Long-term contract; revenue recognition over time; loss projected on entire project
• LO5–9
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000.
In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of $3,800,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.
Required:
- 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
- 2. Prepare
journal entries for 2018 and 2019 to record the transactions described (credit “various accounts” for construction costs incurred). - 3. Prepare a partial
balance sheet to show the presentation of the project as of December 31, 2018 and 2019.
Requirement – 1

Contract
Contract is a written document that creates legal enforcement for buying and selling the property. It is committed by the parties to performing their obligation and enforcing their rights.
Revenue recognized point of long term contract
A long-term contract qualifies for revenue recognition over time. The seller can recognize the revenue as per percentage of the completion of the project, which is recognized by revenue mines cost of completion until date.
A contract does not meet the performance obligation norm. The seller cannot recognize the revenue till the project complete.
The revenue recognition principle
The revenue recognition principle refers to the revenue that should be recognized in the time period, when the performance obligation (sales or services) of the company is completed.
To calculate: The amount of revenue and gross profit or loss to be recognized in the year 2018, 2019, and 2020.
Explanation of Solution
Recognized revenue
In the year 2018:
Here,
Contract price is $8,000,000,
Actual cost to date is $2,000,000,
Total estimated cost is $6,000,000.
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $2,666,667.
In the year 2019:
Here,
Contract price is $8,000,000,
Actual cost to date is $4,500,000,
Total estimated cost is $8,100,000,
Revenue recognition in 2018 is $2,666,667.
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $1,777,778.
In the year 2020:
Here,
Contract price is $8,000,000,
Revenue recognition in 2018 is $2,666,667,
Revenue recognition in 2019 is $1,777,778.
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $3,555,555.
Recognized gross profit
In the year 2018:
Here,
Revenue recognition in 2018 is $2,666,667
Actual cost to date is $2,000,000.
Now, calculate the gross profit recognition:
Hence, the calculated gross profit recognition is $666,667.
In the year 2019:
Here,
Revenue recognition in 2019 is ($100,000)
Gross profit recognition in 2018 is $666,667.
Now, calculate the gross profit recognition:
Hence, the calculated gross loss recognition is ($766,667).
In the year 2020:
Here,
Revenue recognition in 2020 is ($300,000)
Revenue recognition in 2019 is ($100,000).
Now, calculate the gross profit recognition:
Hence, the calculated gross loss recognition is ($200,000).
Working note:
Calculate the value of gross profit (in millions)
Particulars | 2018 | 2019 | 2020 | |||
Contract price | $8 | $8 | $8 | |||
Actual costs to date | $2 | $4.5 | $8.3 | |||
Estimated costs to complete | $4 | $3.6 | $0 | |||
Total estimated cost | $6 | $8.1 | $8.3 | |||
Estimated gross profit | $2 | ($0.1) | ($0.3) |
Table (1)
(1)
Requirement – 2

To record: The journal entry for the year 2018 and 2019.
Explanation of Solution
In the year 2018:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $2,000,000 | |||
Various accounts | $2,000,000 | |||
(To record construction cost) |
Table (2)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $2,500,000 | |||
Billings on construction contract | $2,500,000 | |||
(To record progress billings) |
Table (3)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is a decrease in liability value. Therefore, it is debited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $2,250,000 | |||
Account receivable | $2,250,000 | |||
(To record cash collection) |
Table (4)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $666,667 | |||
Cost of construction | $2,000,000 | |||
Revenue from long-term contracts | $2,666,667 | |||
(To record gross profit) |
Table (5)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Cost of construction is an expense. There is a decrease in liability value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in liability value. Therefore, it is credited.
In the year 2019:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $2,500,000 | |||
Various accounts | $2,500,000 | |||
(To record construction cost) |
Table (6)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $2,750,000 | |||
Billings on construction contract | $2,750,000 | |||
(To record progress billings) |
Table (7)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is a decrease in liability value. Therefore, it is debited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $2,475,000 | |||
Account receivable | $2,475,000 | |||
(To record cash collection) |
Table (8)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cost of construction (2) | $2,544,445 | |||
Revenue from long-term contracts | $1,777,778 | |||
Construction in progress | $766,667 | |||
(To record expected loss) |
Table (9)
- Cost of construction is an expense. There is a decrease in liability value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in liability value. Therefore, it is credited.
- Construction in progress is an asset. There is a decrease in asset value. Therefore, it is credited.
Working note:
Calculate the cost of construction
Given,
Revenue recognition in 2019 is $1,777,778
Loss recognition in 2019 is $766,667.
Now, calculate the gross profit recognition:
(2)
Requirement – 3

