To determine

The personnel and cost required to sort all the refuse from a town and the description of problems involved in its implementation.

Expert Solution & Answer
Check Mark

Explanation of Solution

Given:

Population of town is 100000 .

Calculation:

Assume the following;

  • Municipal waste generation is 4.5lb/person/day .
  • The pickers can salvage 1000lb/hour/person .
  • Working time is 8hour/day .
  • Rate of picking is $10perhour .

Write the expression to calculate the manpower.

  M=P×qph×t   ...... (I)

Here, the manpower required is M , the population is P , the solid waste production per capita per day is q and the handpicking rate is ph .

Substitute, 100000person for P , 4.5lb/person/day for q , 1000lb/hour/person for ph and 8hour/day for t in Equation (I).

  M=( 100000person)×( 4.5 lb/ person / day )( 1000 lb/ hour / person )×( 8 hour/ day )=( 450000 8000)person=56.25person57person

Write the expression to calculate the required cost.

  C=M×t×s   ...... (II)

Here, the cost for manpower per day is C and the hourly salary rate is s .

Substitute 57person for M , 8hour/day for t and $10perhour in Equation (II).

  C=(57person)×(8hour/day)×($10perhour)=$4560perday

Conclusion:

Thus, the number of personnel required are 57person .

The cost required is $4560perday .

The major problem of this proposal is that it has significant effects on the health of manpower.

The solid waste contains volatile compounds that can be absorbed by the body.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
: A 5ms- long current pulse is desired for two linear lamps connected in series and pumped at a total energy input of (1KJ). Each of lamps has an arc-length of (10cm) and a bore of (1cm). If we assume a peak current of (i, -650A). Design a multiple mesh network including number of LC sections, inductance and capacitance per section and capacitor voltage. Laser design
What would be the best way to handle when a contractor misses a concrete pour deadline which causes delays for other contractors?
Please solve manually
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Solid Waste Engineering
Civil Engineering
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Cengage Learning,