Chapter 6, Problem 23P

(a)

To determine

Calculate the equivalent annual worth.

(a)

Expert Solution
Check Mark

Explanation of Solution

Table -1 shows the cash flow of different models.

Table -1

Models12
Price (P)-30,000-2,000
AOC (MO) per year-1,000-150
Salvage value (SV)8,000 
Number of pallet (PA)500800
Cost per pallet (CP)-10-10
Wage (W)-32,000-55,000
Time period (n)124
Interest  (i)8%8%

Pallets are purchased every 2 years once.

The equivalent annual worth of project 1 (AW1) can be calculated as follows:

AW1=(C(i(1+i)n(1+i)n1)+MO+SV(i(1+i)n1)+W+(PA×CP)(1(1+i)2+1(1+i)4+1(1+i)6+1(1+i)8+1(1+i)10+1)(i(1+i)n(1+i)n1))=(30,000(0.08(1+0.08)12(1+0.08)121)1,000+8,000(0.08(1+0.08)121)32,000+(500×10)(1(1+0.08)2+1(1+0.08)4+1(1+0.08)6+1(1+0.08)8+1(1+0.08)10+1)(0.08(1+0.08)12(1+0.08)121))=(30,000(0.08(2.51817)2.518171)+8,000(0.082.518171)33,0005,000(11.1664+11.360489+11.586874+11.85093+12.158925+1)(0.08(2.51817)2.518171))=(30,000(0.201451.51817)+8,000(0.081.51817)33,0005,000(0.857339+0.735029+0.630169+0.540269+0.463193+1)(0.201451.51817))=(30,000(0.132693)+8,000(0.052695)33,0005,000(4.225999)(0.132693))=(3,980.79+421.5633,0002,803.8)=39,363.03

The annual worth of the project 1 is -$39,363.03.

Number of electric pallet mover (N) is 2. The equivalent annual worth of project 2 (AW2) can be calculated as follows:

AW2=((N)C(i(1+i)n(1+i)n1)+(N)MO+W+(PA×CP)(1+1(1+i)2)(i(1+i)n(1+i)n1))=(2(2,000)(0.08(1+0.08)4(1+0.08)41)+2(150)55,000+(800×10)(1+1(1+0.08)2)(0.08(1+0.08)4(1+0.08)41))=(4,000(0.08(1.360489)1.3604891)30055,0008,000(1+11.1664)(0.08(1.360489)1.3604891))=(4,000(0.1088390.360489)55,3008,000(1+0.857339)(0.1088390.360489))=4,000(0.30192)55,30014,858.712(0.30192)=1,207.6855,3004,486.14=60,993.82

The annual worth of the project 2 is -$38,699.56.

Since the annual worth of the project 1 is greater than the project 2, select the project 1.

(b)

To determine

Calculate the annual worth using spreadsheet.

(b)

Expert Solution
Check Mark

Explanation of Solution

The annual worth of the project 1 and 2 is calculated by using spreadsheet as follows:

Engineering Economy, Chapter 6, Problem 23P

Since the annual worth of the project 1 (Forklift) is greater than the project 2 (Walkies), select the project 1.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Knowledge Booster
Background pattern image
Economics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education
Valuation Analysis in Project Finance Models - DCF & IRR; Author: Financial modeling;https://www.youtube.com/watch?v=xDlQPJaFtCw;License: Standard Youtube License