Chapter 5, Problem 5.1P
To determine

The personnel and cost required to sort all the refuse from a town and the description of problems involved in its implementation.

Expert Solution & Answer
Check Mark

Explanation of Solution

Given:

Population of town is 100000 .

Calculation:

Assume the following;

  • Municipal waste generation is 4.5lb/person/day .
  • The pickers can salvage 1000lb/hour/person .
  • Working time is 8hour/day .
  • Rate of picking is $10perhour .

Write the expression to calculate the manpower.

  M=P×qph×t   ...... (I)

Here, the manpower required is M , the population is P , the solid waste production per capita per day is q and the handpicking rate is ph .

Substitute, 100000person for P , 4.5lb/person/day for q , 1000lb/hour/person for ph and 8hour/day for t in Equation (I).

  M=( 100000person)×( 4.5 lb/ person / day )( 1000 lb/ hour / person )×( 8 hour/ day )=( 450000 8000)person=56.25person57person

Write the expression to calculate the required cost.

  C=M×t×s   ...... (II)

Here, the cost for manpower per day is C and the hourly salary rate is s .

Substitute 57person for M , 8hour/day for t and $10perhour in Equation (II).

  C=(57person)×(8hour/day)×($10perhour)=$4560perday

Conclusion:

Thus, the number of personnel required are 57person .

The cost required is $4560perday .

The major problem of this proposal is that it has significant effects on the health of manpower.

The solid waste contains volatile compounds that can be absorbed by the body.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Describe in detail how a waste pipe size is calculated?
Question B-8 8. You are part of a group of Second Year Engineering Students at University of Botswana, intending to establish a Small Scale Recycling Plant for plastic materials in Gaborone. (a) Which recycling process options would you consider? (4 marks) (b) Briefly explain which option you would adopt, giving reasons for your choice. (6 marks) Question B-9 9. (a) Name two types of moulds commonly used in Compression Moulding of polymer materials. (2 marks) (b) Explain the main differences between the two types of moulds. (4 marks) (c) What are the advantages and disadvantages associated with each type of mould? (4 marks) Question B-10 10. (a) With the aid of diagrams briefly describe the 'Blow Moulding Process (6 marks) (b) Give two examples of polymer materials that can be processed by Blow Moulding. (2 marks) (c) Give two examples of products that can be produced by Blow Moulding. (2 marks)
Describe the different types of domestic solid waste.
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Solid Waste Engineering
Civil Engineering
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Cengage Learning,