South-Western Federal Taxation 2019: Individual Income Taxes (Intuit ProConnect Tax Online 2017 & RIA Checkpoint 1 term (6 months) Printed Access Card)
42nd Edition
ISBN: 9781337702546
Author: James C. Young, William H. Hoffman, William A. Raabe, David M. Maloney, Annette Nellen
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 5, Problem 57P
a.
To determine
Determine the tax consequences to V in the given scenario.
b.
To determine
Determine the tax consequences to V in the given scenario.
c.
To determine
Determine the tax consequences to V in the given scenario.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Your answer is partially correct.
During 2023, Darwin Corporation started a construction job with a contract price of $4.20 million. Darwin ran into severe technical
difficulties during construction but managed to complete the job in 2025. The contract is non-cancellable. Under the terms of the
contract, Darwin sends billings as revenues are earned. Billings are non-refundable. The following information is available:
Costs incurred to date
2023
Estimated costs to complete 3,150,000
Gross profit/(loss)
2024
$600,000 $2,100,000 $4,100,000
2023
2,100,000
2025
Calculate the amount of gross profit or loss that should be recognized each year under the zero-profit method. (Enter negative amounts
using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Do not leave any answer field blank. Enter O for amounts.)
72000 $
-0-
2024
-72000
2025
100000
DJ Builders Company began operations on January 1, 2008. During the year, DJ Builders Company entered into a contract with Joey Company to construct a manufacturing facility. At that time, DJ Builders estimated that it would take five years to complete the facility at a total cost of P 4,800,000. The contract price for construction of the facility is P 5,800,000.
During 2008, DJ Builders incurred P 1,250,000 in construction costs related to the project because of rising material and labor costs, the estimated cost to complete the contract at the end of 2008 is P 3,750,000. Joey Company was billed for and paid 30% of the contract price in accordance with the contract agreement. It is further agreed, that any costs incurred is expected to be recoverable.
Compute the amount of construction in progress (net) – due from customers or progress billings (net) – due to customers:
(Zero profit approach) Percentage of Completion…
Chan Builders Inc entered into a contract with George Company to construct a production plant. At that time, Chan Builders estimated that it would take five years to complete the facility at a total cost of P28,800,000. Chan Builders therefore, pegged the total contract price for the construction of the facility at P34,800,000. During 2010, Chan Builders incurred P7,500,000 in construction costs related to the project. Because of rising material and labor costs, the estimated cost to complete the contract at the end of 2010 amounted to P22,500,000. George was billed and paid 30% on the contract price in accordance with the contract agreement. Compute the Contract Asset (Contract Liability) for 2010.
George Co. enters into a contract to build an apartment for Jungle Co. for a fixed fee of ₱20,000,000. At contract inception, George Co. assesses its performance obligations in the contract and concludes that it has a single performance obligation that is satisfied over time. George…
Chapter 5 Solutions
South-Western Federal Taxation 2019: Individual Income Taxes (Intuit ProConnect Tax Online 2017 & RIA Checkpoint 1 term (6 months) Printed Access Card)
Ch. 5 - Prob. 1DQCh. 5 - Prob. 2DQCh. 5 - Prob. 3DQCh. 5 - Prob. 4DQCh. 5 - Prob. 5DQCh. 5 - Prob. 6DQCh. 5 - Prob. 7DQCh. 5 - Holly was injured while working in a factory and...Ch. 5 - Prob. 9DQCh. 5 - Prob. 10DQ
Ch. 5 - Ted works for Azure Motors, an automobile...Ch. 5 - Prob. 12DQCh. 5 - Eagle Life Insurance Company pays its employees...Ch. 5 - Several of Egret Companys employees have asked the...Ch. 5 - Prob. 15DQCh. 5 - Tammy, a resident of Virginia, is considering...Ch. 5 - Andrea entered into a 529 qualified tuition...Ch. 5 - Prob. 18DQCh. 5 - Prob. 19DQCh. 5 - Prob. 20CECh. 5 - Prob. 21CECh. 5 - Ellie purchases an insurance policy on her life...Ch. 5 - Prob. 23CECh. 5 - Leland pays premiums of 5,000 for an insurance...Ch. 5 - Jarrod receives a scholarship of 18,500 from...Ch. 5 - Prob. 26CECh. 5 - Prob. 27PCh. 5 - Prob. 28PCh. 5 - Prob. 29PCh. 5 - Prob. 30PCh. 5 - Prob. 31PCh. 5 - Prob. 