Firenza Company manufactures specialty tools to customer order. Budgeted
Previously, Sanjay Bhatt, Firenza Company’s controller, had applied overhead on the basis of machine hours. Expected machine hours for the coming year are 50,000. Sanjay has been reading about activity-based costing, and he wonders whether or not it might offer some advantages to his company. He decided that appropriate drivers for overhead activities are purchase orders for purchasing, number of setups for setup cost, engineering hours for engineering cost, and machine hours for other. Budgeted amounts for these drivers are 5,000 purchase orders, 500 setups, and 2,500 engineering hours.
Sanjay has been asked to prepare bids for two jobs with the following information:
The typical bid price includes a 40 percent markup over full
Required:
- 1. Calculate a plantwide rate for Firenza Company based on machine hours. What is the bid price of each job using this rate?
- 2. Calculate activity rates for the four overhead activities. What is the bid price of each job using these rates?
- 3. Which bids are more accurate? Why?
1.
Calculate the plant wide overhead rate for F Company based on machine hours and bid price for each job using plant wide overhead rate.
Explanation of Solution
Plant wide overhead rate: Plant wide overhead rate is the rate a company uses to allocate its manufacturing overhead costs to products and cost centers.
Calculate the overhead rate:
Working note:
- a) Calculate the budgeted overhead.
Calculate the bid price for job 1 and job 2.
F company | ||
Particulars | Job 1 | Job 2 |
Direct materials | $4,500 | $9,340 |
Direct labor | 1,200 | 2,100 |
Overhead | $650 (b) | $650 (c) |
Total manufacturing cost | $6,350 | $12,090 |
Add: 40% markup | 2,540 (d) | 4,836 (e) |
Bid price | $8,890 | $16,926 |
Table (1)
Working notes:
- b) Calculate the overhead for job 1.
- c) Calculate the overhead for job 2.
- d) Calculate the 40% markup for job 1.
- e) Calculate the 40% markup for job 2.
2.
Calculate the activity rate for all the overhead activities and bid price for both jobs using activity price.
Explanation of Solution
Calculate the purchasing rate per order.
Calculate the setup cost rate per setup.
Calculate the engineering rate per engineering hour.
Calculate the other cost rate per machine hour.
Calculate the bid price for job 1 and job 2.
F company | ||
Particulars | Job 1 | Job 2 |
Direct materials | $4,500 | $9,340 |
Direct labor | $1,200 | $2,100 |
Overhead: | ||
Purchasing | 120 (f) | 160 (g) |
Setup | 225 (h) | 300 (i) |
Engineering | 810 (j) | 180 (k) |
Other | 160 (l) | 160 (m) |
Total manufacturing cost | $7,015 | $12,240 |
Add: 40% markup | 2,806 (n) | 4,896 (o) |
Bid price | $9,281 | $17,136 |
Table (2)
Working notes:
- f) Calculate the purchasing overhead for job 1.
- g) Calculate the purchasing overhead for job 2.
- h) Calculate the setup overhead for job 1.
- i) Calculate the setup overhead for job 2.
- j) Calculate the engineering overhead for job 1.
- k) Calculate the engineering overhead for job 2.
- l) Calculate the other overhead for job 1.
- m) Calculate the other overhead for job 2.
- n) Calculate the 40% markup for job 1.
- o) Calculate the 40% markup for job 2.
3.
Identify the accurate bid price and explain the reason behind it.
Explanation of Solution
Assigning the overhead using activity based approach shows the accurate cost figure because most of the overheads are non-unit level and there is a variety of products.
Want to see more full solutions like this?
Chapter 5 Solutions
EBK CORNERSTONES OF COST MANAGEMENT
- The industrial enterprise "HUANG S.A." purchased a sorting and packaging machine from a foreign company on 1/4/2017 at a cost of €500,000. The useful life of the machine was estimated by the Management at ten (10) years, while the residual value was estimated at zero. For the transportation of the machine from abroad to the company's factory, the amount of €20,000 was paid on 15/4/2017. As the insurance coverage of the machine during transportation was the responsibility of the selling company, HUANG S.A. proceeded to insure the machine from 16/4/2017 to 15/4/2018, paying the amount of €1,200. The delivery took place on 15/4/2017. As adequate ventilation of the multifunction device is essential for its proper operation, the company fitted an air duct on the multifunction device. The cost of the air duct amounted to €2,000 and was paid on 20/4/2017. On 25/4/2017, an external electrician was paid €5,000 for the electrical connection of the device. The company also paid €5,000 to an…arrow_forwardI need answer typing clear urjent no chatgpt used pls i will give 5 Upvotes.only typing .arrow_forwardCash flow cyclearrow_forward
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
- Excel Applications for Accounting PrinciplesAccountingISBN:9781111581565Author:Gaylord N. SmithPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College