To prepare: A partial balance sheet to show the presentation of the project as of December 31, 2018 and 2019.
Explanation of Solution
In the year ended 2018:
Balance sheet At December 31,2018 | |
Current assets | Amount |
Account receivable | $250,000 |
Cost and profit in excess of billings (3) | $166,667 |
Table (10)
Working note:
Calculate the costs and profit in excess of billings:
Given,
Profit is $2,666,667
Billing profit is $2,500,000.
Now, calculate the costs and profit in excess of billings:
(3)
In the year ended 2019:
Balance sheet At December 31,2019 | |
Current assets | Amount |
Account receivable | $525,000 |
Current liability | Amount |
Cost and profit in excess of billings (4) | $850,000 |
Table (11)
Working note:
Calculate the costs and profit in excess of billings:
Given,
Profit is $5,250,000
Billing profit is $4,400,000.
Now, calculate the costs and profit in excess of billings:
(4)
Want to see more full solutions like this?
Chapter 5 Solutions
INTERMEDIATE ACCOUNTING, W/CONNECT
- Financing Deficit Stevens Textile Corporation's 2019 financial statements are shown below: Just need the correct LOC? Balance Sheet as of December 31, 2019 (Thousands of Dollars) Cash $ 1,080 Accounts payable $ 4,320 Receivables 6,480 Accruals 2,880 Inventories 9,000 Line of credit 0 Total current assets $16,560 Notes payable 2,100 Net fixed assets 12,600 Total current liabilities $ 9,300 Mortgage bonds 3,500 Common stock 3,500 Retained earnings 12,860 Total assets $29,160 Total liabilities and equity $29,160 Income Statement for December 31, 2019 (Thousands of Dollars) Sales $36,000 Operating costs 34,000 Earnings before interest and taxes $ 2,000 Interest 160 Pre-tax earnings $ 1,840 Taxes (25%) 460 Net income $ 1,380 Dividends (40%) $ 552 Addition to retained earnings $ 828 Stevens grew rapidly in 2019 and financed the growth with notes payable and long-term bonds. Stevens expects sales to…arrow_forwardWhen iuploading image then it get blurry Comment in comment section I will write data.arrow_forwardCorrect answer pleasearrow_forward
- In 2022, North Shore Community College had a total student body that was 5% more than in 2021, which was 5% more than in 2020. The enrollment in 2022 was 4,200. How many students attended the college in 2021? How many students attended the college in 2020?arrow_forwardWhen iam uploading it getting blurr comment i will write values. Don't answer with incorrect dataarrow_forwardSolve correctly if image is blurry comment..arrow_forward
- If data is not clear please commentarrow_forwardPlease don't use AI And give correct answer .arrow_forwardLouisa Pharmaceutical Company is a maker of drugs for high blood pressure and uses a process costing system. The following information pertains to the final department of Goodheart's blockbuster drug called Mintia. Beginning work-in-process (40% completed) 1,025 units Transferred-in 4,900 units Normal spoilage 445 units Abnormal spoilage 245 units Good units transferred out 4,500 units Ending work-in-process (1/3 completed) 735 units Conversion costs in beginning inventory $ 3,250 Current conversion costs $ 7,800 Louisa calculates separate costs of spoilage by computing both normal and abnormal spoiled units. Normal spoilage costs are reallocated to good units and abnormal spoilage costs are charged as a loss. The units of Mintia that are spoiled are the result of defects not discovered before inspection of finished units. Materials are added at the beginning of the process. Using the weighted-average method, answer the following question: What are the…arrow_forward