Question
Book Icon
Chapter 5, Problem 30P

(a):

To determine

Compare the project based on future worth.

(a):

Expert Solution
Check Mark

Explanation of Solution

Table-1 shows the cash flow of different projects.

Table -1

ProjectsABC
First cost (C)40,00080,000130,000
Annual cost (AC) per year9,0006,0004,000
Salvage value (SV)  10% to C
Time period (n)248

Interest rate (i) is 10%.

The time period for project A should be equated with project time period C. Thus, all the cash flows are repeated for other 6 years. The time period 1 (n) is 8 years, time period 2 (n1) is 6 years, time period 3 (n2) is 4 years, and time period 4 (n3) is 2 years.

Future value project A (FWA) can be calculated as follows:

FWA=C((1+i)n+(1+i)n1+(1+i)n2+(1+i)n4)AC((1+i)n1i)=40,000((1+0.1)8+(1+0.1)6+(1+0.1)4+(1+0.1)2)9,000((1+0.1)810.1)=40,000(2.143589+1.771561+1.4641+1.21)9,000(2.14358910.1)=40,000(6.58925)9,000(1.1435890.1)=263,5709,000(11.43589)=240,335.7102,923.01=366,493.01

The future worth of project A is -$366,493.01.

The time period for project B should be equated with project time period C. Thus, all the cash flows are repeated for other 4 years. The time period 1 (n) is 8 years and time period 2 (n1) is 4 years.

Future value project B (FWB) can be calculated as follows:

FWB=C((1+i)n+(1+i)n1)AC((1+i)n1i)=80,000((1+0.1)8+(1+0.1)4)6,000((1+0.1)810.1)=80,000(2.143589+1.4641)6,000(2.14358910.1)=80,000(3.607689)6,000(1.1435890.1)=288,615.126,000(11.43589)=288,615.1268,615.34=357,230.46

The future worth of project B is -$357,230.46.

Future value project C (FWC) can be calculated as follows:

FWB=C(1+i)nAC((1+i)n1i)+C×0.1=130,000(1+0.1)84,000((1+0.1)810.1)+130,000×0.1=130,000(2.143589)4,000(2.14358910.1)+13,000=278,666.574,000(1.1435890.1)+13,000=278,666.574,000(11.43589)+13,000=278,666.5745,743.56+13,000=311,410.13

The future worth of project C is -$311,410.13. Since the future worth of project C is greater than the other available projects, select project C.

(b):

To determine

Compare the projects based on the present worth.

(b):

Expert Solution
Check Mark

Explanation of Solution

Present worth of project A (PWA) can be calculated as follows:

PWA=FWA(1+i)n=366,493.01(1+0.1)8=366,493.012.143589=170,971.68

Present worth of project A is -$170,971.68.

Present worth of project B (PWB) can be calculated as follows:

PWB=FWA(1+i)n=357,230.46(1+0.1)8=357,230.462.143589=166,650.63

Present worth of project B is -$166,650.63.

Present worth of project C (PWC) can be calculated as follows:

PWC=FWA(1+i)n=311,410.13(1+0.1)8=311,410.132.143589=145,275.11

Present worth of project C is -$145,275.11. Since the present worth of project C is greater than the other two projects, select project C.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
• 3 different people working at any companies under the BPO industry in the Philippines. • What are the 3 different Vision, Mission, Duties and Responsibilities and Career Path of these people in their companies under the BPO industry?
Module 6 ⚫(1902) Buckner C X | (1902) How to d x (1902) Buckner F X (1902) Productic X WP Videoplayer Canvas Login | Ir x | + Σ R mybrcc.instructure.com/courses/417310/discussion_topics/3420114?module_item_id=20155705 Spring 2025 Home Announcements Modules Syllabus Grades 8 People BRCC-_Library DLASC Module 6 Discussion - Business Costs Relaunch to update For this discussion, think about where you work or a business you have a significant amount of knowledge about. What is a common product that the business sells? What are the main costs the business has to incur in order to be able to sell that product? Which of these costs are fixed and which are variable? How much additional costs would be incurred if it were to sell one additional unit of that product (marginal cost)? Write a discussion thread about this business, the product it commonly sells, and your answers to the above questions. Also, respond to at least two threads created by your classmates. In these responses, share what…
Refer to the video to answer the following:  • what are all the key policies or all the strategies the Philippine government should prioritize to accelerate sustainable economic growth?  • these should consider the Philippines current economic challenges, including inflation, unemployment, and the need for digital transformation.   "The Philippines' Strong Economic Growth"  (YouTube link: https://youtu.be/1YtEoGp2ZeM?siJQfIv5kbu0txVsLL.)
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education