Textbook Question
Chapter 7, Problem 26P
Consider the office renovation project data in Table 7.16. A“zero” time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis.
- Based on the critical path, find the probability of completing the office renovation project by 39 days.
- Find the date by which you would be 90 percent sure of completing the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider the office renovation project data in Table 7.16. A “zero” time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis.a. Based on the critical path, find the probability of completing the office renovation project by 39 days.b. Find the date by which you would be 90 percent sure of completing the project.
The following information has been computed from a project:
Expected total project time = T = 62 weeks
Project variance = 81
1- What is the probability that the project will be completed 18 weeks before its expected
completion date?
2- Draw Normal Curve & Analysis your solution with conclusion
you can solve it on table and i will copy it
Chapter 7 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (11th Edition)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7P
Ch. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Additional Business Textbook Solutions
Find more solutions based on key concepts
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Feeding America Each year, the Feeding America network helps provide food to more than 46 million people facing...
Operations and Supply Chain Management 9th edition
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
What is precedent, and how does it affect common law?
Business in Action
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Please solve my Problem as Soon as possible. Thank You!arrow_forwardConsider the following PERT time estimates: a. Draw a network for this project and determine the critical path based on the most likely times by inspection.b. Assuming that the critical path is the one you identified in part (a), what is the probability that the project will be completed before 28weeks? Before 32 weeks?c. Assuming that the critical path is the one you identified in part (a), how many weeks are required to complete the project with probability .95?arrow_forwardWhy might a probabilistic estimate of a project’s completion time based solely on the variance of the critical path be misleading? Under what circumstances would it be acceptable?arrow_forward
- 29 A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 224 days or more to complete? Select one: a. 0.1587 b. 2.14 c. near zero d. 0.0126 e. 0.8413arrow_forwardDo not use chatgptarrow_forwardPlease helparrow_forward
- A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 169, what is the probability that the project will be completed within 224 days? O 0.50 O 0.84 0.80 O 0.78arrow_forwardWhat is the value of the missing item labeled (a) in the table above? Round to the nearest integer. What is the value of the missing item labeled (b) in table above? Round to two decimals. Draw the network diagram for this project. Clearly label the earliest start, earliest finish, latest start, latest finish and slack for each activity. Specify the critical path and the critical activities. State the expected C.P. duration State the variance of the critical path. What is the probability that the dashboard will be delivered within 20 days?arrow_forwardWhat is the value of the missing item labeled (a) in the table above? Round to the nearest integer. What is the value of the missing item labeled (b) in table above? Round to two decimals. Draw the network diagram for this project. Clearly label the earliest start, earliest finish, latest start, latest finish and slack for each activity. Specify the critical path and the critical activities. State the expected C.P. duration State the variance of the critical path. What is the probability that the dashboard will be delivered within 20 days?arrow_forward
- A company is willing to develop their rocket before the end of current financial year which is now 28 weeks away. The chief engineer of the company has decided to use PERT technique in order to plan, schedule and control program of development for the data given in table below. What is the probability that the program will be completed by the end of the current financial year? (all durations are in weeks). (i) G) Optimum Duration Most likely duration Pesimistic duration 1 2 3 8 13 3 2 8 4 3 8 10 4 7 10 3 6. 3 8 4 9 10 4 8. 4 9. 5 7 9. 12 6. 5 11 7 9. 14 8 4. 00 2.arrow_forwardThe expected duration of a project is 26 weeks and the total project variance along the critical path is 11.555 Calculate the probability of completing the project in 25 weeks. Calculate the Z value which is used for finding the probability of completion of the project from the normal distribution table O a. + 0.0865 O b. + 0.2942 O C. - 0.0865 O d. - 0.2942arrow_forwardConsider the following project activities with a normal unit: (The normal unit is Day) Activity Name Immediate Predecessor (list number/ name, separated by ‘,’) Normal Time A 6 B A 2 C A 4 D B, C 3 E D 1 F D 7 G E 4 H F, G 2 I F 6 J I 1 K H, J 5 Fill the following table: Activity Name Activity Time Earliest Expected Competition Time (TE) Latest Expected Competition Time (TL) Slack (TL-TE) A 6 B 2 C 4 D 3 E 1 F 7 G 4 H 2 I 6 J 1 K 5 Project Completion Time = Days The Critical Path is=arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY