Question
Book Icon
Chapter 6, Problem 10OQ

a)

Summary Introduction

To determine: The last unit cost to build.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

It is given that first unit took 4,000 hours to complete and the cost for materials and equipment usage is $30,000. Second unit took 3,200 hours to complete and the cost for materials and equipment usage is $21,000. Labor cost is given as $18 per hour.

Determine the last unit (22nd unit) cost to build:

Labor learning rate=3,2004,000=80%

Material learning rate=21,00030,000=70%

Labor cost for 22nd unit=4,000×0.3697×$18=$26,618.40

Machine cost for 22nd unit=30,000×0.2038=$6,114.00

Total amount for 22nd unit=$26,618.40+$6,114.00=$32,732.40

Hence, the last unit cost is $32,732.40.

b)

Summary Introduction

To determine: The average time for the 20 missile guidance controls.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

It is given that first unit took 4,000 hours to complete and the cost for materials and equipment usage is $30,000. Second unit took 3,200 hours to complete and the cost for materials and equipment usage is $21,000. Labor cost is given as $18 per hour.

Determine the average time for the 20 missile guidance controls:

Labor cost for20 more units}=(Cumulative value for 22 unitsCumulative value for 2 units)×(Time to producefirst unit)=(11.2301.800)×4,000=37,720

Average labor time=Labor time for 20 more units20=37,72020=1,886 hours

c)

Summary Introduction

To determine: The average cost for guidance control for the 20 in the contract.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

It is given that first unit took 4,000 hours to complete and the cost for materials and equipment usage is $30,000. Second unit took 3,200 hours to complete and the cost for materials and equipment usage is $21,000. Labor cost is given as $18 per hour.

Determine average cost for guidance control for the 20 in the contract:

Labor cost for20 more units}=(Cumulative value for 22 unitsCumulative value for 2 units)×(Time to producefirst unit)=(11.2301.800)×4,000=37,720

Average labor cost=Labor time for 20 more units20×$18=37,72020×$18=$33,948

Material cost for20 more units}=(Cumulative value for 22 unitsCumulative value for 2 units)×(Material cost forfirst unit)=(7.8191.700)×$30,000=$183,570

Average cost=Material cost for 20 more units20=$183,57020=$9,178.50

Determine the average total cost:

Average total cost=Average labor cost+Average material cost=$33,948+$9,178.50=$43,126.50

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
View the video Noodles & Company (8.28minutes, Ctrl + Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 7 & 7S – service process design, type of job design, methods analysis, work methods, job design, learning curve effect, etc.) after watching this video. https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=E5i8OKgpqhwywhgFmpp1bmM Note: As a rough guideline, please try to keep the written submission to one or two paragraphs.    2) Leland, the job analyst at Zevo Toys, wanted to perform a time study on the assembling of toys. He observed one of the workers, Magorium, for five hours. During that time, Magorium assembled 250 toys. Leland rated Magorium as performing at 110 percent. The allowance for rest, personal time, etc. at Zevo Toys is 12 percent.   a) Compute the normal time for the job. b) Compute the standard time for the job.   Note: You could work out the problem by hand or use excel; in chapter 7,…
1) Noodles & Company   View the video Noodles & Company (8.28minutes, Ctrl + Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 7 & 7S – service process design, type of job design, methods analysis, work methods, job design, learning curve effect, etc.) after watching this video. https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=E5i8OKgpqhwywhgFmpp1bmM Note: As a rough guideline, please try to keep the written submission to one or two paragraphs.    2) Leland, the job analyst at Zevo Toys, wanted to perform a time study on the assembling of toys. He observed one of the workers, Magorium, for five hours. During that time, Magorium assembled 250 toys. Leland rated Magorium as performing at 110 percent. The allowance for rest, personal time, etc. at Zevo Toys is 12 percent.   a) Compute the normal time for the job. b) Compute the standard time for the job.   Note: You could work out the problem by hand or use…
An investigation of career development opportunities and job satisfaction at
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.