Advantage Energy Technology Data Center Migration—Part A
Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data center to a new office location. Careful planning is needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago, AET jumped into the “application service provider’ world. Their large data center provides clients with remote access to AET’s complete suite of application software systems. Traditionally, one of AET’s primary competitive advantages has been the company’s trademark IT reliability Due to the complexity of this project. Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised.
Currently, AET’s data center is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building located in the recently developed industrial complex at the Corvallis International Airport. On February 1, Brian is formally assigned the task by the Vice President of Operations, Dan Whitmore, with the following guidelines:
• From start to finish, it is anticipated the entire project will take three to four months to complete.
• It is essential that AET’s 235 clients suffer no downtime.
Whitmore advises Brian to come back to the Executive Committee on February 15, with a presentation on the scope of the project that includes costs, “first-cut” timeline, and proposed project team members.
Brian had some preliminary discussions with some of AET’s managers and directors from each of the functional departments and then arranged for a full-day scope meeting on February 4 with a few of the managers and technical representatives from operations, systems, facilities, and applications. The scope team determined the following;
Three to four months is a feasible project timeline and first-cut cost estimate is $80,000—$90,000 (this includes the infrastructure upgrade of the new site).
• Critical to the ‘no-downtime” requirement is the need to completely rely on AET’s remote disaster recovery ‘hot” site for full functionality.
• Brian will serve as project manager of a team consisting of one team member each from facilities, operations/systems, operations/telecommunications, systems & applications, and customer service.
Brian’s Executive Committee report was positively received and. after a few modifications and recommendations, he was formally charged with responsibility for the project Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project planning process.
Once the initial meeting is conducted Brian can hire the contractors to renovate the new data center. During this time Brian will figure out how to design the network Brian estimates that screening and hiring a contractor will take about one week and that the network design will take about two weeks. The new center requires a new ventilation system. The manufacturer’s requirements include an ambient temperature of 67 degrees to keep all of the data servers running at optimal speeds. The ventilation system has a lead time of three weeks. Brian will also need to order new racks to hold the servers, switches, and other network devices. The racks have a two- week delivery time.
The data center supervisor requested that Brian replace all of the old power supplies and data cables. Brian will need to order these as well. Because Brian has a great relationship with the vendor, they guarantee that it will take only one week lead time for the power supplies and the data cables. Once the new ventilation system and racks arrive, Brian can begin installing them. It will take one week to install the ventilation system and three weeks to install the racks. The renovation of the new data center can begin as soon as the contractors have been hired. The contractors tell Brian that construction will take 20 days. Once the construction begins and after Brian installs the ventilation system and racks, the city inspector must approve the construction of the raised floor.
The city inspector will take two days to approve the infrastructure. After the city inspection and after the new power supplies and cables have arrived, Brian can install the power supplies and run the cables. Brian estimates that it will take five days to install the power supplies and one week to run all of the data cables. Before Brian can assign an actual date for taking the network off line and switching to the hot remote site, he must get approval from each of the functional units (“Switchover Approval”). Meetings with each of the functional units will require one week During this tune he can initiate a power check to ensure that each of the racks has sufficient voltage. This will require only one day.
Upon completion of the power check, he can take one week to install his test servers. The test servers will test all of the primary network functions and act as a safeguard before the network is taken off line. The batteries must be charged, ventilation installed, and test servers up and running before management can be assured that the new infrastructure is safe, which will take two days. Then they will sign off the Primary Systems check, taking one day of intense meetings. They will also set an official date for the network move.
Brian is happy that everything has gone well thus far and is convinced that the move will go just as smoothly. Now that an official date is set, the network will be shut down for a day. Brian must move all of the network components to the new data center. Brian will do the move over the weekend—two days—when user traffic is at low point.
2. Develop a WBS for Brian’s project. Include duration (days) and predecessors.

Want to see the full answer?
