Principles of Corporate Finance (Mcgraw-hill/Irwin Series in Finance, Insurance, and Real Estate)
12th Edition
ISBN: 9781259144387
Author: Richard A Brealey, Stewart C Myers, Franklin Allen
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 5, Problem 11PS
- a. Calculate the NPV of each project for discount rates of 0%, 10%, and 20%. Plot these on a graph with NPV on the vertical axis and discount rate on the horizontal axis.
- b. What is the approximate IRR for each project?
- c. In what circumstances should the company accept project A?
- d. Calculate the NPV of the incremental investment (B – A) for discount rates of 0%, 10%, and 20%. Plot these on your graph. Show that the circumstances in which you would accept A are also those in which the IRR on the incremental investment is less than the
opportunity cost of capital.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Project Analysis. Assume that you are evaluating the following three mutually exclusive projects: A. Complete the following analyses. (For the last two lines, Terminal Value, please write in the dollar amount of the terminal value.) B. Compare and explain the conflicting rankings of the NPVs and TRRs versus the IRRs. C. Using different discount rates, is it possible to get different rankings within the NPV calculation? Why or why not? D. If 10 percent is the required return, which project is preferred? E. Which is the fairer representation of these two projects, TRR or IRR? Why?
a. Calculate the projects’ NPVs, IRRs, MIRRs, regular paybacks, and discounted paybacks.b. If the two projects are independent, which project(s) should be chosen?c. If the two projects are mutually exclusive and the WACC is 10%, which project(s)should be chosen?d. Plot NPV profiles for the two projects. Identify the projects’ IRRs on the graph.e. If the WACC was 5%, would this change your recommendation if the projects weremutually exclusive? If the WACC was 15%, would this change your recommendation?Explain your answers.f. The crossover rate is 13.5252%. Explain what this rate is and how it affects the choicebetween mutually exclusive projects.g. Is it possible for conflicts to exist between the NPV and the IRR when independentprojects are being evaluated? Explain your answer.h. Now look at the regular and discounted paybacks. Which project looks better whenjudged by the paybacks?i. If the payback was the only method a firm used to accept or reject projects, what paybackshould it…
QUESTION 5
Invest in any or all of the four projects whose relevant cash flows are given in the following table.
The firm has RM7,000,000 budgeted to fund these projects, all of which are known to be
acceptable. Initial investment for each project is the same for all projects which is RM1,600,000.
The rate of return for all projects is equivalent to 8%.
Operating cash outflow
Project X
Year 1
Project Y
Cash Outflow
RM1,600,000 (for each project)
Operating Cash Inflows
RM
440,000
RM
140,000
1
340,000
220,000
(110,000)
( 95,000 )
105,000
220,000
388,000
180,000
250,000
260,000
370,000
460,000
3.
4.
5.
6.
7.
8.
9.
Use this table for PROJECT X and Y
Period
PVIF 8%
1
0.9259
2
0.8573
3
0.7938
4
0.7350
0.6806
6
0.6302
7
0.5835
8
0.5403
9
0.5002
10
0.4632
8
Chapter 5 Solutions
Principles of Corporate Finance (Mcgraw-hill/Irwin Series in Finance, Insurance, and Real Estate)
Ch. 5 - (IRR) Check the IRRs for project F in Section 5-3.Ch. 5 - (IRR) What is the IRR of a project with the...Ch. 5 - (XIRR) What is the IRR of a project with the...Ch. 5 - Payback a. What is the payback period on each of...Ch. 5 - IRR Write down the equation defining a projects...Ch. 5 - Prob. 3PSCh. 5 - IRR rule You have the chance to participate in a...Ch. 5 - IRR rule Consider a project with the following...Ch. 5 - IRR rule Consider projects Alpha and Beta: The...Ch. 5 - Capital rationing Suppose you have the following...
Ch. 5 - Payback Consider the following projects: a. If the...Ch. 5 - Prob. 9PSCh. 5 - IRR Calculate the IRR (or IRRs) for the following...Ch. 5 - IRR rule Consider the following two mutually...Ch. 5 - IRR rule Mr. Cyrus Clops, the president of Giant...Ch. 5 - Prob. 13PSCh. 5 - Profitability index Look again at projects D and E...Ch. 5 - Prob. 15PSCh. 5 - Prob. 16PS
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- Suppose the net present values of projects A and B show a distribution as follows. a) Compare the projects by expected value criteria?b) Compare the projects by standard deviation criteria?c) Evaluate A and B projects according to the coefficient of variation criterion?Calculate on paper.arrow_forwarda. They payback period of project A is ___ years (round to two decimal places) The payback period of project B is ____ years. (round to two decimal places) According to the payback method, which project should the firm choose? b. The NPV of project A is $___ The NPV of project B is $___ c. The IRR of project A is ___ The IRR of project B is ___ d. Make a reccomendationarrow_forwardConsider the following sets of investment projects: (a) Classify each project as either simple or nonsimple.(b) Compute the i* for Project A, using the quadratic equation.(c) Obtain the rate(s) of return for each project by plotting the PW as a function of interest rate.arrow_forward
- Which of the following statement is correct Select one: a. A project is accepted when profitability index will be greater than one b. All statements are correct c. A project is accepted when net present value is greater than zero d. A project is accepted when payback period is less than the other projectarrow_forward3) could you use the Figure below that shows the net present value profile of two projects Y and W to answer the following questions: What is the internal rate of return on project Y? Determine the “approximate” discount rate at which you would be indifferent between the two projects Find the “approximate” net present value of project W when the discount rate is 4%.arrow_forwardWhich of the following statements is correct? A. If the NPV of a project is greater than 0, its PI will equal 0. B. If the IRR of a project is 0%, its NPV, using a discount rate, k, greater than 0, will be 0. C. If the PI of a project is less than 1, its NPV should be less than 0. D. Nonearrow_forward
- Use these data to compute for each (a) the NPV at discount rates of 10 and 5 percent, (b) the BCR at the same rates, and (c) the internal rate of return for each. Describe the facts about the projects that would dictate which criterion is appropriate, and indicate which project is preferable under each circumstance.arrow_forwardis this accuratearrow_forwardConsider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Discount Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow Rate A - 100 40 50 60 N/A 0.18 B - 73 30 30 30 30 0.18 Assume that projects A and B are mutually exclusive. The correct investment decision and the best rationale for that decision is to A. invest in project B, since NPV, > NPV, A B. invest in project A, since NPV, > 0. OC. invest in project A, since NPV, IRR, A'arrow_forward
- Choices for last three requirements 3. What is the approximate IRR of Project A? a. 28% b. 18% c. 24% d. 21% 4. What is the approximate IRR of Project B? a. 17% b. 14% c. 20% d. 22% 5. if the crossover rate is exactly 9.31% which of the following discount rate would have a conflict in the decision making (between NPV and IRR) assuming the projects are mutually exclusive? a. 7% b. 11%arrow_forwardA project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's IRR undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the IRR cash flows (Project Delta). A steep (where NPV = 0). The Y-axis intersection point represents the project's of the differences in the projects' NPV profile indicates that increases in the cost of capital lead to large declines in NPV. If a project has most of its cash flows coming in later years, its NPV will decline v sharply if the cost of capital increases; but a project whose cash flows come earlier will not be severely penalized by high capital costs. The significance of the crossover rate is that at any cost of capital [greater less than the crossover rate, the NPV and IRR methods will provide the same conclusion for evaluating mutually exclusive projects. However, at any cost of capital than the crossover…arrow_forwardProfitability index. Given the discount rate and the future cash flow of each project listed in the following table, , use the PI to determine which projects the company should accept. ..... What is the Pl of project A? (Round to two decimal places.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License