Twelve tasks, with times and precedence requirements as shown in the following table, are 10 be assigned to workstations using a cycle time of 1.5 minutes. Two heuristic rules will be tried: (1) greatest positional weight, and (2) most following tasks. In each case, the tiebreaker will be shortest processing time.

Chapter 6, Problem 6P, Twelve tasks, with times and precedence requirements as shown in the following table, are 10 be

a. Draw the precedence diagram for this line.

b. Assign tasks to stations under each of the two rules.

c. Compute the percentage of idle tune fox each rule.

a)

Expert Solution
Check Mark
Summary Introduction

To draw: The precedence diagram.

Answer to Problem 6P

Precedence diagram:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 6, Problem 6P , additional homework tip  1

Explanation of Solution

Given information:

Task Duration (minutes) Immediate (Predecessor)
a 0.1 Nil
b 0.2 a
c 0.9 b
d 0.6 c
e 0.1 Nil
f 0.2 d, e
g 0.4 f
h 0.1 g
i 0.2 h
j 0.7 i
k 0.3 j
l 0.2 k

Cycle time = 1.5 minutes

Precedence diagram:

OPERATIONS MANAGEMENT(LL)-W/CONNECT, Chapter 6, Problem 6P , additional homework tip  2

The precedence diagram is drawn circles and arrows. The tasks are represented in circles and weights for each task are represented outside the circle. The arrows are represented to show which task is preceding the other task and so on.

b)

1)

Expert Solution
Check Mark
Summary Introduction

To assign: Tasks on the basis of greatest positional weight.

Explanation of Solution

Given information:

Task Duration (minutes) Immediate (Predecessor)
a 0.1 Nil
b 0.2 a
c 0.9 b
d 0.6 c
e 0.1 Nil
f 0.2 d, e
g 0.4 f
h 0.1 g
i 0.2 h
j 0.7 i
k 0.3 j
l 0.2 k

Cycle time = 1.5 minutes

The number of following tasks, calculation of positional weight, processing time for each task is shown below.

Task Following tasks Number of following tasks Calculation of positional weight Positional weight Processing time
a b, c, d, f, g, h, i, j, k, l 10 0.1 + 0.2 + 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.9 0.1
b c, d, f, g, h, i, j, k, l 9 0.2 + 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.8 0.2
c d, f, g, h, i, j, k, l 8 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.6 0.9
d f, g, h, i, j, k, l 7 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.7 0.6
e f, g, h, i, j, k, l 7 0.1 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.2 0.1
f g, h, i, j, k, l 6 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.1 0.2
g h, i, j, k, l 5 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 1.9 0.4
h i, j, k, l 4 0.1 + 0.2 + 0.7+ 0.3 + 0.2 1.5 0.1
i j, k, l 3 0.2 + 0.7+ 0.3 + 0.2 1.4 0.2
j k, l 2 0.7+ 0.3 + 0.2 1.2 0.7
k l 1 0.3 + 0.2 0.5 0.3
l Nil 0 0.2 0.2 0.2

Assigning tasks to workstations:

Workstation number Eligible task Assigned task Task time Unassigned cycle time Reason
1.5
1 a, e a 0.1 1.4 Task 'a' has highest positional weight
b, e b 0.2 1.2 Task 'b' has highest positional weight
c, e c 0.9 0.3 Task 'c' has highest positional weight
d, e e 0.1 0.2 Task 'e' is the only eligible task available
d None 0.2 (Idle time) The task time is greater than the unassigned cycle time.
1.5
2 d d 0.6 0.9 Task 'd' is the only eligible task available
f f 0.2 0.7 Task 'f' is the only eligible task available
g g 0.4 0.3 Task 'g' is the only eligible task available
h h 0.1 0.2 Task 'h' is the only eligible task available
i i 0.2 0 Task 'i' is the only eligible task available
1.5
3 j j 0.7 0.8 Task 'j' is the only eligible task available
k k 0.3 0.5 Task 'k' is the only eligible task available
l l 0.2 0.3 Task 'l' is the only eligible task available
0.3 (Idle time) All tasks completed

Overview of tasks assignment:

Workstation Assigned tasks Total cycle time used Idle time
1 a, b, c, e 1.3 0.2
2 d, f, g, h, i 1.5 0
3 j, k, l 1.2 0.3

2)

Expert Solution
Check Mark
Summary Introduction

To assign: Tasks on the basis of most following tasks.

