a)

Summary Introduction

To determine: The estimate of the learning rate.

Introduction: It is the rate to measure the performance of the person in the new skills and in gaining experiences.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Loose Leaf for Operations and Supply Chain Management, Chapter 6, Problem 6OQ , additional homework tip  1

Estimate the learning rate for Unit 1 to Unit 2:

It is calculated by dividing the time taken to complete the second unit and first unit.

Learning percentage=Time taken to complete second unitTime taken to complete first unit=1012=83.33%

Hence, the learning percentage is 83.33%.

Estimate the learning rate for Unit 2 to Unit 4:

It is calculated by dividing the time taken to complete the fourth unit and second unit.

Learning percentage=Time taken to complete fourth unitTime taken to complete second unit=6.510=65%

Hence, the learning percentage is 65%.

Estimate the learning rate for Unit 4 to Unit 8:

It is calculated by dividing the time taken to complete the eighth unit and fourth unit.

Learning percentage=Time taken to complete eighth unitTime taken to complete fourth unit=3.66.5=55.38%

Hence, the learning percentage is 55.38%.

Estimate the learning rate for Unit 8 to Unit 16:

It is calculated by dividing the time taken to complete the eighth unit and fourth unit.

Learning percentage=Time taken to complete sixteenth unitTime taken to complete eighth unit=2.73.6=75%

Hence, the learning percentage is 75%.

Determine the average learning rate:

Average learning rate=83.33%+65%+55.38%+75%4=278.714=69.68%70%

Hence, the average learning rate is 70%.

b)

Summary Introduction

To determine: The bid that Company L should submit for the total order of 100 units.

Introduction: It is the rate to measure the performance of the person in the new skills and in gaining experiences.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Loose Leaf for Operations and Supply Chain Management, Chapter 6, Problem 6OQ , additional homework tip  2

Determine the average learning rate:

Average learning rate=83.33%+65%+55.38%+75%4=278.714=69.68%70%

Hence, the average learning rate is 70%.

Determine the bid that Company L should submit for the total order of 100 units:

It is computed by subtracting the cumulative value for 20 units from cumulative value for 120 units and multiplying it with the cost to produce the first unit.

Cost to produce100 more units}=(Cumulative value for 120 unitsCumulative value for 20 units)×(Cost to producefirst unit)=(19.5707.407)×$12 million=12.163×$12 million=$145,956,000

The cumulative values can be determined using the table of cumulative values. For example, 19.570 is the cumulative value for 120 units and 70% learning rate.

Hence, the bid that Company L should submit for the total order of 100 units is $145,956,000.

c)

Summary Introduction

To determine: The expected cost for the last unit under the learning rate.

Introduction: It is the rate to measure the performance of the person in the new skills and in gaining experiences.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Loose Leaf for Operations and Supply Chain Management, Chapter 6, Problem 6OQ , additional homework tip  3

Determine the average learning rate:

Average learning rate=83.33%+65%+55.38%+75%4=278.714=69.68%70%

Hence, the average learning rate is 70%.

Determine the expected cost for the last unit under the learning rate:

It is computed by multiplying the cumulative value for 120 units with the cost to produce one unit.

Cost to produce120th unit}=Cumulative value for 120 units×(Cost to producefirst unit)=0.0851×$12 million=$1,021,200

The cumulative values can be determined using the table of cumulative values. For example, .0062 is the cumulative value for 120 units and 70% learning rate.

Hence, the expected cost to produce 120th units is $1,021,200.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
What is the best way to manage emotions and thoughts? How to work through Emotions and thoughts?
What are the emotions or stressful thoughts? What are the differences between them? How can we work through the emotions or stressful thoughts? How can we avoid or prevent emotions or stressful thoughts from happening or occurring? What are the obstacles?
Main Challenges at TechInnovateStrategic DirectionTechInnovate's board of directors is pushing for a more aggressive expansion into emerging markets, particularly in Africaand Southeast Asia. However, there's internal disagreement about whether to focus on these new markets or consolidatetheir position in existing ones. Sarah Chen favors rapid expansion, while some senior executives advocate for a morecautious approach.Ethical ConcernsThe company's AI algorithms have come under scrutiny for potential biases, particularly in facial recognition technology.There are concerns that these biases disproportionately affect minority groups. Some employees have voiced ethicalconcerns about selling this technology to law enforcement agencies without addressing these issues.Team Leadership and DiversityTechInnovate's leadership team is predominantly male and Western, despite its global presence. There's growing pressurefrom employees and some board members to diversify the leadership team to…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.