Practical Management Science
6th Edition
ISBN: 9781337406659
Author: WINSTON, Wayne L.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 5.4, Problem 28P
Summary Introduction
To determine: The modification where there are N plants, M warehouses, and L customers.
Introduction: In linear programming, unbounded solution would occur when the objective function is infinite. If no solution satisfied the constraints then it is said to be unfeasible solution.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
In the original Gorman Construction Company problem, we found the shortest distance from the office (node 1) to the construction site located at node 6. Because some of the roads are highways and others are city streets, the shortest-distance routes between the office and the construction site may not necessarily provide the quickest or shortest-time route. Shown here is the Gorman road network with travel time rather than distance. Find the shortest route from Gorman’s office to the construction site at node 6 if the objective is to minimize travel time rather than distance.
Greenstreets Recycling, Inc., collects used motor oil from several collection sites around the Greater Stanford area. To minimize the use, and thereby the cost, of its labor, vehicle, and energy resources, the company is interested in locating the shortest route that will allow its collection vehicle to visit each collection site exactly once. The following table provides the travel distances in miles between each site. Note that the company’s recycling facility is located at site A.
From/To
A
B
C
D
E
F
A (depot)
–
25
50
48
41
60
B
25
–
35
22
23
43
C
50
35
–
25
47
65
D
48
22
25
–
24
40
E
41
23
47
24
–
21
F
60
43
65
40
21
–
Provide an efficient route for the collection vehicle.
Abu Dhabi municipality is given an assignment to ensure provision of enough water for residents of the Abu Dhabi city. The water is purified in a large water treatment plant (node
1) and then is sent via a water supply network to the Abu Dhabi city (node 14). As shown in the below water supply network, the capacity of each water pipeline (arc) is shown in million liters per hour. For example, the hourly water flow from node 1 to node 2 is four million liters, and from node 2 to node 1 is zero million liters.
a) The municipality is interested to find out how much water (in million liters per hour) can be sent from the water treatment plant to the Abu Dhabi city via this water supply network. Determine it.
b) Due to a maintenance problem both nodes 10 and 11 need to be taken offline.
Therefore, these nodes cannot flow any water in and out. How this problem impacts the network maximum flow capacity?
Please include algebraic method and excel solver.
Chapter 5 Solutions
Practical Management Science
Ch. 5.2 - Prob. 1PCh. 5.2 - Prob. 2PCh. 5.2 - Prob. 3PCh. 5.2 - Prob. 4PCh. 5.2 - Prob. 5PCh. 5.2 - Prob. 6PCh. 5.2 - Prob. 7PCh. 5.2 - Prob. 8PCh. 5.2 - Prob. 9PCh. 5.3 - Prob. 10P
Ch. 5.3 - Prob. 11PCh. 5.3 - Prob. 12PCh. 5.3 - Prob. 13PCh. 5.3 - Prob. 14PCh. 5.3 - Prob. 15PCh. 5.3 - Prob. 16PCh. 5.3 - Prob. 17PCh. 5.3 - Prob. 18PCh. 5.4 - Prob. 19PCh. 5.4 - Prob. 20PCh. 5.4 - Prob. 21PCh. 5.4 - Prob. 22PCh. 5.4 - Prob. 23PCh. 5.4 - Prob. 24PCh. 5.4 - Prob. 25PCh. 5.4 - Prob. 26PCh. 5.4 - Prob. 27PCh. 5.4 - Prob. 28PCh. 5.4 - Prob. 29PCh. 5.5 - Prob. 30PCh. 5.5 - Prob. 31PCh. 5.5 - Prob. 32PCh. 5.5 - Prob. 33PCh. 5.5 - Prob. 34PCh. 5.5 - Prob. 35PCh. 5.5 - Prob. 36PCh. 5.5 - Prob. 37PCh. 5.5 - Prob. 38PCh. 5 - Prob. 42PCh. 5 - Prob. 43PCh. 5 - Prob. 44PCh. 5 - Prob. 45PCh. 5 - Prob. 46PCh. 5 - Prob. 47PCh. 5 - Prob. 48PCh. 5 - Prob. 49PCh. 5 - Prob. 50PCh. 5 - Prob. 51PCh. 5 - Prob. 52PCh. 5 - Prob. 53PCh. 5 - Prob. 54PCh. 5 - Prob. 55PCh. 5 - Prob. 56PCh. 5 - Prob. 57PCh. 5 - Prob. 58PCh. 5 - Prob. 59PCh. 5 - Prob. 60PCh. 5 - Prob. 61PCh. 5 - Prob. 62PCh. 5 - Prob. 63PCh. 5 - Prob. 64PCh. 5 - Prob. 65PCh. 5 - Prob. 66PCh. 5 - Prob. 67PCh. 5 - Prob. 68PCh. 5 - Prob. 69PCh. 5 - Prob. 70PCh. 5 - Prob. 71PCh. 5 - Prob. 72PCh. 5 - Prob. 73PCh. 5 - Prob. 74PCh. 5 - Prob. 75PCh. 5 - Prob. 76PCh. 5 - Prob. 77PCh. 5 - Prob. 80PCh. 5 - Prob. 81PCh. 5 - Prob. 82PCh. 5 - Prob. 83PCh. 5 - Prob. 85PCh. 5 - Prob. 86PCh. 5 - Prob. 87PCh. 5 - Prob. 1C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 7. The BD restaurant chain purchases materials from four different food suppliers. The company wants to construct a new central distribution center to process and package the materials before shipping them to their various restaurants. The suppliers transport items in 40-foot truck trailers, each with a capacity of 38,000 lbs. The locations of the four suppliers and the annual number of trailer loads that will be transported to the distribution center are shown in the following table (distance in miles). Using the center-of-gravity method, determine a possible location for the distribution center. A B с D X Y 200 200 100 500 250 600 500 300 Load 75 105 135 60 BD wants to evaluate three different sites it has identified for its new distribution center relative to the four suppliers identified. The coordinates of the three sites under consideration are as follows: Site 1: x1 = 360, y₁ = 180 Site 2: X2 = 420, y2 = 450 Site 3: X3 = 250, y3 = 400arrow_forwardsolve for X in part Barrow_forwardThe network in the figure, shows the routes for shipping cars from three (3) plants (nodes, 1,2 and 3) to three (3) dealers (nodes, 6, 7, 8) by way of two (2) distribution centers (nodes 4and 5). The shipping costs per car (in $100) are shown on the arcs. Solve the problem as a transshipment model.1. Formulate the Linear Programming model 2. Choose one among the three methods for the starting/initial basic solution 3. Solve for the optimal solution using Method of Multipliersarrow_forward
- A bank has its head office in the financial district in the middle ofa city. A bank has six branches, three in the north of the city and threein the south all 5 km from the centre and spaced 3 km apart. The bankwishes to link all its branches via private leased lines but mustdecide between providing an individual line to each branch via anumber of inter-branch links and a smaller number of multiplexed linesto the centre. If a modem costs £100, a multiplexer/demultiplexercosts £200 and leased lines cost £100 per km per year to rent, suggesta design that will yield the most cost effective solution if theinstallation is to remain in operation for four years. 1st option is - link all branches by providing individual line to each branch via a number of inter branch links to the centre. 2nd option is - link all branches by providing smaller number of multiplexed lines to the centre Please calculate both options and choose the most cost effective solution for four years?arrow_forwardThe next diagram depicts a system of aqueducts that originate at three rivers (nodes R1, R2, and R3) and terminate at a major city (node T), where the other nodes are junction points in the system. From R1 R2 R3 R1 R2 Το R3 A B Using units of thousands of acre feet, the tables below show the maximum amount of water that can be pumped through each aqueduct per day. To D ABC From 130 115 - A 70 90 110 B 140 120 C E F T DEF DEF From D 110 85 - 130 95 85 130 160 F To T 220 330 240 The city water manager wants to determine a flow plan that will maximize the flow of water to the city. a) Formulate this problem as a maximum flow problem by identifying a source, a sink, and the transshipment nodes, and then drawing the complete network that shows the capacity of each arc.arrow_forward4. The plant engineer for the Bitco manufacturing plant is designing an overhead conveyor system that will connect the distribution/inventory center to all areas of the plant. The network of possible conveyor routes through the plant, with the length (in feet) along each branch, follows 120 160 80 50 210 140 4 190 40 130 50 6 Determine the shortest conveyor route from the distribution/inventory center at node 1 to each of the other six areas of the plant.arrow_forward
- Consider the following transshipment network for finding the shortest route from node 1 to node 7. Min s.t. Node 1 Flows X12 +*13 Node 3 Flows Node 4 Flows Node 5 Flows 18 Node 6 Flows Node 7 Flows w +x14 X Node 2 Flows -x12 - x32-x52 + x23+x25 = 0 3 4 (a) Formulate a linear programming model of the problem. (Express your answers using Xij, where each x¡¡ is either 0 or 1 for the arc from node i to node j.) 5 4 3 6 3 6 7arrow_forwardThe plant engineer for the Bitco manufacturing plant is designing an overhead conveyor system that will connect the distribution/inventory center to all areas of the plant. The network of possible conveyor routes through the plant, with the length (in feet) along each branch, follows: Determine the shortest conveyor route from the distribution/inventory center at node 1 to each of the other six areas of the plant.arrow_forwardAll-Weather Oil and Gas Company is planning delivery routes to six natural gas customers. The customer locations and gas requirements (in gallons) are given in the following table. (given) Assume that the depot is located at the origin of the grid and that the delivery trucks have a capacity of 1,200 gallons. Also assume that the cost of travel between any two locations is the straight-line (Euclidean) distance between them. Find the route schedule obtained from the savings method.arrow_forward
- The MidLands Trucking Company based in Louisvillehas eight trucks located throughout the Mideast that havedelivered their loads and are available for shipments. Through their Internet logistics site MidLands has re-ceived shipping requests from 12 customers. The follow-ing table shows the mileage for a truck to travel to a customer location, pick up the load, and deliver it. Determine the optimal assignment of trucks to customersthat will minimize the total mileage. Customers Truck A B C D E F G H I J K L1 500 730 620 410 550 600 390 480 670 710 440 5902 900 570 820 770 910 660 650 780 840 950 590 6703 630 660 750 540 680 750 810 560 710 1200 490 6504 870 1200 810 670 710 820 1200 630 700 900 540 6205 950 910 740 810 630 590 930 650 840 930 460 5606 1100 860 800 590 570 550 780 610 1300 840 550 7907 610 710 910 550 810 730 910 720 850 760 580 6308 560 690 660 640 720 670 830 690 880 1000 710 680arrow_forwardRauschenberg Manufacturing is investigating which locations would best position its new plant relative to three important customers (located in cities A, B, and C). As shown in the table below, all three customers require multiple daily deliveries. Management limited the search for this plant to those three locations and compiled the following information: Location A B C Coordinates (miles) (200,100) (400,200) (300,100) a. Which of these three locations yields the smallest load-distance score, based on Euclidean distances? Location one decimal place.) b. Which of these locations is best, based on rectilinear distances? yields the smallest load-distance score of Location whole number.) c. What are the coordinates of the center of gravity? is the best, yielding a load-distance score of * The center of gravity is x = decimal place.) * Deliveries per day miles, y = 5 7 9 (Enter your response rounded to (Enter your response as a miles. (Enter your responses rounded to onearrow_forwardPlease refer to the attached photo:arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,