A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following:

a. Construct the precedence diagram.

b. Assign tasks according to the most following tasks rule. Break ties with the greatest positional weight rule.

c. Assign tasks according to the greatest positional weight rule. Break ties with the most following tasks rule.

d. Compute the balance delay for each rule. Which one yields the better set of assignments in this instance?

Chapter 6, Problem 8P, A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the

a)

Expert Solution
Check Mark
Summary Introduction

To draw: The precedence diagram.

Introduction:

Process selection:

It is the tactical choices made by a firm in picking the kind of production procedure to be followed in the process of production. The process is selected after reviewing many numbers of criteria and constraints.

Answer to Problem 8P

Precedence diagram:

Loose Leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences), Chapter 6, Problem 8P , additional homework tip  1

Explanation of Solution

Given information:

Task Task time (Minutes) Immediate predecessor
a 0.5 Nil
b 1.4 a
c 1.2 a
d 0.7 a
e 0.5 b, c
f 1 d
g 0.4 e
h 0.3 g
i 0.5 f
j 0.8 e, i
k 0.9 h, j
m 0.3 k

Number of minutes per day = 400

Desired output per day = 200 units

Precedence diagram:

Loose Leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences), Chapter 6, Problem 8P , additional homework tip  2

The precedence diagram is drawn circles and arrows. The tasks are represented in circles and weights for each task are represented outside the circle. The arrows are represented to show which task is preceding the other task and so on.

b)

Expert Solution
Check Mark
Summary Introduction

To assign: Tasks on the basis of most following tasks.

Introduction:

Process selection:

It is the tactical choices made by a firm in picking the kind of production procedure to be followed in the process of production. The process is selected after reviewing many numbers of criteria and constraints.

Explanation of Solution

Given information:

Task Task time (Minutes) Immediate predecessor
a 0.5 Nil
b 1.4 a
c 1.2 a
d 0.7 a
e 0.5 b, c
f 1 d
g 0.4 e
h 0.3 g
i 0.5 f
j 0.8 e, i
k 0.9 h, j
m 0.3 k

Number of minutes per day = 400

Desired output per day = 200 units

Calculation of cycle time:

The cycle time is calculated by dividing the operating time per day by the desired output per day.

Cycle time=400200=2 minutes / unit

The number of following tasks, calculation of positional weight for each task is shown below.

Task Following tasks Number of following tasks Calculation of positional weight Positional weight
a b, c, d, e, f, g, h, i, j, k, m 11 0.5 + 1.4 + 1.2 + 0.7 + 0.5 + 1 + 0.4 + 0.3 + 0.5 + 0.8 + 0.9 + 0.3 8.5
b e, g, h, j, k, m 6 1.4 + 0.5 + 0.4 + 0.3 + 0.8 + 0.9 + 0.3 4.6
c e, g, h, j, k, m 6 1.2 + 0.5 + 0.4 + 0.3 + 0.8 + 0.9 + 0.3 4.4
d f, i, j, k, m 5 0.7 + 1 + 0.5 + 0.8 + 0.9 + 0.3 4.2
e g, h, j, k, m 5 0.5 + 0.4 + 0.3 + 0.8+ 0.9 + 0.3 3.2
f i, j, k, m 4 1 + 0.5 + 0.8 + 0.9 + 0.3 3.5
g h, k, m 3 0.4 + 0.3 + 0.9 + 0.3 1.9
h  k, m 2 0.3 + 0.9 + 0.3 1.5
i j, k, m 3 0.5 + 0.8 0.9 + 0.3 2.5
j  k, m 2 0.8 + 0.9 + 0.3 2
k m 1 0.9 + 0.3 1.2
m Nil 0 0.3 0.3

Assigning tasks to workstations:

Workstation number Eligible task Assigned task Task time Unassigned cycle time Reason
2
1 a a 0.5 1.5 Task 'a' is the only eligible task available
b, c, d b 1.4 0.1 Task 'b' has the highest positional weight
c, d None 0.1 (Idle time) The task time is greater than the unassigned cycle time.
2
2 c, d c 1.2 0.8 Task 'c' has more following tasks
d, e d 0.7 0.1 Task 'd' has the highest positional weight
e, f None 0.1 (Idle time) The task time is greater than the unassigned cycle time.
2
3 e, f e 0.5 1.5 Task 'e' has more following tasks
f, g f 1 0.5 Task 'f' has more following tasks
g, i i 0.5 0 Task 'i' has the highest positional weight
2
4 g, j g 0.4 1.6 Task 'g' has more following tasks
h, j j 0.8 0.8 Task 'j' has the highest positional weight
h h 0.3 0.5 Task 'h' is the only eligible task available
k None 0.5 (Idle time) The task time is greater than the unassigned cycle time.
2
5 k k 0.9 1.1 Task 'k' is the only eligible task available
m m 0.3 0.8 Task 'm' is the only task remaining
0.8 (Idle time) All tasks completed

Overview of tasks assignment:

Workstation Assigned tasks Total cycle time used Idle time
1 a, b 1.9 0.1
2 c, d 1.9 0.1
3 e, f, i 2 0
4 g, j, h 1.5 0.5
5 k, m 1.2 0.8

c)

Expert Solution
Check Mark
Summary Introduction

To assign: Tasks on the basis of greatest positional weight.

Introduction:

Process selection:

It is the tactical choices made by a firm in picking the kind of production procedure to be followed in the process of production. The process is selected after reviewing many numbers of criteria and constraints.

Explanation of Solution

Given information:

Task Task time (Minutes) Immediate predecessor
a 0.5 Nil
b 1.4 a
c 1.2 a
d 0.7 a
e 0.5 b, c
f 1 d
g 0.4 e
h 0.3 g
i 0.5 f
j 0.8 e, i
k 0.9 h, j
m 0.3 k

Number of minutes per day = 400

Desired output per day = 200 units

Calculation of cycle time:

The cycle time is calculated by dividing the operating time per day by the desired output per day.

Cycle time=400200=2 minutes / unit

The number of following tasks, calculation of positional weight for each task is shown below.

Task Following tasks Number of following tasks Calculation of positional weight Positional weight
a b, c, d, e, f, g, h, i, j, k, m 11 0.5 + 1.4 + 1.2 + 0.7 + 0.5 + 1 + 0.4 + 0.3 + 0.5 + 0.8 + 0.9 + 0.3 8.5
b e, g, h, j, k, m 6 1.4 + 0.5 + 0.4 + 0.3 + 0.8 + 0.9 + 0.3 4.6
c e, g, h, j, k, m 6 1.2 + 0.5 + 0.4 + 0.3 + 0.8 + 0.9 + 0.3 4.4
d f, i, j, k, m 5 0.7 + 1 + 0.5 + 0.8 + 0.9 + 0.3 4.2
e g, h, j, k, m 5 0.5 + 0.4 + 0.3 + 0.8+ 0.9 + 0.3 3.2
f i, j, k, m 4 1 + 0.5 + 0.8 + 0.9 + 0.3 3.5
g h, k, m 3 0.4 + 0.3 + 0.9 + 0.3 1.9
h  k, m 2 0.3 + 0.9 + 0.3 1.5
i j, k, m 3 0.5 + 0.8 0.9 + 0.3 2.5
j  k, m 2 0.8 + 0.9 + 0.3 2
k m 1 0.9 + 0.3 1.2
m Nil 0 0.3 0.3

Assigning tasks to workstations:

Workstation number Eligible task Assigned task Task time Unassigned cycle time Reason
2
1 a a 0.5 1.5 Task 'a' is the only eligible task available
b, c, d b 1.4 0.1 Task 'b' has the highest positional weight
c, d None 0.1 (Idle time) The task time is greater than the unassigned cycle time.
2
2 c, d c 1.2 0.8 Task 'c' has the highest positional weight
d, e d 0.7 0.1 Task 'd' has the highest positional weight
e, f None 0.1 (Idle time) The task time is greater than the unassigned cycle time.
2
3 e, f f 1 1 Task 'f' has the highest positional weight
e, i e 0.5 0.5 Task 'e' has the highest positional weight
g, i i 0.5 0 Task 'g' has the highest positional weight
2
4 g, j j 0.8 1.2 Task 'j' has the highest positional weight
g g 0.4 0.8 Task 'g' is the only eligible task available
h h 0.3 0.5 Task 'h' is the only eligible task available
k None 0.5 (Idle time) The task time is greater than the unassigned cycle time.
2
5 k k 0.9 1.1 Task 'k' is the only eligible task available
m m 0.3 0.8 Task 'm' is the only task remaining
0.8 (Idle time) All tasks completed

Overview of tasks assignment:

Workstation Assigned tasks Total cycle time used Idle time
1 a, b 1.9 0.1
2 c, d 1.9 0.1
3 f, e, i 2 0
4 j, g, h 1.5 0.5
5 k, m 1.2 0.8

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The balance delay.

Introduction:

Process selection:

It is the tactical choices made by a firm in picking the kind of production procedure to be followed in the process of production. The process is selected after reviewing many numbers of criteria and constraints.

Answer to Problem 8P

The balance delay for most following tasks and greatest positional weight rule is 15%.

Explanation of Solution

The balance delay is also known as the percentage of idle time.

Formula to calculate percentage of idle time:

Idle time=Total idle timeNumber of workstations×Cycle time×100

Calculation of percentage of idle time:

Most following tasks:

Idle time=0.1+0.1+0+0.5+0.85×2×100=1.510×100=0.15×100=15%

The percentage of idle time is 15%.

Greatest positional weight:

Idle time=0.1+0.1+0+0.5+0.85×2×100=1.510×100=0.15×100=15%

The percentage of idle time is 15%.

The balance delay for most following tasks and greatest positional weight rule is 15%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
“Implementing a Performance Management Communication Plan at Accounting, Inc.” Evaluate Accounting Inc.’s communication plan.  Specifically, does it answer all of the questions that a good communication plan should answer? Which questions are left unanswered?  How would you provide answers to the unanswered questions? “Implementing an Appeals Process at Accounting, Inc.”   If you were to design an appeals process to handle these complaints well, what would be the appeal process?  Describe the recommended process and why.
The annual demand for water bottles at Mega Stores is 500 units, with an ordering cost of Rs. 200 per order. If the annual inventory holding cost is estimated to be 20%. of unit cost, how frequently should he replenish his stocks? Further, suppose the supplier offers him a discount on bulk ordering as given below. Can the manager reduce his costs by taking advantage of either of these discounts? Recommend the best ordering policy for the store. Order size Unit cost (Rs.) 1 – 49 pcs. 20.00 50 – 149 pcs. 19.50 150 – 299 pcs. 19.00 300 pcs. or more 18.00
Help answer showing level work and formulas

Chapter 6 Solutions

Loose Leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)

Ch. 6.5 - Prob. 1.1RQCh. 6.5 - Prob. 1.2RQCh. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY