Chapter 5, Problem 21P

(a):

To determine

Compare the projects based on the present worth.

(a):

Expert Solution
Check Mark

Explanation of Solution

Table -1 shows the cash flow of different projects.

Table -1

ProjectsBC
First cost (C)203,000396,000
Operating cost (MO) per year85,000119,000
Replacement cost (O) per year5,500 
Sludge hauling cost (S) per year less 37,000
Salvage value (SV)10% at C10% at C
Time period (n)510

MARR (i) is 6%.

The time period for project B should equate with project time period C. Thus, all the cash flows are repeated for other five years. The time period (n1) is 10 years and time period 2 (n2) is five years.

The present worth of project B (PWA) can be calculated as follows:

PWB=C(MO+O)((1+i)n11i(1+i)n1)+C+(C×0.1)(1+i)n2+(C×0.1)(1+i)n1=(203,000(85,000+5,500)((1+0.06)1010.06(1+0.06)10)+203,000+(203,000×0.1)(1+0.06)5+(203,000×0.1)(1+0.06)10)=(203,000(90,500)(1.79084810.06(1.790848))+203,000+20,3001.338226+20,3001.790848)=203,000(90,500)(0.7908480.107451)136,524.03+11,335.42=203,000(90,500)(7.36008)136,524.03+11,335.42=203,000666,087.24136,524.03+11,335.42=994,275.85

The present worth of project B is -$994,275.85.

The present worth of the project C (PWC) can be calculated as follows:

PWC=C(MOS)((1+i)n1i(1+i)n)+(C×0.1)(1+i)n=(396,000(119,00037,000)((1+0.06)1010.06(1+0.06)10)+(396,000×0.1)(1+0.06)10)=(396,00082,000(1.79084810.06(1.790848))+39,6001.790848)=396,00082,000(0.7908480.107451)+22,112.43=396,00082,000(7.36008)+22,112.43=396,000603,526.56+22,112.43=977,414.13

The present worth of project C is -$977,141.13. Since the present worth of project C is greater than project B, select project C.

(b):

To determine

Compare the projects based on the present worth.

(b):

Expert Solution
Check Mark

Explanation of Solution

The time period for project B should equate with project time period C. Thus, all the cash flows are repeated for other three years. The time period (n1) is eight years and time period 2 (n2) is five years.

The present worth of the project B (PWA) can be calculated as follows:

PWB=C(MO+O)((1+i)n11i(1+i)n1)+C+(C×0.1)(1+i)n2+(C×0.1)(1+i)n1=(203,000(85,000+5,500)((1+0.06)810.06(1+0.06)8)+203,000+(203,000×0.1)(1+0.06)5+(203,000×0.1)(1+0.06)8)=(203,000(90,500)(1.59384810.06(1.593848))+203,000+20,3001.338226+20,3001.593848)=203,000(90,500)(0.5938480.095631)136,524.03+12,736.4717=203,000(90,500)(6.209786)136,524.03+12,736.4717=203,000561,985.633136,524.03+12,736.4717=888,773.25

The present worth of project B is -$888,773.2513.

Time period (n) is eight years. The present worth of the project C (PWC) can be calculated as follows:

PWC=C(MOS)((1+i)n1i(1+i)n)+(C×0.1)(1+i)n=(396,000(119,00037,000)((1+0.06)810.06(1+0.06)8)+(396,000×0.1)(1+0.06)8)=(396,00082,000(1.59384810.06(1.593848))+39,6001.593848)=396,00082,000(1.59384810.06(1.593848))+24,845.5311=396,00082,000(6.209786)+24,845.5311=396,000509,202.452+24,845.5311=880,356.92

The present worth of project C is -$880.356.92. Since the present worth of project C is greater than project B, select project C.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
QUESTION 2 2.1 [30] Mariana, a researcher at the World Health Organisation (WHO), collects information on weekly study hours (HOURS) and blood pressure level when writing a test (BLOOD) from a sample of university students across the country, before running the regression BLOOD = f(STUDY). She collects data from 5 students as listed below: X (STUDY) 2 Y (BLOOD) 4 6 8 10 141 138 133 127 123 2.1.1 By using the OLS method and the information above derive the values for parameters B1 and B2. 2.1.2 Derive the RSS (sum of squares for the residuals). 2.1.3 Hence, calculate ô 2.2 2.3 (6) (3) Further, she replicates her study and collects data from 122 students from a rival university. She derives the residuals followed by computing skewness (S) equals -1.25 and kurtosis (K) equals 8.25 for the rival university data. Conduct the Jacque-Bera test of normality at a = 0.05. (5) Upon tasked with deriving estimates of ẞ1, B2, 82 and the standard errors (SE) of ẞ1 and B₂ for the replicated data.…
If you were put in charge of ensuring that the mining industry in canada becomes more sustainable over the course of the next decade (2025-2035), how would you approach this? Come up with (at least) one resolution for each of the 4 major types of conflict: social, environmental, economic, and political
How is the mining industry related to other Canadian labour industries? Choose one other industry, (I chose Forestry)and describe how it is related to the mining industry. How do the two industries work together? Do they ever conflict, or do they work well together?
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education