Check out a sample textbook solution
Chapter 6 Solutions
PROJECT MANAGEMENT(LL)W/CONNECT
- Why do you think there is so much variation in how companies handle global training and development for their employees? Some firms adopt what is called an ethnocentric staffing model. Firms that use this model primarily use parent-country nationals (PCNs) to staff higher-level foreign positions. This strategy is based on the assumption that home-office perspectives and issues should take precedence over local perspectives and issues and that PCNs will be more effective in representing the views of the home office in the foreign operation Other international businesses adopt what is called a polycentric staffing model that calls for a much heavier use of host-country nationals (HCNs) from top to bottom throughout the organization. Thus, polycentric staffing is used with the assumption that such individuals (i.e., HCNs) are better equipped to deal with local market conditions. Organizations using this approach usually have a fully functioning HR department in each foreign subsidiary…arrow_forwardWhat are some contingency plans or actions that could have been taken by the Dubai man-made islands project managers to limit the impact of this possible risk event and other such related events the projects faced? Please list in PowerPoint forarrow_forwardDiscuss the attributes of good information.arrow_forward
- What quality management components should be considered for a project such as the Dubai man-made islands? Explain your position In a PowerPoint forarrow_forwardFor a small local Caribbean based company selling pepper sauces, seasonings looking to expand its operations to the us market provide details for the expansion plan proposal. Explain why international expansion is a good strategy for the company. International Business Environment Conduct a detailed SWOT analysis for the potential country of expansion (THREE points per category. These should be written in complete sentences). Evaluate key cultural factors that may impact business operations in the target market. Use Hofstede's six cultural dimensions to assess how cultural differences might affect the company's success in expanding internationally. Market Entry Strategy Discuss the different market entry modes, giving an example of each. Recommend the best one for the company based on its resources and goals. International Business Strategies Discuss the key international business strategies that could help the company succeed internationally. You are to recommend the best…arrow_forwardFor a small local Caribbean based company selling pepper sauces, seasonings looking to expand its operations to the us market provide details for the expansion plan proposal. Explain why international expansion is a good strategy for the company. International Business Environment Conduct a detailed SWOT analysis for the potential country of expansion (THREE points per category. These should be written in complete sentences). Evaluate key cultural factors that may impact business operations in the target market. Use Hofstede's six cultural dimensions to assess how cultural differences might affect the company's success in expanding internationally. Market Entry Strategy Discuss the different market entry modes, giving an example of each. Recommend the best one for the company based on its resources and goals. International Business Strategies Discuss the key international business strategies that could help the company succeed internationally. You are to recommend the best…arrow_forward
- As for The Soup Kitchen Project, why is managing and addressing risk is very important? After consulting with stakeholders and other team members for suggestions, why do you think utilizing an adaptive management risk approach would be great?arrow_forwardWhat employees will be eligible ? how long must the employees be employed under the plan ? what is the level of cost of the company will take on ?arrow_forwardIn a small island developing country, the service sector has been dominated by four companies: LightingPros Ltd., Island Solutions Inc., Real Services Co., and Entertainment Enterprises. Each company offers similar services, including event planning, catering, transportation, equipment rental, and audio-visual production. At present clients engage different companies for specific services, creating a balanced distribution of business across the market. However, recent shifts in client preferences have disrupted this equilibrium. Clients now prefer the convenience and efficiency of working with a single provider that can offer a comprehensive package of services. This has led to a significant decline in business for some companies that are unable to offer the full suite of services on their own. Some of the challenges faced by the companies include limited-service offerings, client convenience where clients prefer working with a single vendor to simplify communication, reduce costs, and…arrow_forward
- St. Lucia, a small island developing country, the service sector has been dominated by four companies: LightingPros Ltd., Island Solutions Inc., Real Services Co., and Entertainment Enterprises. Each company offers similar services, including event planning, catering, transportation, equipment rental, and audio-visual production. At present clients engage different companies for specific services, creating a balanced distribution of business across the market. However, recent shifts in client preferences have disrupted this equilibrium. Clients now prefer the convenience and efficiency of working with a single provider that can offer a comprehensive package of services. This has led to a significant decline in business for some companies that are unable to offer the full suite of services on their own. Some of the challenges faced by the companies include limited-service offerings, client convenience where clients prefer working with a single vendor to simplify communication, reduce…arrow_forwardTransactional leadership Discuss how this leadership style will fit with the healthcare industry and can benefit the staff. Explain your answer.arrow_forwardFive crucial traits—emotional intelligence, visionary wondering, conversation, adaptability, and empathy discuss in detail how these traits support someone in becoming an effective leader in a management position.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning