Using Microsoft Project, set up the network and determine the critical path for Phase 1 of the Whistler Ski Resort project. The project workweek will be 5 days (M-F).
Whistler Ski Resort Project
Given the fact that the number of skiing visitors to Whistler, B.C., Canada, has been increasing at an exciting rate, thanks to the 2010 Winter Olympics, the Whistler Ski Association has been considering construction of another ski lodge and ski complex. The results of an economic feasibility study just completed by members of the staff show that a winter resort complex near the base of Whistler Mountain could be a very profitable venture. The area is accessible by car, bus, train, and air. The board of directors has voted to build the 10-million-dollar complex recommended in the study. Unfortunately, due to the short summer season, the complex will have to be built in stages. The first stage (year 1) will contain a day lodge, chair lift, rope tow, generator house (for electricity), and a parking lot designed to accommodate 400 cars and 30 buses. The second and third stages will include a hotel, ice rink, pool, shops, two additional chair lifts, and other attractions. The board has decided that stage one should begin no later than April 1 and be completed by October 1, in time for the next skiing season. You have been assigned the task of project manager, and it is your job to coordinate the ordering of materials and construction activities to ensure the project’s completion by the required date.
After looking into the possible sources of materials, you are confronted with the following time estimates. Materials for the chair lift and rope tow will take 30 days and 12 days, respectively, to arrive once the order is submitted. Lumber for the day lodge, generator hut, and foundations will take 9 days to arrive. The electrical and plumbing materials for the day lodge will take 12 days to arrive. The generator will take 12 days to arrive. Before actual construction can begin on the various facilities, a road to the site must be built; this will take 6 days. As soon as the road is in. clearing can begin concurrently on the sites of the day lodge, generator house, chair lift, and rope tow. It is estimated that the clearing task at each site will take 6 days, 3 days, 36 days, and 6 days, respectively. The clearing of the main ski slopes can begin after the area for the chair lift has been cleared; this will take 84 days.
The foundation for the day lodge will take 12 days to complete. Construction of the main framework will take an additional 18 days. After the framework is completed, electrical wiring and plumbing can be installed concurrently. These should take 24 and 30 days, respectively. Finally, the finishing construction on the day lodge can begin; this will take 36 days.
Installation of the chair lift towers (67 days) can begin once the site is cleared, lumber delivered, and the foundation completed (6 days). Also, when the chair lift site has been cleared, construction of a permanent road to the upper towers can be started; this will take 24 days. While the towers are being installed, the electric motor to drive the chair lift can be installed; the motor can be installed in 24 days. Once the towers are completed and the motor installed, it will take 3 days to install the cable and an additional 12 days to install the chairs.
Installation of the towers for the rope tow can begin once the site is cleared and the foundation is built and poured; it takes 4 days to build the foundation, pour the concrete and let it cure, and 20 days to install the towers for the rope tow. While the towers are being erected, installation of the electric motor to drive the rope tow can begin; this activity will take 24 days. After the towers and motor are installed, the rope tow can be strung in 1 day. The parking lot can be cleared once the rope tow is finished; this task will take 18 days.
The foundation for the generator house can begin at the same time as the foundation for the lodge; this will take 6 days. The main framework for the generator house can begin once the foundation is completed; framing will take 12 days. After the house is framed, the diesel generator can be installed in 18 days. Finishing construction on the generator house can now begin and will take 12 more days.
Assignment:
Identify the critical path on your network.
Can the project be completed by October 1?
Want to see the full answer?
Check out a sample textbook solutionChapter 6 Solutions
PROJECT MANAGEMENT
- I participated in a team tasked with developing and implementing a new customer service training program. The team included five members: myself, two training specialists, an HR representative, and a team leader. Our work environment was a mix of virtual and collocated, with weekly in-person meetings and frequent virtual check-ins. Reflecting on our process, it's evident that parts of “Tuckman's model”(Forming, Storming, Norming, Performing, and Adjourning) were present in the development and completion of the project.arrow_forwardProvince/Territory Ontario Quebec British Columbia Alberta Saskatchewan Manitoba Nova Scotia Newfoundland and Labrador Number of Firms 2017 2019 2020 58 54 70 16 19 20 16 17 13 5 6 3 2 1 1 2 2 1 1 1 1 0 0 1 What makes these companies leaders is that they grew rapidly. It does not matter whether they are high-tech or old-economy companies, manufacturing or service companies, they all are exceptional. A remarkable assortment of products and services are offered by these companies. Examples include trucking, car parts, exterior painting services, steeped tea, gaming, sustainable office furniture, business performance consultants, and construction management. Dana 12arrow_forwardelijah wants to start a carpet cleaning business. to do so, he needs to purchase a carpet cleaner and advertise. he estimates the cleaner will cost $400 and advertising will cost $1,600 initially. the cleaning solution is fairly cheap, costing only $5 per room cleaned. he also thinks he will have $3 in gas on average for each client. if he charges $40 per room cleaned and cleans an average of 2 rooms per house, how many houses will he have to clean before breaking even? if taxes are 25% of profits, how many rooms will he have to clean before making $5,000 profit? answer the question by making a cvp worksheet similar to the depreciation sheets. make sure it works well, uses cell references and functions/formulas when appropriate, and looks nice.arrow_forward
- What insights can you gain from working in a laundry business while maintaining a balance in your personal life? What about the joy of doing your work?arrow_forwardHow can you improve your lost and found system in laundry business? Like if there's a customer who has a missing garments and another customer found it accidentally in their clothes?arrow_forwardthe government is about to build a coop housing project in an open land where rich elites are living,suggest some survey questions for the rich elites on citing the coop housing project in their neigbourhood.arrow_forward
- suggest a A PITCH TO CONVINCE CAPE BRETON UNIVERSITY USING THEIR MISSIO STATEMENT ,VISION STATEMENT AND VALUES TO TELL THE SCHOOL WHY THEY SHOULD SUPPORT THE COOP HOUSING PROJECT INITIATIVE WITH RESOURCES OTHER THAN FINANCE.arrow_forwardDRAW UP A PITCH TO CONVINCE CAPE BRETON UNIVERSITY USING THEIR MISSIO STATEMENT ,VISION STATEMENT AND VALUES TO TELL THE SCHOOL WHY THEY SHOULD SUPPORT THE COOP HOUSING PROJECT INITIATIVE WITH RESOURCES OTHER THAN FINANCE.arrow_forwardPlease original work (Please dont add any AI sentences) Background information: LEGO was founded in 1932. The word LEGO is from the Danish words LEg GOdt (play well). Later, it was realized that in Latin the word means “I put together”. The firm initially made wooden toys as well as other wood products stepladders, ironing boards, stools, etc. In 1947, the LEGO Group bought a plastic injection-molding machine for toy production and in 1949 the first LEGO Automatic Binding Brick with four and eight studs appeared. LEGO flourished for many years with its innovative toys. However, in 2004, innovation almost bankrupted the Danish toymaker. LEGO had become concerned about low-cost copies of its plastic building products so it sought to diversify into different activities including: theme parks, Clikits craft sets, action figures (Galidor), and a television show among other efforts. All of these were unprofitable and were eventually discontinued. Today, LEGO is growing in an overall…arrow_forward
- Please original work Talk about your current organization’s greatest needs for creating a balanced scorecard for management consulting firm, and steps you would take to design the balance scorecard. Please cite in text references and add weblinks.arrow_forwardPlease original work How do you think organizations can effectively balance short-term resource constraints with the need for long-term investments in areas like technology and employee development, especially when both are critical to achieving strategic goals? Please cite in text references and add weblinksarrow_forwardImportanc of the process Tuckman's model”(Forming, Storming, Norming, Performing, and Adjourning)arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,