Operations Management
17th Edition
ISBN: 9781259142208
Author: CACHON, Gérard, Terwiesch, Christian
Publisher: Mcgraw-hill Education,
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 7, Problem 1CQ
Summary Introduction
To determine: The setup time of the process.
Expert Solution & Answer
Explanation of Solution
Correct option: (c)
Correct answer:
100 minutes.
Justification:
The amount of agent added to the vat determines the setup time of the process. The reaction time of 85 minutes does not depend on the volume present in the batch and so it will be the setup time. In addition to that, 15 minutes is required to perform the cleaning process and it is also not dependent on the amount added to the vat. Therefore, the total setup time would be:
The total setup time is 100 minutes.
Want to see more full solutions like this?
Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The Flip Chip Company manufactures nacho chips, potato chips, and related products. There has been a problem in the manufacture of nacho chips. The process begins with the mixing of water, corn and lime (called the MASA). A mixer can produce a batch of 300 lbs of MASA in 2 minutes. The MASA is then cooked. This takes 30 minutes. Only 95% of the MASA makes it to the ovens and of that only 75% is transferred to the next step. There are four ovens. The next step is chip making. The MASA is extruded into the chip itself and the chips are baked. There are 2 chip machines. A total of 950 chips/minute are produced (each chip weighs approximately .5oz). The yield from this process is 72%. The chips are then placed in 20 oz bags. This step takes 2 seconds for each bag.
Where is the bottleneck?
What recommendation would you make?
Consider the mixing process shown in the figure. A mixing chamber initially contains 4 liters of a clear liquid. Clear liquid flows into the chamber at a rate of 10 liters per minute. A dye solution having a concentration of 0.25 kilograms per liter is injected into the mixing chamber at a constant rate of liters per minute. When the mixing process is started, the well-stirred mixture is pumped from the chamber at a rate of 10 + r liters per minute.
(a) Develop a mathematical model for the mixing process. Let Q represent the amount of dye in kilograms in the mixture.
(dQ/dt)=?
(b) The objective is to obtain a dye concentration in the outflow mixture of 0.1 kilograms per liter. What injection rate r is required to achieve this equilibrium solution?
r = ?
Would this equilibrium value of r be different if the fluid in the chamber at time t=0 contained some dye? yes, no or maybe?
(c) Assume the mixing chamber contains 4 liters of clear liquid at time t. How many minutes will it take…
Blue Lotus is a bike shop located near a beach resort, which rents its bikes to
guests staying in the resort. When a customer requests to rent a bike and no
bikes are available (they are either with another customers or being cleaned for
rental), customer waits until a bike is available. Once a bike rented out to a
customer, the customer keeps it for an average of 1 day. Upon return, the bike is
cleaned and tuned-up, which takes half a day (0.5 day).
Suppose Blue Lotus has 7 bikes, and demand for bike rental is 4.1 per day. What
is the average amount of time a customer waits to receive a bike?
(Hint: From the perspective of customer waiting time, 0.5 day of cleaning time would
be part of the processing time" so, p = 1+0.5 =1.5 days. Assume CVa = CVp = 1 in
your calculations).
O 1.197 days
O2.134 days
O 0.761 days
O 5.380 days
Chapter 7 Solutions
Operations Management
Ch. 7 - Prob. 1CQCh. 7 - Prob. 2CQCh. 7 - Prob. 3CQCh. 7 - Prob. 4CQCh. 7 - Prob. 5CQCh. 7 - Prob. 6CQCh. 7 - Prob. 7CQCh. 7 - Prob. 8CQCh. 7 - Prob. 9CQCh. 7 - Prob. 10CQ
Ch. 7 - Prob. 11CQCh. 7 - Prob. 12CQCh. 7 - Prob. 13CQCh. 7 - Prob. 14CQCh. 7 - Prob. 1PACh. 7 - Prob. 2PACh. 7 - Prob. 3PACh. 7 - Prob. 4PACh. 7 - Sarahs Organic Soap Company makes four kinds of...Ch. 7 - Prob. 6PACh. 7 - Prob. 7PACh. 7 - Bruno Fruscalzo decided to set up a small...Ch. 7 - Prob. 9PACh. 7 - Prob. 10PACh. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A rigid tank whose volume is 10 L contains 1 kg of water at 0.1 MPa pressure. The tank is now heated until the pressure is 20 MPa. Determine the amount of heat transfer for this process. Neglect kinetic and potential energy changes.arrow_forwardSuppose you work in a textiles factory. You know that it's normal for machines to print an average of 12 flaws per bolt of fabric. But if there's something wrong with the machine, they will print more flaws; you use this fact to determine if a machine needs to be fixed. Fixing a machine is always a time consuming process--it can require two hours just to take the machine apart to inspect it--so you only fix them if you really think there's something wrong. A machine just printed 15 flaws on a bolt of fabric. Using the appropriate distribution function in Excel, determine the chance that this is just a coincidence and the machine is working fine? Express your answer as a decimal to four places. Include a zero before the decimal point.arrow_forwardLet's work together to reunite the cards with their owners North Africa is a country with a population of 100 million citizens and all residing within 20 provinces. It is the government's responsibility to make sure that every citizen of the country has a valid form of identity. The country was using a "Bar- Coded ID Book" as a form of citizen's identification. Two years ago they replaced "Bar-Coded ID Book" by "Smart ID Card". Citizens owning a Bar- Coded ID Book can apply for a Smart ID Card at no cost, new applicants are also issued ID cards at no cost. About 50% of the population holds "Smart ID Cards". Transiting from bar-coded ID book to "Smart ID Card" has been a successful project. However, there is a lot of reported cases everyday where citizens are losing their ID Cards. A Smart ID card is a small card (similar size to a bank card) with a chip that can store information about the citizen, however due to its size and flexibility compared to bar-coded book there is a high…arrow_forward
- Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs have been assigned to each activity using direct tracing and resource drivers as follows: Activity Expected Cost Activity Driver Activity Capacity Engineering $1,000,000 Engineering hours 5,000 hours Setups 900,000 Setups 200 setups Machining 2,000,000 Machine hours 25,000 machine hours Inspection 800,000 Inspection hours 2,500 inspection hours Quasi-Tech produces two models: Model C and Model D. The following table…arrow_forwardProcess Redesign is concerned with increasing the performance of processes without changing the order of activities within the process or fundamentally changing the activities themselves. focuses on eliminating costs works to find ways to eliminate activities within a process. is concerned with improving performance by changing the order of activities or fundamentally changing the activities themselves.arrow_forwardConsider the two stage process depicted below: Stage 1 Stage 2 The first stage of the process requires 6 minutes of work for a single employee to complete. There are 8 employees working at this process stage - each for a total of 5 hours per day. This stage includes an inspection where 14% of WIP is rejected and exits the system after completing Stage 1. The remaining WIP continues to Stage 2 of the process. At this stage, 7 employees work - each for a total of 4 hours per day. WIP is processed at Stage 2 in 10 minutes by a single employee. What is the daily process capacity? Round your answer to the nearest first decimal place. Your Answer: Answerarrow_forward
- There is a 4 percent error rate at a specific point in a production process. If an inspector is placed at this point, all the defects can be detected and eliminated. The inspector would cost $9 per hour and could inspect units in the process at the current production rate of 46 per hour. If no inspector is hired and defects are allowed to pass this point, there is a cost of $10 per defective unit to correct the defects later on. Assume that the line will operate at the same rate (i.e., the current production rate) regardless of whether the inspector is hired or not. a. if the inspector is hired, what will be the inspection cost per unit? b. if an inspector is not hired, what will be the defective cost per unit? c. should an inspector be hired based on costs alone?arrow_forwardA small, privately owned Asian company is producing a private-label soft drink called Yoggo. A bottling line puts the soft drinks into plastic bottles and then packages the bottles into boxes holding 10 bottles each. The bottling line is comprised of the following four steps: (1) the bottling machine takes 1 second to fill a bottle, (2) the lid machine takes 3 seconds to cover the bottle with a lid, (3) a labeling machine takes 3 seconds per bottle, and (4) the packaging machine takes 4 seconds to place a bottle into a box. When a box has been filled with 10 bottles, a worker tending the packaging machine removes the filled box and replaces it with an empty box. Assume that the time for the worker to remove a filled box and replace it with an empty box is negligible and hence does not affect the capacity of the line. Problem data are summarized in the following table. Process Step Number of Machines Seconds per Bottle Bottling 1 1 Apply a lid 1 3 Labeling 1 3 Packaging 1 4…arrow_forwardA small, privately owned Asian company is producing a private-label soft drink called Yoggo. A bottling line puts the soft drinks into plastic bottles and then packages the bottles into boxes holding 10 bottles each. The bottling line is comprised of the following four steps: (1) the bottling machine takes 1 second to fill a bottle, (2) the lid machine takes 3 seconds to cover the bottle with a lid, (3) a labeling machine takes 3 seconds per bottle, and (4) the packaging machine takes 4 seconds to place a bottle into a box. When a box has been filled with 10 bottles, a worker tending the packaging machine removes the filled box and replaces it with an empty box. Assume that the time for the worker to remove a filled box and replace it with an empty box is negligible and hence does not affect the capacity of the line. Problem data are summarized in the following table. Assuming unlimited demand, what would be the flow rate? Assuming unlimited demand, what would be the utilization at…arrow_forward
- . A small, privately owned Asian company is producing a private-label soft drink calledYoggo. A bottling line puts the soft drinks into plastic bottles and then packagesthe bottles into boxes holding 10 bottles each. The bottling line is comprised of thefollowing four steps: (1) the bottling machine takes 1 second to fill a bottle, (2) the lidmachine takes 3 seconds to cover the bottle with a lid, (3) a labeling machine takes3 seconds per bottle, and (4) the packaging machine takes 4 seconds to place a bottleinto a box. When a box has been filled with 10 bottles, a worker tending the packagingmachine removes the filled box and replaces it with an empty box. Assume that thetime for the worker to remove a filled box and replace it with an empty box is negligibleand hence does not affect the capacity of the line. Problem data are summarized in thefollowing table. a. Draw a process flow diagram of this process. b. What is the capacity (bottles/hour) at the resource “Apply a lid”? c. What…arrow_forwardDuring a plant start-up, the operators should go through the start up sequence quickly to reduce the downtime and increase the profitability of the plant. there should be as few operators as possible near the column to ensure that any major accidents will result in lower injuries and fatalities. the operators should fully depend on the automated start up sequence without any intervention to increase the smoothness of the start up. Othere should be as many operators as possible near the column to ensure that any operational emergencies can be safely and quickly managed.arrow_forwardA 10 station automated assembly system produces an ideal cycle time (Tc) of 14 seconds/cycle. When a defective part enters any assembly station it sometimes causes a station jam or stoppage. Defective parts occur at a rate of 0.07 and a jams due to defective parts occur at a rate of 0.4. When a jam occurs, it takes on average 74 seconds to clear and restart the station. Determine the production rate of acceptable parts (Rap) to the nearest 1 part/hour.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.