Explanation of Solution

Given information:

Task Duration (minutes) Immediate (Predecessor)
a 0.1 Nil
b 0.2 a
c 0.9 b
d 0.6 c
e 0.1 Nil
f 0.2 d, e
g 0.4 f
h 0.1 g
i 0.2 h
j 0.7 i
k 0.3 j
l 0.2 k

Cycle time = 1.5 minutes

The number of following tasks, calculation of positional weight, processing time for each task is shown below.

Task Following tasks Number of following tasks Calculation of positional weight Positional weight Processing time
a b, c, d, f, g, h, i, j, k, l 10 0.1 + 0.2 + 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.9 0.1
b c, d, f, g, h, i, j, k, l 9 0.2 + 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.8 0.2
c d, f, g, h, i, j, k, l 8 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.6 0.9
d f, g, h, i, j, k, l 7 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.7 0.6
e f, g, h, i, j, k, l 7 0.1 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.2 0.1
f g, h, i, j, k, l 6 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.1 0.2
g h, i, j, k, l 5 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 1.9 0.4
h i, j, k, l 4 0.1 + 0.2 + 0.7+ 0.3 + 0.2 1.5 0.1
i j, k, l 3 0.2 + 0.7+ 0.3 + 0.2 1.4 0.2
j k, l 2 0.7+ 0.3 + 0.2 1.2 0.7
k l 1 0.3 + 0.2 0.5 0.3
l Nil 0 0.2 0.2 0.2

Assigning tasks to workstations:

Workstation number Eligible task Assigned task Task time Unassigned cycle time Reason
1.5
1 a, e a 0.1 1.4 Task 'a' has the most following tasks
b, e b 0.2 1.2 Task 'b' has the most following tasks
c, e c 0.9 0.3 Task 'c' has the most following tasks
d, e e 0.1 0.2 Task 'e' is the only eligible task available
d None 0.2 (Idle time) The task time is greater than the unassigned cycle time.
1.5
2 d d 0.6 0.9 Task 'd' is the only eligible task available
f f 0.2 0.7 Task 'f' is the only eligible task available
g g 0.4 0.3 Task 'g' is the only eligible task available
h h 0.1 0.2 Task 'h' is the only eligible task available
i i 0.2 0 Task 'i' is the only eligible task available
1.5
3 j j 0.7 0.8 Task 'j' is the only eligible task available
k k 0.3 0.5 Task 'k' is the only eligible task available
l l 0.2 0.3 Task 'l' is the only eligible task available
0.3 (Idle time) All tasks completed

Overview of tasks assignment:

Workstation Assigned tasks Total cycle time used Idle time
1 a, b, c, e 1.3 0.2
2 d, f, g, h, i 1.5 0
3 j, k, l 1.2 0.3

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The percentage of idle time.

Answer to Problem 6P

The percentage of idle time is 11.11%.

Explanation of Solution

Formula to calculate percentage of idle time:

Idle time=Total idle timeNumber of workstations×Cycle time×100

Calculation of percentage of idle time:

The solutions for most following tasks rule and highest positional weight is same. Hence, the percentage of idle time will also be the same.

Idle time=0.2+0.0+0.33×1.5×100=0.54.5×100=0.1111×100=11.11%

The percentage of idle time is 11.11%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
“Implementing a Performance Management Communication Plan at Accounting, Inc.” Evaluate Accounting Inc.’s communication plan.  Specifically, does it answer all of the questions that a good communication plan should answer? Which questions are left unanswered?  How would you provide answers to the unanswered questions? “Implementing an Appeals Process at Accounting, Inc.”   If you were to design an appeals process to handle these complaints well, what would be the appeal process?  Describe the recommended process and why.
The annual demand for water bottles at Mega Stores is 500 units, with an ordering cost of Rs. 200 per order. If the annual inventory holding cost is estimated to be 20%. of unit cost, how frequently should he replenish his stocks? Further, suppose the supplier offers him a discount on bulk ordering as given below. Can the manager reduce his costs by taking advantage of either of these discounts? Recommend the best ordering policy for the store. Order size Unit cost (Rs.) 1 – 49 pcs. 20.00 50 – 149 pcs. 19.50 150 – 299 pcs. 19.00 300 pcs. or more 18.00
Help answer showing level work and formulas

Chapter 6 Solutions

OPERATIONS MANAGEMENT(LL)-W/CONNECT

Ch. 6.5 - Prob. 1.1RQCh. 6.5 - Prob. 1.2RQCh. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY