Textbook Question
Book Icon
Chapter 6, Problem 1C

In October 1908, just prior to the launch of his Model T, Henry Ford proclaimed, “I will build a motor car for the great multitude.” During the next 19 years, Ford built 15 million vehicles of this model. The success of the Model T was made possible through Ford’s development of the moving assembly line, where thousands of workers assembled the cars under harsh conditions. Unskilled labor was cheap. Workers initially received $2.30 for a 9-hour shift.

Given the rough conditions at the factory, absenteeism was a major problem. From the 13,000 workers at the plant, typically 1000 of them did not show up for work. Moreover, the employee turnover was a remarkable 370 percent at Ford’s Highland Park plant. Workers were becoming increasingly difficult to hire, and because most workers were immigrants, the plant was plagued by communications problems reflecting poor English language skills.

To respond to this challenge, in January 1914, wages were doubled to $5 per day and shifts were limited to 8-hour durations. In addition to the pay raise, Ford also requested that his workers learn English, take care of their health, and start saving for a home.

Many experts in the industry thought that Ford’s move was insane and he would not be able to afford the higher labor costs. But Ford proved them wrong. In the fall of 1908, a new Model T cost $850 (this corresponds to $20,763 in 2013). By 1927, Ford was producing a new Model T every 27 seconds and each cost $260 (this corresponds to $3372 in 2013).

In 1913, how long did the average worker stay with the plant?

Blurred answer
Students have asked these similar questions
Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Activity A B с Time according to schedule (weeks) Activity F G H Time according to schedule (weeks) D E COE
Given the information below, estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that B-F-G will take 20 weeks or less. Refer to the standard normal table. Activity A Expected Time (weeks) Variance 3.5 1.00 BCDE 5.5 0.96 C 4.0 0.45 12.0 1.78 6.5 2.25 F G 9.0 2.78 4.5 0.69 The probability that this path will take more than 20 weeks to complete is (Enter your response rounded to four decimal places.)
You are the event manager of a wedding project that is behind schedule and over budget. The client has requested some additional features that were not in the original scope. How would you prioritize the additional features requested by the client? What strategies would you employ to adjust the project plan and budget to accommodate these changes effectively? Additionally, what specific tools and techniques would you utilize to monitor and control the progress and ensure the quality of the project?

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY