Long-term contract; revenue recognition over time vs. upon project completion
• LO5–9
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture of the down payment. Occasionally, homes remain unsold for as long as three months after construction. In these situations, sales price reductions are used to promote the sale.
During 2018, Citation began construction of an office building for Altamont Corporation. The total contract price is $20 million. Costs incurred, estimated costs to complete at year-end, billings, and cash collections for the life of the contract are as follows:
Also during 2018, Citation began a development consisting of 12 identical homes. Citation estimated that each home will sell for $600,000, but individual sales prices are negotiated with buyers. Deposits were received for eight of the homes, three of which were completed during 2018 and paid for in full for $600,000 each by the buyers. The completed homes cost $450,000 each to construct. The construction costs incurred during 2018 for the nine uncompleted homes totaled $2,700,000.
Required:
1. Briefly explain the difference between recognizing revenue over time and upon project completion when accounting for long-term construction contracts.
2. Answer the following questions assuming that Citation concludes it does not qualify for revenue recognition over time for its office building contracts:
a. How much revenue related to this contract will Citation report in its 2018 and 2019 income statements?
b. What is the amount of gross profit or loss to be recognized for the Altamont contract during 2018 and 2019?
c. What will Citation report in its December 31, 2018,
3. Answer requirements 2a through 2c assuming that Citation recognizes revenue over time according to percentage of completion for its office building contracts.
4. Assume the same information for 2018 and 2019, but that as of year-end 2019 the estimated cost to complete the office building is $9,000,000. Citation recognizes revenue over time according to percentage of completion for its office building contracts.
a. How much revenue related to this contract will Citation report in the 2019 income statement?
b. What is the amount of gross profit or loss to be recognized for the Altamont contract during 2019?
c. What will Citation report in its 2019 balance sheet related to this contract? (Ignore cash.)
5. When should Citation recognize revenue for the sale of its single-family homes?
6. What will Citation report in its 2018 income statement and 2018 balance sheet related to the single-family home business (ignore cash in the balance sheet)?
Want to see the full answer?
Check out a sample textbook solutionChapter 6 Solutions
INTERMEDIATE ACCOUNTING ACCESS 540 DAY
- Discussion Question 21 at the end of Chapter 18 after Key Terms The Hawk Corporation builds yachts. The vessels it currently produces are practically identical and are completed in approximately 8 months. A customer has approached Hawk about constructing a larger yacht that would take approximately 15 months to complete. What are the tax implications of accepting the contract proposal? To fully answer this question, please address the following in your post. What is the definition of a long - term contract? Which long term contract method is required to be used by tax regulations? What is the process used to compute income using the required method?arrow_forwardProblem 6-12 (Algo) Long-term contract; revenue recognized over time vs. upon project completion; loss projected on entire project [LO6-9] Curtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod Associates on July 1, 2024, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,120,000. The building was completed on December 31, 2026. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date Required: At 12-31-2024 At 12-31-2025 At 12-31-2026 10% 60% 100% $ 361,000 3,249,000 722,000 $ 2,604,000 1,736,000 2,210,000 $ 4,392,000 0 4,120,000 1. Compute gross profit or…arrow_forwardA-1arrow_forward
- sharadarrow_forwardDinesh Bhaiarrow_forwardExercise 6-24 (Algo) Long-term contract; revenue recognition over time; solve for unknowns [LO6-9] In 2021, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,200,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2021, is as follows: Balance Sheet Accounts receivable (from construction progress billings) Construction in progress. Less: Billings on construction contract Cost and profit of uncompleted contracts in excess of billings Income Statement Income (before tax) on the contract recognized in 2021 Required: 1. What was the cost of construction actually incurred in 2021? $ 160,000 (152,000) 1. Actual costs incurred in 2021 2. Cash collections in 2021 3. Estimated cost to complete 4. Estimated percentage $26,000 $36,000 8,000 2. How much cash was collected in 2021 on this contract? 3. What…arrow_forward
- 5 4 On January 1, 2024, Nath-Langstrom Services, Incorporated, a computer software training firm, leased several computers under a two-year operating lease agreement from ComputerWorld Leasing, which routinely finances equipment for other firms at an annual interest rate of 4%. • The contract calls for four rent payments of $10,500 each, payable semiannually on June 30 and December 31 each year. ⚫ The computers were acquired by ComputerWorld at a cost of $91,000 and were expected to have a useful life of five years with no residual value. ⚫ Both firms record amortization and depreciation semiannually. Note: Use tables, Excel, or a financial calculator. (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) Required: 1. Prepare appropriate journal entries recorded by Nath-Langstrom Services for the first year of the lease. 2. Prepare appropriate journal entries recorded by ComputerWorld Leasing for the first year of the lease. Answer is not complete. Complete this…arrow_forwardMM-6 An office equipment representative has a machine for sale or lease. If you buy the machine, the cost is $7,596. If you lease the machine, you will have to sign a noncancelable lease and make 5 payments of $2,000 each. The first payment will be paid on the first day of the lease. At the time of the last payment, you will receive title to the machine. The present value of an ordinary annuity of $1 is as LO M.8 follows: Present Value of $1 Discounted at Number of Periods 10% 12% 16% 0.909 0.893 0.862 1.736 2.487 1.690 2.402 1.605 2.246 3.037 3.605 2.798 3.274 3.170 3.791 The interest rate implicit in this lease is approximately: 2345arrow_forwarda. P150,000 b. P450,000 c. P900,000 d. Answer not givenarrow_forward
- Individual Income TaxesAccountingISBN:9780357109731Author:HoffmanPublisher:CENGAGE LEARNING - CONSIGNMENT