32PCh. 5 - Prob. 33PCh. 5 - Prob. 34PCh. 5 - LO.2 Leigh sued an overzealous bill collector and...Ch. 5 - LO.2 Determine the effect on gross income in each...Ch. 5 - Prob. 37PCh. 5 - Prob. 38PCh. 5 - Prob. 39PCh. 5 - Prob. 40PCh. 5 - Prob. 41PCh. 5 - LO.2 Does the taxpayer recognize gross income in...Ch. 5 - Prob. 43PCh. 5 - Prob. 44PCh. 5 - Prob. 45PCh. 5 - LO.2, 5 Rosas employer has instituted a flexible...Ch. 5 - Prob. 47PCh. 5 - Prob. 48PCh. 5 - Prob. 49PCh. 5 - Prob. 50PCh. 5 - Prob. 51PCh. 5 - Prob. 52PCh. 5 - Prob. 53PCh. 5 - Prob. 54PCh. 5 - Prob. 55PCh. 5 - Prob. 56PCh. 5 - Prob. 57PCh. 5 - Prob. 59CPCh. 5 - Prob. 1RPCh. 5 - Prob. 2RPCh. 5 - Prob. 3RPCh. 5 - Prob. 4RPCh. 5 - Prob. 1CPACh. 5 - Linda is an employee of JRH Corporation. Which of...Ch. 5 - Kim was seriously injured at her job. As a result...Ch. 5 - Danny received the following interest and dividend...Ch. 5 - Prob. 5CPA
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $30 million. Construction costs incurred in the first year were $16 million and estimated remaining costs to complete at the end of the year were $17 million. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion? What if instead Franklin recognizes revenue upon contract completion?arrow_forwardYour client, Hazelton Mining, recently entered into an agreement to obtain the rights to operate a coal mine in West Virginia for $15 million. Hazelton incurred development costs of $6 million in preparing the mine for extraction, which began on July 1, 2021. The contract requires Hazelton to restore the land and surrounding area to its original condition after extraction is complete in three years.The company controller, Alice Cushing, is not sure how to account for the restoration costs and has asked your advice. Alice is aware of an accounting standard addressing this issue, but is not sure of its provisions. She has narrowed down the possible cash outflows for the restoration costs to four possibilities. Cash Outflow Probability $ 3 million 20 % 4 million 30 % 5 million 25 % 6 million 25 % Alice also informs you that the company’s credit-adjusted risk-free interest rate is 9%. Before responding to Alice, you need to research the issue.…arrow_forwardYour client, Hazelton Mining, recently entered into an agreement to obtain the rights to operate a coal mine in West Virginia for $15 million. Hazelton incurred development costs of $6 million in preparing the mine for extraction, which began on July 1, 2021. The contract requires Hazelton to restore the land and surrounding area to its original condition after extraction is complete in three years.The company controller, Alice Cushing, is not sure how to account for the restoration costs and has asked your advice. Alice is aware of an accounting standard addressing this issue, but is not sure of its provisions. She has narrowed down the possible cash outflows for the restoration costs to four possibilities. Cash Outflow Probability $ 3 million 20 % 4 million 30 % 5 million 25 % 6 million 25 % Alice also informs you that the company’s credit-adjusted risk-free interest rate is 9%. Before responding to Alice, you need to research the issue. Research…arrow_forward
- Your client, Hazelton Mining, recently entered into an agreement to obtain the rights to operate a coal mine in West Virginia for $15 million. Hazelton incurred development costs of $6 million in preparing the mine for extraction, which began on July 1, 2021. The contract requires Hazelton to restore the land and surrounding area to its original condition after extraction is complete in three years.The company controller, Alice Cushing, is not sure how to account for the restoration costs and has asked your advice. Alice is aware of an accounting standard addressing this issue, but is not sure of its provisions. She has narrowed down the possible cash outflows for the restoration costs to four possibilities. Cash Outflow Probability $ 3 million 20 % 4 million 30 % 5 million 25 % 6 million 25 % Alice also informs you that the company’s credit-adjusted risk-free interest rate is 9%. Before responding to Alice, you need to research the issue.…arrow_forwardYour client, Hazelton Mining, recently entered into an agreement to obtain the rights to operate a coal mine in West Virginia for $15 million. Hazelton incurred development costs of $6 million in preparing the mine for extraction, which began on July 1, 2021. The contract requires Hazelton to restore the land and surrounding area to its original condition after extraction is complete in three years.The company controller, Alice Cushing, is not sure how to account for the restoration costs and has asked your advice. Alice is aware of an accounting standard addressing this issue, but is not sure of its provisions. She has narrowed down the possible cash outflows for the restoration costs to four possibilities. Cash Outflow Probability $ 3 million 20 % 4 million 30 % 5 million 25 % 6 million 25 % Alice also informs you that the company’s credit-adjusted risk-free interest rate is 9%. Before responding to Alice, you need to research the issue.…arrow_forwardYour client, Portsmouth Mining, recently entered into an agreement to obtain the rights to operate a coal mine in Virginia for $15 million. Portsmouth incurred development costs of $6 million in preparing the mine for extraction, which began on Jul 1, 2021. The contract requires Portsmouth to restore the land and surrounding area to its original condition after extraction is complete in three years. The company controller, Anna Dickson, is not sure how to account for the restoration costs and has asked your advice. Anna is aware of an accounting standard addressing this issue, but is not sure of its provisions. She has narrowed down the possible cash outflows for the restoration costs to four possibilities. Cash Outflow Probability $ 3 million 20% $ 4 million 30% $ 5 million 25%…arrow_forward
- Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,200,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete the project are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,200,000 by the end of the end of the year. How should Tullis report Construction in Progress and Billings on Construction in Progress at the end of year 1 on the balance sheet assuming the use of the completed-contract method?arrow_forwardThe amount collected from the client in 2018 amounted to:arrow_forwardTullis Construction enters into a long-term fixed price contract to build an office tower for $10,300,000. In the first year of the contract Tullis incurs $2,200,000 of cost and the engineers determined that the remaining costs to complete the project are $5,800,000. Tullis billed $3,600,000 in year 1 and collected $3,500,000 by the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method? (Round any intermediary percentages to the nearest hundredth percent, and round your final answer to the nearest dollar) A. $2,832,500 B. $0 C. $5,032,500 D. $632,500 13arrow_forward
- A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the yearwere $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue, cost, and gross profit will the company recognize in the firstand second year of the contract applying the cost recovery method that is required by IFRS?arrow_forwardTullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete the project are $5,000,000. Tullis billed $5,000,000 in year 1 and collected $3,100,000 by the end of the end of the year. How should Tullis report Construction in Progress and Billings on Construction in Progress at the end of year 1 on the balance sheet assuming the use of the completed - contract method? O A. asset of $2,000,000 O B. liability of $1,900,000 O C. asset of $1,900,000 O D. liability of $2,000,000arrow_forwardOn April 1, 2018, the new machinery was ordered at a quoted price of P56, 000. On July 1, 2018, it arrived at Dodik Corp’s plant with an actual invoice price of P58,000, which it paid immediately. During July 2018, a new concrete platform was constructed at a cost of P4,000 to properly install the machine. In August 2018, testing was performed at a cost of P7,000 to ensure the machine was operating properly. On August 31, 2018, the machine was entered into service. Minor repairs and maintenance costs on the new machine amounted to P3,000 in September 2018. No other costs were incurred prior to December 31, 2018. Similar machinery is depreciated on a straight line basis over 10 years and typically has no residual value. What should be the depreciation expense for the year ended 31 December 2018?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Individual Income TaxesAccountingISBN:9780357109731Author:HoffmanPublisher:CENGAGE LEARNING - CONSIGNMENT
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Individual Income Taxes
Accounting
ISBN:9780357109731
Author:Hoffman
Publisher:CENGAGE LEARNING - CONSIGNMENT
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning