6 C, D G 7 D, E, F H 3 F, G Draw a network diagram for the IS project shown above. For each activity, calculate its earliest completion time (TE) and latest completion time (TL). Label TE and TL on the network diagram. Calculate the slack time for each activity.arrow_forwardThe table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities. Activity Preceding Activity Expected Time (ET) A - 7 B A 9 C A,B 5 D C 17 E C 12 F C 7 G D,E,F 10 H D,G 7 Construct a network diagram ,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST). If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?arrow_forward
- project managementarrow_forwardA project consists of eight activities. The activity completion times and the precedence relationships are as follows: Activity Completion Immediate predecessor activities time (weeks) A 50 70 C 60 D 30 A E 40 B,C F 20 G 60 A.D E,F H 50 I G,H Draw the project network diagram using the Activity-On-Node (AON) method for this project and calculate the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and Slack (SL) for each activity.arrow_forward. Given the following network with activity times in weeks, determine the earliest start and finish times, latest start and finish times, and slack for each activity. Indicate the critical path and the project duration. photo attached- Calculate and insert ALL missing Earliest Start or Earliest Finish at each Activity. Calculate and insert ALL missing Latest Start and Latest Finish at each Activity. Calculate missing Slack at Every Activity on the network Diagram. List of all possible paths & Total Slacks from Start to finish for each path. *Which activities are on the critical path? What is the total slack along the critical path.arrow_forward
- For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. I have the node and table filled out I have several questions related to the nodes. What is the project duration? List the activities on the critical path. What is the free float on activity N? What is the total float on activity F? What are the early start and finish dates on activity H? What are the late dates on activity D? What activities have the largest amount of total float? What activities have the most free float and how much?arrow_forwardBased on Table below, discuss how to complete the following project case:a. Create a network model in the form of Activity and Arrow (AoA) and Activity on Node (AoN) for the marketing product project of a company using the CPM method (manual and optimization software)! b. Analyze the critical path and critical duration for the company's project! Activity Description Predecessor Duration (day) A Production Planning — 18 B Market Survey and Market Research — 20 C Production Analysis A 28 D Modeling Product A, B 31 E Sales Brochures A, B 21 F Cost Analysis C, E 33 G Product Experiment D, E 42 H Sales Training B, E 29 I Cost Pricing H 26 J Project Report F, G, I 50arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) A (BCDEFG This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = d) Slack time for each of the activities is: days. B A, D с E, F Activity A B CDEFG Slack Time Time (days) 3 GANGG 5 2 10 4 8arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY