A producer of inkjet printer is planning to add a new line of printers, and you have been asked to balance the process, given the following task time and precedence relationship. Assume that cycle time is to be the minimum possible.
a. Do each of the following:
(1) Draw the precedence diagram.
(2) Assign tasks to stations in order of most following tasks. Tiebreaker, greatest positional weight.
(3) Determine the percentage of idle time.
(4) Compute the late of output in printers per day that could be expected for that line assuming a 420-minute working day.
b. Answer these questions:
(1) What it the shortest cycle tone that will permit use of only two workstations? Is this cycle time feasible? Identify the tasks you would assign to each station.
(2) Determine the percentage of idle time that would results if two stations were used.
(3) What is the daily output under this arrangement?
(4) Determine the output rate that would be associated with the maximum cycle time.
a) 1

To draw: The precedence diagram.
Answer to Problem 4P
Answer: Precedence diagram:
Explanation of Solution
Given information:
Task | Length (minutes) | Immediate (Predecessor) |
a | 0.2 | Nil |
b | 0.4 | a |
c | 0.3 | Nil |
d | 1.3 | b, c |
e | 0.1 | Nil |
f | 0.8 | e |
g | 0.3 | d, f |
h | 1.2 | g |
Precedence diagram:
The precedence diagram is drawn circles and arrows. The tasks are represented in circles and weights for each task are represented outside the circle. The arrows are represented to show which task is preceding the other task and so on.
2)

To assign: Tasks to workstations in the order of most following tasks.
Explanation of Solution
Given information:
Task | Length (minutes) | Immediate (Predecessor) |
a | 0.2 | Nil |
b | 0.4 | a |
c | 0.3 | Nil |
d | 1.3 | b, c |
e | 0.1 | Nil |
f | 0.8 | e |
g | 0.3 | d, f |
h | 1.2 | g |
The positional weight of a task is the sum of the task times of the task itself and all of the following tasks.
Task | Following tasks | Number of following tasks | Calculation of positional weight | Positional weight |
a | b, d, g, h | 4 | 0.2 + 0.4 + 1.3 + 0.3 + 1.2 | 3.4 |
b | d, g, h | 3 | 0.4 + 1.3 + 0.3 + 1.2 | 3.2 |
c | d, g, h | 3 | 0.3 + 1.3 + 0.3 + 1.2 | 3.1 |
d | g, h | 2 | 1.3 + 0.3 + 1.2 | 2.8 |
e | f, g, h | 3 | 0.1 + 0.8 + 0.3 + 1.2 | 2.4 |
f | g, h | 2 | 0.8 + 0.3 + 1.2 | 2.3 |
g | h | 1 | 0.3 + 1.2 | 1.5 |
h | Nil | 0 | 1.2 | 1.2 |
Calculation of cycle time:
The cycle is said to be the minimum time possible.
Therefore, the cycle time is 1.3 minutes / unit.
Assigning tasks to workstations:
Workstation number | Eligible task | Assigned task | Task time | Unassigned cycle time | Reason |
1.3 | |||||
1 | a, c, e | a | 0.2 | 1.1 | Task 'a' has more number of following tasks |
b, c , e | b | 0.4 | 0.7 | Task 'b' has greatest positional weight | |
c, e | c | 0.3 | 0.4 | Task 'c' has greatest positional weight | |
d, e | e | 0.1 | 0.3 | Task 'e' has greatest positional weight | |
d, f | None | 0.3 (Idle time) | The task time is greater than the unassigned cycle time. | ||
1.3 | |||||
2 | d, f | d | 1.3 | 0 | Task 'd' has greatest positional weight |
1.3 | |||||
3 | f | f | 0.8 | 0.5 | Task 'f' is the only eligible task available |
g | g | 0.3 | 0.2 | Task 'g' is the only eligible task available | |
h | None | 0.2 (Idle time) | The task time is greater than the unassigned cycle time. | ||
1.3 | |||||
4 | h | h | 1.2 | 0.1 | Task 'h' is the only task remaining |
0.1 (Idle time) | All tasks completed |
Overview of tasks assignment:
Workstation | Assigned tasks | Total cycle time used | Idle time |
1 | a, b, c, e | 1 | 0.3 |
2 | d | 1.3 | 0 |
3 | f, g | 1.1 | 0.2 |
4 | h | 1.2 | 0.1 |
3)

To determine: The percentage of idle time.
Answer to Problem 4P
Explanation of Solution
Formula to calculate percentage of idle time:
Calculation of percentage of idle time:
The percentage of idle time is 11.54%.
4)

To determine: The rate of output printers per day.
Answer to Problem 4P
Explanation of Solution
Given information:
Operating time per day = 420 minutes
Formula to calculate output printers per day:
Calculation of output printers per day:
The rate of output printers per day is 323.08 printers / day.
b) 1

To determine: The shortest cycle time that will permit the use of only 2 workstations and to check if it is feasible.
Explanation of Solution
Given information:
Task | Length (minutes) | Immediate (Predecessor) |
a | 0.2 | Nil |
b | 0.4 | a |
c | 0.3 | Nil |
d | 1.3 | b, c |
e | 0.1 | Nil |
f | 0.8 | e |
g | 0.3 | d, f |
h | 1.2 | g |
Calculation of shortest cycle time:
The shortest cycle time is calculated by summing all the task times and dividing the resultant value by 2 workstations.
The obtained shortest cycle time is feasible based on the task times. Every task time is either equal to or less than 2.3 minutes. The feasibility is checked by assigning the tasks to the 2 workstations.
Assigning tasks to workstations:
Workstation number | Eligible task | Assigned task | Task time | Unassigned cycle time | Reason |
2.3 | |||||
1 | a, c, e | a | 0.2 | 2.1 | Task 'a' has more number of following tasks |
b, c , e | b | 0.4 | 1.7 | Task 'b' has greatest positional weight | |
c, e | c | 0.3 | 1.4 | Task 'c' has greatest positional weight | |
d, e | e | 0.1 | 1.3 | Task 'e' has more number of following tasks | |
d, f | d | 1.3 | 0 | Task 'd' has greatest positional weight | |
2.3 | |||||
2 | f | f | 0.8 | 1.5 | Task 'f' is the only eligible task available |
g | g | 0.3 | 1.2 | Task 'g' is the only eligible task available | |
h | h | 1.2 | 1.2 | Task 'h' is the only task available |
Overview of tasks assignment:
Workstation | Assigned tasks | Total cycle time used | Idle time |
1 | a, b, c, e, d | 2.3 | 0 |
2 | f, g, h | 2.3 | 0 |
The shortest cycle time of 2.3 minutes is feasible.
2)

To determine: The percentage of idle time.
Answer to Problem 4P
Explanation of Solution
Formula to calculate percentage of idle time:
Calculation of percentage of idle time:
The percentage of idle time is 0.00%.
3)

To determine: The daily output under this arrangement.
Answer to Problem 4P
Explanation of Solution
Given information:
Operating time per day = 420 minutes
Formula to calculate output under this arrangement:
Calculation of output under this arrangement:
The rate of output under this arrangement is 182.61 units / day.
4)

To determine: The output rate associated with cycle time.
Answer to Problem 4P
Explanation of Solution
Given information:
Operating time per day = 420 minutes
Formula to calculate output under this arrangement:
Calculation of output under this arrangement:
The maximum cycle time is the sum of all task times.
The sum of all task times is:
The rate of output under this arrangement is 91.30 units / day.
Want to see more full solutions like this?
Chapter 6 Solutions
EBK OPERATIONS MANAGEMENT
- 1) View the videos Taco Bell test-drives Live Mas restaurant concept in South Bay (0.32 mins, Ctrl+Click on the link) https://www.youtube.com/watch?v=04wRc5Wg8GU , and First-ever Taco Bell Live Mas Café serving exclusive drinks in Chula Vista (1.56 mins, Ctrl+Click on the link) https://www.youtube.com/watch?v=fq6jDxJk1LM , and answer the following questions: a) What is driving Taco Bell to try a beverage-focused format? b) What type of a process strategy does their beverage-focused format represent? c) What operational issues do you think Taco Bell would face from their beverage-focused format? d) What do you think are the main advantages and disadvantages of kiosk ordering? Note: As a rough guideline, please try to keep the written submission to one or two paragraphs for each of the questions. 2) Taipei Pharmaceuticals is planning to open a new manufacturing facility as part of its expansion plans. The firm has narrowed down the search to locate its new manufacturing facility…arrow_forward1) View the videos Taco Bell test-drives Live Mas restaurant concept in South Bay (0.32 mins, Ctrl+Click on the link) https://www.youtube.com/watch?v=04wRc5Wg8GU , and First-ever Taco Bell Live Mas Café serving exclusive drinks in Chula Vista (1.56 mins, Ctrl+Click on the link) https://www.youtube.com/watch?v=fq6jDxJk1LM , and answer the following questions: a) What is driving Taco Bell to try a beverage-focused format? b) What type of a process strategy does their beverage-focused format represent? c) What operational issues do you think Taco Bell would face from their beverage-focused format? d) What do you think are the main advantages and disadvantages of kiosk ordering? Note: As a rough guideline, please try to keep the written submission to one or two paragraphs for each of the questions. 2) Taipei Pharmaceuticals is planning to open a new manufacturing facility as part of its expansion plans. The firm has narrowed down the search to locate its new manufacturing facility…arrow_forwardThe Clothing Shack is an online retailer of men's, women's, and children's clothing. The company has been in business for four years and makes a modest profit from its online sales. However, in an effort to compete successfully against online retailing heavyweights, the Clothing Shack's marketing director, Makaya O'Neil, has determined that the Clothing Shack's marketing information systems need improvement. Ms. O'Neil feels that the Clothing Shack should begin sending out catalogs to its customers, keep better track of its customer's buying habits, perform target marketing, and provide a more personalized shopping experience for its customers. Several months ago, Ms. O'Neil submitted a systems service request (SSR) to the Clothing Shack's steering committee. The committee unanimously approved this project. You were assigned to the project at that time and have since helped your project team successfully complete the project initiation and planning phase. Your team is now ready to move…arrow_forward
- b-1. Activity ES EF LS LF Slack 1 2 3 4 5 6 7 8 9 b-2. Identify the critical activities, and determine the duration of the project. The critical activities are .arrow_forwardThe forecast for each week of a four-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. Customer orders (committed) are follows: Week Customer Order 1 52 35 20 12 Use a production lot size of 75 units and no beginning Inventory. Determine the available-to-promise (ATP) quantities for each period. Note: Leave no cells blank - be certain to enter "0" wherever required. Period ATP 1 2 3arrow_forwardPrepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. Customer orders (committed) are as follows: Week Customer Orders 1 2 36 28 4 1 Use a production lot size of 85 units and no beginning inventory. Note: In the ATP row, enter a value of 0 (zero) in any periods where ATP should not be calculated. Leave no cells blank - be certain to enter "0" wherever required. June July 1 2 3 4 5 8 7 8 Forecast 60 60 60 60 60 60 60 60 Customer Orders 38 28 4 1 0 0 0 0 Projected On-Hand Inventory MPS ATParrow_forward
- Sales of tablet computers at Marika Gonzalez's electronics store in Washington, D.C., over the past 10 weeks are shown in the table below: Week 1 2 3 4 5 6 7 8 9 10 Demand 21 21 27 38 25 30 35 24 25 30 a) The forecast for weeks 2 through 10 using exponential smoothing with a = 0.50 and a week 1 initial forecast of 21.0 are (round your responses to two decimal places): Week 1 2 3 4 5 6 7 8 9 10 Demand 21 21 27 38 25 30 35 24 25 30 Forecast 21.0 21 21 24 31 28 29 32 28 26.50 b) For the forecast developed using exponential smoothing (a = 0.50 and initial forecast 21.0), the MAD = |||||sales (round your response to two decimal places).arrow_forwardSales of tablet computers at Marika Gonzalez's electronics store in Washington, D.C., over the past 10 weeks are shown in the table below: Week Demand 1 2 3 4 5 6 7 8 9 10 21 21 27 38 25 30 35 24 25 30 a) The forecast for weeks 2 through 10 using exponential smoothing with a = 0.50 and a week 1 initial forecast of 21.0 are (round your responses to two decimal places): Week 1 2 3 4 5 Demand 21 21 27 38 Forecast 21.0 ☐ G ☐ ☐ 6 7 25 30 35 ∞ ☐ 8 9 10 24 25 30arrow_forwardEach machine costs $3 Million. Building the room with all its attendant safety protection and other ancillary costs increases the spending by an additional $2.0 million dollars per MRI suite. Each machine can perform 2000 scans per year. Each reading of an MRI scan by a radiologist, along with other per-scan-related costs, is $500 per scan. The machine will last five years. Don’t worry about discount rates for this problem Graph the total costs over 5 years as a function of sales for 0-3000 patients annually. Hint: you may need to add a second MRI at some point. Suppose that you want to make a profit of $500 per scan at a target volume of 1000 patients per year, and you purchase only one machine. Superimpose the total revenue curve on top of the total cost curve in (1).arrow_forward
- I need the answer to requirement C.arrow_forwardImagine you are Susan Kim and are faced with a difficult choice to either follow the orders she was given, or refusing to do so. Using each lens determine what the ethical response would be. Suppot your answer with materials from readings and lectures. For example, using Universalism what would the ethical response be? Do the same for all four lenses.arrow_forwardAnswer all these questions, selecting any company of your choice. Choose a specific type of food company. Select a specific product. Develop all the inputs that are part of the process. Develop the transformation process in a graphic (diagram, etc.). Develop all the outputs or finished products that are part of the process. Describe all the processes involved in one line of production in any manufacturing facility. Also describing how good management is the center of any part of a production company.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing