Loose Leaf for Operations and Supply Chain Management
Loose Leaf for Operations and Supply Chain Management
15th Edition
ISBN: 9781260152562
Author: F. Robert Jacobs
Publisher: McGraw-Hill Education
bartleby

Concept explainers

Question
Book Icon
Chapter 7, Problem 15OQ

a)

Summary Introduction

To draw: A process flow diagram and determine the processing capacity of the whole process.

Process capacity:

Process capacity is the maximum level of output can be possibly obtained through a specific machine of the production line.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Hours     = 8 per day

Days     = 5 per week.

Cost of purchasing parts:

Part A     = 40 cents per piece.

Part B     = 35 cents per piece

Part C     = 15 cents per piece.

Production output:

Assembly line 1         = 140 components per hour.

Operational drill machines     = 3

Drilling Part C         = 50 parts per hour.

Final assembly line         = 160 components per hour.

Cost of production:

Assembly labor             = 30 cents per part.

Drilling labor                 = 15 cents per part.

Cost of electricity             = 1 cent per part.

Total overhead cost             = $1,200 per week,

Depreciation cost for equipment     = $30 per week

Process flow diagram:

Loose Leaf for Operations and Supply Chain Management, Chapter 7, Problem 15OQ , additional homework tip  1

Calculation of capacity:

Assembly line 1=Units per hour×Hours per day×Days per week=140×8×5=5,600 units per week

Drill machines=Number of drill machines×Parts per hour×Hours per day×Days per week=3×50×8×5=6,000 units per week

Final Assembly line=Units per hour×Hours per day×Days per week=160×8×5=6,400 units per week

The overall capacity of the process will be equal to the activity with the lowest individual capacity.

Hence, the capacity of the process is 5,600 units per week.

b)

Summary Introduction

To calculate: The new process capacity and identify the operation that limits the capacity.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Hours             = 16 per day

Days             = 5 per week.

Number of shifts     = 2 per day

Cost of purchasing parts:

Part A     = 40 cents per piece.

Part B     = 35 cents per piece

Part C     = 15 cents per piece.

Production output:

Assembly line 1         = 140 components per hour.

Operational drill machines     = 4

Drilling hours             = 8 per day

Drilling Part C         = 50 parts per hour.

Final assembly line         = 160 components per hour.

Cost of production:

Assembly labor             = 30 cents per part.

Drilling labor                 = 15 cents per part.

Cost of electricity             = 1 cent per part.

Total overhead cost             = $1,200 per week,

Depreciation cost for equipment     = $30 per week

Calculation of capacity:

Assembly line 1=Units per hour×Hours per day×Days per week=140×16×5=11,200 units per week

Drill machines=Number of drill machines×Parts per hour×Hours per day×Days per week=4×50×8×5=8,000 units per week

Final Assembly line=Units per hour×Hours per day×Days per week=160×16×5=12,800 units per week

The overall capacity of the process will be equal to the activity with the lowest individual capacity. The capacity of the process is 8,000 units per week.

The drilling operation only works for 8 hours in a day limiting the overall capacity.

c)

Summary Introduction

To calculate: The new process capacity and identify the operation that limits the capacity.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Hours for assembly line 1    = 16 per day

Hours of Final assembly line     = 12 per day

Days                 = 5 per week.

Number of shifts         = 2 per day

Cost of purchasing parts:

Part A     = 40 cents per piece.

Part B     = 35 cents per piece

Part C     = 15 cents per piece.

Production output:

Assembly line 1         = 140 components per hour.

Operational drill machines     = 5

Drilling hours             = 8 per day

Drilling Part C         = 50 parts per hour.

Final assembly line         = 160 components per hour.

Cost of production:

Assembly labor             = 30 cents per part.

Drilling labor                 = 15 cents per part.

Cost of electricity             = 1 cent per part.

Total overhead cost             = $1,200 per week,

Depreciation cost for equipment     = $30 per week

Calculation of capacity:

Assembly line 1=Units per hour×Hours per day×Days per week=140×16×5=11,200 units per week

Drill machines=Number of drill machines×Parts per hour×Hours per day×Days per week=5×50×8×5=10,000 units per week

Final Assembly line=Units per hour×Hours per day×Days per week=160×12×5=9,600 units per week

The overall capacity of the process will be equal to the activity with the lowest individual capacity. The capacity of the process is 9,600 units per week.

The final assembly line only works for 4 hours in the second shift limiting the overall capacity.

d)

Summary Introduction

To calculate: The cost per unit for the previous two calculated capacities.

d)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Hours for assembly line 1    = 16 per day

Hours of Final assembly line     = 12 per day

Days                 = 5 per week.

Number of shifts         = 2 per day

Cost of purchasing parts:

Part A     = 40 cents per piece.

Part B     = 35 cents per piece

Part C     = 15 cents per piece.

Production output:

Assembly line 1         = 140 components per hour.

Operational drill machines     = 5

Drilling hours             = 8 per day

Drilling Part C         = 50 parts per hour.

Final assembly line         = 160 components per hour.

Cost of production:

Assembly labor             = 30 cents per part.

Drilling labor                 = 15 cents per part.

Cost of electricity             = 1 cent per part.

Total overhead cost             = $1,200 per week,

Depreciation cost for equipment     = $30 per week

Calculation of cost per unit when the capacity is 8,000 and 9,600 units:

Loose Leaf for Operations and Supply Chain Management, Chapter 7, Problem 15OQ , additional homework tip  2

Formula:

Loose Leaf for Operations and Supply Chain Management, Chapter 7, Problem 15OQ , additional homework tip  3

e)

Summary Introduction

To calculate: The break-even number of units.

e)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Product selling price             = $4 per unit.

Fixed cost per drilling machine     = $30,000

Output per week             = 8,000 parts

Number of drilling machines         = 4

Product buying price             = $3 per unit

Calculation of break-even number of units:

Let ‘x’ be the number of units each option will produce.

The cost of buying the unit becomes

Total cost=3x .

When the firm decides to manufacture the part, it incurs a fixed for each of the drilling machines which will be:

Fixed cost for drilling machine=4 machines×30,000 per machine=$120,000

The cost per unit for manufacturing as calculated before is $1.81.

Therefore the total cost of manufacturing the part is:

Total cost=120,000+3x

The total cost of buying and manufacturing is equated to each other to calculate the break-even units as shown below:

3x=120,000+1.81x3x-1.81x=120,000x=120,0001.19=100,840 units

The break-even units are 100,840 units.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
With the aid of examples, fully discuss any five (5) political tactics used in organisations.
a. With the aid of examples, define discrimination. b. Fully discuss any four (4) types of discrimination in the workplace
Read the Following Extract and Answer the Questions that Follows:The word politics has a somewhat negative connotation. It suggests that someone is attempting touse means or to gain ends that are not sanctioned by the organisation. Political behaviour, as we’vedefined it is quite neutral. Similarly, power is not inherently negative. Whether a person viewspower and politics as unsavoury topics depends on several considerations, most important perhapsbeing where the individual stands on a specific issue in each situation. Nonetheless, most managersare reluctant to admit to political character of their own work settings.Discuss any Five (5) Political tactics you know.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.